Skip to content
Company or firm · first RERA registration 2017

Alamdar Infrastructure Pvt Ltd

Deedo IDDD-5583

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 4 mo late.

Projects44 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay4 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

3 of 4 registrations with dates moved or missed their RERA date · months late against the original promise

4 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Marine PalaceP51900002919Ward AbcdCertificate Signed7 Nov 20267 Nov 2026On date
Ali TowerP51900028809Ward AbcdCertificate Signed7 May 20267 Sep 2026+6 mo*
The AuroP51900033823Ward GsouthCertificate Signed7 Nov 20277 Mar 2028+4 mo
Mufaddal ParkP51900049088MazgaonCertificate Signed7 Nov 20297 Mar 2030+4 mo

Alamdar Infrastructure Pvt Ltd, in questions

Does Alamdar Infrastructure Pvt Ltd finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.

How many projects has Alamdar Infrastructure Pvt Ltd registered with MahaRERA?

4 projects under 4 MahaRERA registrations; 1 completed on MahaRERA.

Does Alamdar Infrastructure Pvt Ltd have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology