Completion was pushed back 4 years to Dec 2023, and that date has passed too; no MahaRERA orders on record; 77% of its units are booked.
Ichalkaranji (M Cl), Kolhapur 416115 · Promoter: Vision Infra Developers
Completion was pushed back 4 years to Dec 2023, and that date has passed too
- This projectRegistered 5 Jul 2017, completion promised 31 Dec 2019, revised to 31 Dec 2023, and still not shown completed today.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP53000000151
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P53000000151 | 5 Jul 2017 | 31 Dec 2019 | 31 Dec 2023 | Vision Infra Developers | Project page |
Documents76
2 documents held by Deedo, 74 filings listed on MahaRERA's project page
Finance
- PAN CardPAN.pdf · uploaded 30 Jun 2017Source
Legal
- Legal Title reportSearch report RT.pdf · uploaded 30 Jun 2017Source
- Declaration Form BForm B RT.pdf · uploaded 30 Jun 2017Source
- OtherStructural Certificate.pdf · uploaded 11 Sep 2020Source
- OtherDeemed OC Letter 01102020.pdf · uploaded 21 Oct 2020Source
- Declaration Form BForm B 14062023.pdf · uploaded 14 Jun 2023Source
Show all 76 documentsShow fewer documents
Migrated
- 1 Commencement Certificates / NA Order for plotted developmentBuilding Permission.pdf · uploaded 28 Jun 2017Source
- 1 PAN CardPAN.pdf · uploaded 30 Jun 2017Source
- 1 Copy of the legal title reportSearch report RT.pdf · uploaded 30 Jun 2017Source
- 1 Details of encumbrances7 12 Uttara.pdf · uploaded 30 Jun 2017Source
- 2 Commencement Certificates / NA Order for plotted developmentPlinth Certificate.pdf · uploaded 30 Jun 2017Source
- 1 Declaration in FORM BForm B RT.pdf · uploaded 30 Jun 2017Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 Signed.pdf · uploaded 30 Jun 2017Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 Engineers Certificate RT.pdf · uploaded 30 Jun 2017Source
- 1 Certificates of CA (Form 3)Form 3 Signed.pdf · uploaded 30 Jun 2017Source
- 1 Proforma of Allotment letterRERA Allotment Letter and AFS to be uploaded.pdf · uploaded 30 Jun 2017Source
- 1 Copy of Layout Approval (in case of layout)2.pdf · uploaded 1 Jul 2017Source
- 2 Copy of Layout Approval (in case of layout)1.pdf · uploaded 1 Jul 2017Source
- 3 Copy of Layout Approval (in case of layout)3.pdf · uploaded 1 Jul 2017Source
- 1 Building Plan Approval (IOD)1.pdf · uploaded 1 Jul 2017Source
- 2 Building Plan Approval (IOD)2.pdf · uploaded 1 Jul 2017Source
- 3 Building Plan Approval (IOD)3.pdf · uploaded 1 Jul 2017Source
- 2 Details of encumbrancesIndex 2 Reconveyance Deed 15022018.pdf · uploaded 24 Feb 2018Source
- 3 Details of encumbrancesIndex 2 Reconveyance Deed 15022018.pdf · uploaded 14 Mar 2018Source
- 4 Copy of Layout Approval (in case of layout)Plan Page 1.pdf · uploaded 14 Mar 2018Source
- 5 Copy of Layout Approval (in case of layout)Plan Page 2.pdf · uploaded 14 Mar 2018Source
- 6 Copy of Layout Approval (in case of layout)Plan Page 3.pdf · uploaded 14 Mar 2018Source
- 3 Commencement Certificates / NA Order for plotted developmentBuilding Permission 2018.pdf · uploaded 14 Mar 2018Source
- 2 Proforma of Allotment letterAgreement for Sale RERA RT.pdf · uploaded 14 Mar 2018Source
- 3 Proforma of Allotment letterAllotment Letter RERA.pdf · uploaded 14 Mar 2018Source
- 1 Certificates of CA (Form 5)Form 5 Runwal Tower.pdf · uploaded 30 Nov 2018Source
- 7 Copy of Layout Approval (in case of layout)1.pdf · uploaded 18 Feb 2019Source
- 8 Copy of Layout Approval (in case of layout)2.pdf · uploaded 18 Feb 2019Source
- 9 Copy of Layout Approval (in case of layout)3.pdf · uploaded 18 Feb 2019Source
- 4 Commencement Certificates / NA Order for plotted developmentUntitled1.pdf · uploaded 18 Feb 2019Source
- 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 Engineers Certificate RT.pdf · uploaded 15 Nov 2019Source
- 2 Certificates of CA (Form 3)Form 3.pdf · uploaded 21 Nov 2019Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1.pdf · uploaded 23 Nov 2019Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Form 2A decleration.pdf · uploaded 12 Dec 2019Source
- 2 Certificates of CA (Form 5)Form 5 Runwal Tower FY 17-18.pdf · uploaded 12 Dec 2019Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Form 5.pdf · uploaded 12 Dec 2019Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentrunwal completion_1.pdf · uploaded 7 Apr 2020Source
