Skip to content
Residential / Group Housing · 1 building · 23 unitsRERA P51900028809

Ali Tower

Deedo IDDP-MUM-054A

Completion was pushed back 4 months to Sep 2026, and that date has passed too; no MahaRERA orders on record; 83% of its units are booked.

Ward Abcd, Maharashtra 400003 · by Alamdar Infrastructure Pvt Ltd

Delivery6 mo latePromised May 2026 · revised Sep 2026 · that date has passed tooRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales83% booked19 of 23 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months to Sep 2026, and that date has passed too

  • This projectRegistered 30 Mar 2021, completion promised 7 May 2026, revised to 7 Sep 2026, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51900028809
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5190002880930 Mar 20217 May 20267 Sep 2026Alamdar Infrastructure Pvt LtdProject page
Documents57

1 document held by Deedo, 56 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPan card of Alamdar.PDF · uploaded 24 Jan 2023Source

Legal

  • Legal Title reportNew Title Certificate_compressed.pdf · uploaded 2 Mar 2021Source
  • Declaration Form BAffidavit cum declaration compressed.pdf · uploaded 2 Mar 2021Source
  • Legal Title reportTitle certificate 16062021.pdf · uploaded 21 Jun 2021Source

Migrated

  • 1 Copy of the legal title reportNew Title Certificate_compressed.pdf · uploaded 2 Mar 2021Source
  • 1 Details of encumbrancesno encumbrance.pdf · uploaded 2 Mar 2021Source
  • 1 Copy of Layout Approval (in case of layout)Amend letter issue.pdf · uploaded 2 Mar 2021Source
Show all 57 documentsShow fewer documents

Migrated

  • 1 Building Plan Approval / NA Order for plotted developmentPlan frm Grd to 21st Floor.pdf · uploaded 2 Mar 2021Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC kudrati New Changes.pdf · uploaded 2 Mar 2021Source
  • 1 Declaration in FORM BAffidavit cum declaration compressed.pdf · uploaded 2 Mar 2021Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architects_Certificate-Ali_Tower.pdf · uploaded 2 Mar 2021Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form_No_2___2A_Engineer_Certificate_for_Rera_submission-converted__2___1_.pdf · uploaded 2 Mar 2021Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA_certificate_-Ali_tower.pdf · uploaded 2 Mar 2021Source
  • 1 Proforma of Allotment letterallotment and sale agreement.pdf · uploaded 2 Mar 2021Source
  • 2 Copy of the legal title reportTitle certificate 16062021.pdf · uploaded 21 Jun 2021Source
  • 1 Declaration about Commencement CertificateDeclaration about CC.pdf · uploaded 21 Jun 2021Source
  • 2 Commencement Certificates / NA Order for plotted developmentFurtherCC.pdf · uploaded 5 Jul 2021Source
  • 3 Commencement Certificates / NA Order for plotted development2322606_FurtherCC_signed.pdf · uploaded 27 Apr 2022Source
  • 4 Commencement Certificates / NA Order for plotted developmentFull CC 18072022.pdf · uploaded 26 Jul 2022Source
  • 1 PAN CardPan card of Alamdar.PDF · uploaded 24 Jan 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect_Certificate-30-6-2022.pdf · uploaded 16 Feb 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect_Certificate-30-9-2022.pdf · uploaded 16 Feb 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect_Certificate-31-12-2021.pdf · uploaded 16 Feb 2023Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect_Certificate-31-12-2022.pdf · uploaded 16 Feb 2023Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect_Certificate-31-03-2022.pdf · uploaded 16 Feb 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer_certificate_form_2-Ali_Tower_21-12-2021.pdf · uploaded 16 Feb 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer_certificate_form_2-Ali_Tower_31-03-2022.pdf · uploaded 16 Feb 2023Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer_certificate_form_2-Ali_Tower_30-06-2022.pdf · uploaded 16 Feb 2023Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer_certificate_form_2-Ali_Tower_30-09-2022.pdf · uploaded 16 Feb 2023Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer_certificate_form_2-Ali_Tower_31-12-2022.pdf · uploaded 16 Feb 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA_CERTIFICATE_Form_3 21-12-21.pdf · uploaded 16 Feb 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA_CERTIFICATE_Form_3-31-03-2022.pdf · uploaded 16 Feb 2023Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA_CERTIFICATE_Form_3_30-06-2022.pdf · uploaded 16 Feb 2023Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Architect Certificate -30-9-2022.pdf · uploaded 16 Feb 2023Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA_CERTIFICATE_Form_3-30-09-2022.pdf · uploaded 16 Feb 2023Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA_CERTIFICATE_Form_3-31-12-2022.pdf · uploaded 16 Feb 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)FY_21-22_FOrm_5.pdf · uploaded 16 Feb 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FY_21-22_FOrm_5.pdf · uploaded 16 Feb 2023Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect_Certificate 31-03-2023.PDF · uploaded 30 May 2023Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer_Certificate 31-03-2023.PDF · uploaded 30 May 2023Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA_Certificate 31-03-2023.PDF · uploaded 30 May 2023Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect_Certificate_ALI_TOWER_June-23.PDF · uploaded 31 Aug 2023Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer_Certificate_ALI_TOWER__June-23.PDF · uploaded 31 Aug 2023Source
  • 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA_Certificate_of_Ali_Tower 30-06-2023.PDF · uploaded 31 Aug 2023Source
  • 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA_Certificate -30-09-2023.PDF · uploaded 12 Dec 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5-FY 2022-23 Ali tower.PDF · uploaded 7 Mar 2024Source
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect_Certificate-31-12-2023.PDF · uploaded 8 Mar 2024Source
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer_Certificate -31-12-2023.PDF · uploaded 8 Mar 2024Source
  • 11 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA_Certificate-31-12-2023.PDF · uploaded 8 Mar 2024Source
  • 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer_Certifcate-31-3-2024.PDF · uploaded 2 Jul 2024Source
  • 12 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA_Certificate Form 3-31-03-2024.PDF · uploaded 2 Jul 2024Source
  • Form 5 (FY 2023-2024)Form-5 Ali Tower FY 23-24.pdf · uploaded 11 Sep 2026Source

Technical

  • DocumentAmend letter issue.pdf · uploaded 2 Mar 2021Source
  • DocumentPlan frm Grd to 21st Floor.pdf · uploaded 2 Mar 2021Source

Technical (Architect)

  • DocumentArchitect Certificate 01032024.pdf · uploaded 18 Nov 2025Source

Technical (Engineer)

  • DocumentEngineer_Certifcate-31-3-2024.PDF · uploaded 2 Jul 2024Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 3678

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK23 units in all
Address
3678, Mutton Street And Gujjar Street, Bhendi BazarPIN 400003
Land area for this project
293 sq m (3,159 sq ft)
Permissible built-up area
3,212 sq m (34,574 sq ft)
Sanctioned built-up area
2,379 sq m (25,610 sq ft)
Recreational open space
1 sq m (11 sq ft)
Designated bank account
220
Developed in phases
No

Survey, CTS, gat or plot numbers

3678

Land as published on MahaRERA's project page

3678

Boundaries

North
Habib Building
South
Gujjar Street
East
Mutton Street
West
Sweeper Passage

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking23 units

19 of 23 units booked (83%), as the promoter reported to MahaRERA

1BHK · 22 units2BHK · 1 unit
TypeCarpet areaUnitsBooked
1BHK37.09 sq m · 399 sq ft43
1BHK37.91 sq m · 408 sq ft109
1BHK38.53 sq m · 415 sq ft87
2BHK56.04 sq m · 603 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectSamoon & Associates—
Chartered accountantAbuali Darukhanawala—
Chartered accountantZ A Bootwala And Company—
EngineerMustansir A Rangwala—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Ward Abcd

All 156 projects in Ward Abcd · Compare Ali Tower with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology