Hatkanangle, Kolhapur
Deedo IDDL-KOL-HATKANANGLE4 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects97
Registrations97
Completion still due2854 past their date
Median extension4 months39% of registrations extended
Regulatory cases4on 4 projects
8 in 10 registrations run late here
97 MahaRERA registrations in Hatkanangle and the places within it
7 not yet due21 extended, not yet due54 past even the latest date15 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Hatkanangle
97 projects registered with MahaRERA in this taluka and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Nakshtra BungalowsShree Construction & Developers | 8 yrs 2 mo late | — | 80% |
| VasantRekha HeightsSurabhi Developers | 7 yrs 5 mo late | — | 25% |
| Century PlazaSurabhi Developers | 7 yrs 3 mo late | — | 61% |
| Laxminarayan ApartmentMayur Vilas Shah Huf | 8 yrs late | — | 39% |
| Vrushab ResidencyPadmavati Developers | 2 yrs late | — | 0% |
| Urban Life Phase II Building CAtharv Estates India Private Limited | 8 yrs 3 mo late | — | 17% |
| Runwal TowerVision Infra Developers | 6 yrs 10 mo late | — | 77% |
| Aslam And Faruk Mujawar | No date on record | — | — |
| Gaiban Residency | No date on record | — | — |
| Gat Mala | No date on record | — | — |
| Golden Heritage | No date on record | — | — |
| Harsh | No date on record | — | — |
| Nirman Suyash | No date on record | — | — |
| Ossiya Construction | No date on record | — | — |
| Pr1150002502928 | No date on record | — | — |
| Premkamal | No date on record | — | — |
| Rajkumar Annu Awate | No date on record | — | — |
| Saraswati Galaxy | No date on record | — | — |
| Shree Aniruddha Developers | No date on record | — | — |
| Shreejans Vishnu Plaza | No date on record | — | — |
| Shrikrushna Residency | No date on record | — | — |
| Tara Complex | No date on record | — | — |
Nearby: other talukas in Kolhapur
Most active promoters
- Shree Construction & Developers3 projects
- Fortune Developers2 projects
- Mahalaxmi Developers2 projects
- Shaheen Mansoor Bijali2 projects
- Sidra Developers2 projects
- Surabhi Developers2 projects
- Todkar Builders2 projects
- Vijay Virupaksha Galgale2 projects
- Abhijeet Hambirrao Kharade1 project
- Aditya Bhimrao Kolawale1 project
Data through22 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology