Alamdar Infrastructure Pvt Ltd
Deedo IDDD-5583Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 4 mo late.
Delivery record
3 of 4 registrations with dates moved or missed their RERA date · months late against the original promise
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Marine PalaceP51900002919 | Ward Abcd | Certificate Signed | 7 Nov 2026 | 7 Nov 2026 | On date |
| Ali TowerP51900028809 | Ward Abcd | Certificate Signed | 7 May 2026 | 7 Sep 2026 | +6 mo* |
| The AuroP51900033823 | Ward Gsouth | Certificate Signed | 7 Nov 2027 | 7 Mar 2028 | +4 mo |
| Mufaddal ParkP51900049088 | Mazgaon | Certificate Signed | 7 Nov 2029 | 7 Mar 2030 | +4 mo |
Alamdar Infrastructure Pvt Ltd, in questions
Does Alamdar Infrastructure Pvt Ltd finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.
How many projects has Alamdar Infrastructure Pvt Ltd registered with MahaRERA?
4 projects under 4 MahaRERA registrations; 1 completed on MahaRERA.
Does Alamdar Infrastructure Pvt Ltd have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.