Meluha
Deedo IDDP-MSB-ZMK2It is due for completion in Dec 2030, with no extension on record; no MahaRERA orders on record; 35% of its units are booked.
Dindoshi, Mumbai Suburban 400097 · by Saptrishi Urban Space Private Limited
Buying a flat here?
See every deed registered on it.
It is due for completion in Dec 2030, with no extension on record
- This projectRegistered 1 Nov 2023, completion promised 31 Dec 2030.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
2 buildings
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page. Construction % is the average of the developer's own declared activity progress to MahaRERA, not an inspection.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51800053441
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51800053441 | 1 Nov 2023 | 31 Dec 2030 | — | Saptrishi Urban Space Private Limited | Project page |
Documents117
65 documents held by Deedo, 52 filings listed on MahaRERA's project page
Commencement certificate (2)
Allotment letter (3)
Show all 117 documentsShow fewer documents
Other (35)
- Other31 Jul 2023ViewSource
- Other4 Sep 2023ViewSource
- Other21 Sep 2023ViewSource
- Other25 Sep 2023ViewSource
- Other29 Sep 2023ViewSource
- Other19 Oct 2023ViewSource
- Other16 Dec 2024ViewSource
- Other30 Dec 2025ViewSource
- Other30 Dec 2025ViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
- OtherDate not statedViewSource
Encumbrance details (3)
Form 1 (7)
Form 2 (7)
Document library
- Commencement Certificates / NA Order for plotted developmentPLINTH_firstcc_signed.pdf · uploaded 26 Jun 2023View
- Copy of Layout Approval (in case of layout)IOA_plan_compressed.pdf · uploaded 27 Jun 2023View
- Building Plan Approval / NA Order for plotted developmentIOA_plan_compressed.pdf · uploaded 27 Jun 2023View
- Declaration in FORM BForm B CR.pdf · uploaded 19 Jul 2023View
- Declaration in FORM BSociety Form B.pdf · uploaded 19 Jul 2023View
- Deviation Report with respect to Allotment letterAllotment Letter deviation.pdf · uploaded 19 Jul 2023View
- Disclosure of sold/ booked inventoryInventory details sold unsold.pdf · uploaded 19 Jul 2023View
- Declaration about Commencement CertificateDeclaration about CC.pdf · uploaded 31 Jul 2023View
- Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest in other real estate organization.pdf · uploaded 31 Jul 2023View
- Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDeclaration of Separate Bank account - V1.pdf · uploaded 8 Aug 2023View
- Other – Legalsaptrishi urban space llp_CS letterhead.pdf · uploaded 29 Aug 2023View
- Other – TechnicalPlot Area Declaration - New.pdf · uploaded 4 Sep 2023View
- CERSAI detailsCERSAI New.pdf · uploaded 21 Sep 2023View
- Disclosure of Interest in Other Real Estate OrganizationsAmit Sir Disclosure.pdf · uploaded 25 Sep 2023View
- a Details of encumbrances concerned to FinanceFinancial Encumbrances updated.pdf · uploaded 26 Sep 2023View
- b Details of encumbrances concerned to LegalFinancial Encumbrances updated.pdf · uploaded 26 Sep 2023View
- Proforma of Agreement for saleUpdated AFS after scrutiny29092023.pdf · uploaded 29 Sep 2023View
- Proforma of Allotment letterA3-Allotment letter final after RERA Scrutiny290923.pdf · uploaded 29 Sep 2023View
- Copy of the legal title reportLegal Title Report - 09102023_compressed.pdf · uploaded 9 Oct 2023View
- a Details of encumbrances concerned to FinanceDeclaration concerned to Legal1910.pdf · uploaded 19 Oct 2023View
- b Details of encumbrances concerned to LegalDeclaration concerned to Legal1910.pdf · uploaded 19 Oct 2023View
- Deviation Report with respect to model copy of AgreementAFS Deviation 1910.pdf · uploaded 19 Oct 2023View
- Status of ConveyancePlot Area Declaration - New (1).pdf · uploaded 19 Oct 2023View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Arch Melhua Dec 23.pdf · uploaded 14 Jun 2024View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Arch Melhua March 24.pdf · uploaded 14 Jun 2024View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Eng Melhua Dec 23.pdf · uploaded 14 Jun 2024View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Eng Melhua March 24.pdf · uploaded 14 Jun 2024View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)Melhua RERA 2 Eng Cert 2023 June 2024.pdf · uploaded 22 Jul 2024View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Arch Melhua June 2024.pdf · uploaded 30 Jul 2024View
- Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Form 2A Eng Quality March 2023.pdf · uploaded 30 Jul 2024View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)RERA Meluha Eng Form 2 30Sept24.pdf · uploaded 15 Nov 2024View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)Meluha Architect certificate 30092024.pdf · uploaded 6 Dec 2024View
- Deviation Report with respect to Allotment letterMeluha Deviation Report Allotment 101224.pdf · uploaded 16 Dec 2024View
- Deviation Report with respect to model copy of AgreementMeluha Deviation Report Agreement 101224.pdf · uploaded 16 Dec 2024View
- Engineer’s Certificate on Cost Incurred on Project (Form 2)Meluha Eng Cert Dec 2024 Form 2.pdf · uploaded 15 Apr 2025View
- Architect’s Certificate of Percentage of Completion of Work (Form 1)Meluha Arch Cert Dec 2024 Form 1.pdf · uploaded 15 Apr 2025View
- Form 1Form 1 - Meluha as on June 2025.pdf · uploaded 30 Dec 2025View
- Form 2Form 2 - Meluha as on June 2025.pdf · uploaded 30 Dec 2025View
- Disclosure of Sold and Booked InventoryCircular 29 - Meluha as on June 2025 (revised).pdf · uploaded 30 Dec 2025View
- Form 1Form 1 - Meluha as on Sept 2025.pdf · uploaded 30 Dec 2025View
- Form 2Form 2 - Meluha as on Sept 2025.pdf · uploaded 30 Dec 2025View
- Disclosure of Sold and Booked InventoryCircular 29 - Meluha as on Sept 2025 (revised).pdf · uploaded 30 Dec 2025View
- Form 5 (FY 2023-2024)Form 5 2023 to 2024.pdf · uploaded 30 Jul 2026View
- Form 5 (FY 2024-2025)Form 5 2024 to 2025.pdf · uploaded 30 Jul 2026View
Promoter documents
Technical documents
Other legal documents
- Other – Legalsaptrishi urban space llp_CS letterhead.pdfView
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 104J · MHADA
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Active
- Address
- 104j, Shivdham Complex, Malad EastPIN 400097
- Village
- Dindoshi, Borivali taluka
- Location
- 19.17594, 72.86226
- Land area for this project
- 2,387 sq m (25,693 sq ft)
- Permissible built-up area
- 18,295 sq m (1,96,926 sq ft)
- Sanctioned built-up area
- 0 sq m (0 sq ft)
- Recreational open space
- 698 sq m (7,513 sq ft)
- Planning authority
- MHADA
- Designated bank account
- Hdfc Bank
- Litigation declared by promoter
- Yes
- Financial encumbrance declared
- None declared
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
104J
Boundaries
- North
- Cts 104b
- South
- Sanket Chs Cts No 104a Cts No 147
- East
- MHADA Ndr Plot Cts No 147
- West
- School Cts No 104a Cts No 104f
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking0 parking spaces
0 units registered
Parking
| Type | Two-wheeler | Four-wheeler | Bus | Visitor | Total |
|---|---|---|---|---|---|
| Closed/Covered | 0 | 0 | 0 | 0 | 0 |
| Open Space | 0 | 0 | 0 | 0 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Construction progress2 buildings and areas
Work completed, as the promoter reported it to MahaRERA (Form 1)
Meluha
Show all 11 activitiesShow fewer activities
Common areas and amenities
Show all 17 activitiesShow fewer activities
Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Tushar Bhor | — |
| Chartered accountant | MRB And Associates | — |
| Chartered accountant | Neelesh Jain and Associates | — |
| Engineer | Rohit Gaur | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Dindoshi
- Je And Vee ShraddhaRERA PM1180002602574
- Sheetal SangamRERA PR1180002601910
- Jeandveesaidham - A WingRERA P51800080568
- Pearl IconRERA P51800079553
- Agarwal Floresta - JavaRERA P51800078684
- Crescent Western Trade Center - GoregaonRERA P51800077923
- Blue ZoneRERA P51800077817
- Sayba Signature SpacesRERA P51800056477
All 16 projects in Dindoshi · Compare Meluha with another project