- 1 OtherStructural Certificate.pdf · uploaded 11 Sep 2020Source
- 2 OtherDeemed OC Letter 01102020.pdf · uploaded 21 Oct 2020Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Annual Report and Computation of Income.pdf · uploaded 29 Dec 2021Source
- 3 Certificates of CA (Form 3)Form 3.pdf · uploaded 5 May 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5.pdf · uploaded 5 May 2023Source
- 1 Disclosure of sold/ booked inventoryStatement of Inventory 01052023.pdf · uploaded 11 May 2023Source
- 1 Declaration about Commencement CertificateDeclaration for Commencement.pdf · uploaded 30 May 2023Source
- 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 27052023.pdf · uploaded 30 May 2023Source
- 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 27052023.pdf · uploaded 30 May 2023Source
- 2 Declaration in FORM BForm B 14062023.pdf · uploaded 14 Jun 2023Source
- 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 27052023.pdf · uploaded 25 Jul 2023Source
- 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 27052023.pdf · uploaded 25 Jul 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A.pdf · uploaded 25 Jul 2023Source
- 4 Certificates of CA (Form 3)Form 3 Certified_compressed.pdf · uploaded 25 Jul 2023Source
- 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOccupancy Certifcate Ver 2.pdf · uploaded 8 Sep 2023Source
- 2 Architect’s Certificate on Completion of Project (Form 4)Form 4.pdf · uploaded 8 Sep 2023Source
- 1 Status of Formation of Legal Entity (Society/Co Op etc.)Deed of Declaration Scan.pdf · uploaded 11 Nov 2023Source
- 1 Status of ConveyanceDeed of Declaration Scan.pdf · uploaded 11 Nov 2023Source
Technical
- Document2.pdf · uploaded 1 Jul 2017Source
- Document3.pdf · uploaded 1 Jul 2017Source
- Document2.pdf · uploaded 1 Jul 2017Source
- Document1.pdf · uploaded 1 Jul 2017Source
- Document3.pdf · uploaded 1 Jul 2017Source
- Document1.pdf · uploaded 1 Jul 2017Source
- DocumentPlan Page 1.pdf · uploaded 14 Mar 2018Source
- DocumentPlan Page 2.pdf · uploaded 14 Mar 2018Source
- DocumentPlan Page 3.pdf · uploaded 14 Mar 2018Source
- Document1.pdf · uploaded 18 Feb 2019Source
- Document2.pdf · uploaded 18 Feb 2019Source
- Document3.pdf · uploaded 18 Feb 2019Source
Technical (Architect)
- DocumentForm 1 27052023.pdf · uploaded 25 Jul 2023Source
Technical (Engineer)
- DocumentForm 2 27052023.pdf · uploaded 25 Jul 2023Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvals9225B
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- G1, G10g11, G12, G13, G14, G15, G16toG24, G2, G3, G4, G5, G6, G7, G8, G9, Hotel, Office F1, Office F10 F12, Office F11 F13, Office F14 F17 F19, Office F15, Office F16, Office F18 F20, Office F2, Office F3, Office F4, Office F5 F6, Office F7 F9, Office F8, Ub01, Ub02, Ub03, Ub04, Ub05, Ub06, Ub07, Ub08, Ub09, Ub10, Ub11, Ub12 and ub14, Ub13 and ub15, Ub16, Ub17 and ub18, Ub19, Ub20, Ub21, Ub22, Ub23, Ub24, Ub25, Ub2652 units in all
- Address
- 9225-B, RB Road, Daate MalaPIN 416115
- Village
- Ichalkaranji (M Cl), Hatkanangle taluka
- Location
- 16.70499, 74.24325
- Designated bank account
- 197
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- Property of CS No 9250-A 9250-4A and 9249
- South
- Government Road
- East
- Government Road
- West
- Government Road and Property of CSNO 92250-3A
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking52 units
40 of 52 units booked (77%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| G1 | 29.65 sq m · 319 sq ft | 1 | 1 |
| G10g11 | 63 sq m · 678 sq ft | 1 | 1 |
| G12 | 28.06 sq m · 302 sq ft | 1 | 1 |
| G13 | 31.59 sq m · 340 sq ft | 1 | 1 |
| G14 | 26.02 sq m · 280 sq ft | 1 | 0 |
| G15 | 29.64 sq m · 319 sq ft | 1 | 1 |
| G16toG24 | 279.35 sq m · 3,007 sq ft | 1 | 1 |
| G2 | 26.67 sq m · 287 sq ft | 1 | 0 |
Show all 52 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| G3 | 28.98 sq m · 312 sq ft | 1 | 1 |
| G4 | 26.11 sq m · 281 sq ft | 1 | 1 |
| G5 | 28.98 sq m · 312 sq ft | 1 | 1 |
| G6 | 26.67 sq m · 287 sq ft | 1 | 0 |
| G7 | 40.24 sq m · 433 sq ft | 1 | 1 |
| G8 | 28.6 sq m · 308 sq ft | 1 | 1 |
| G9 | 39.56 sq m · 426 sq ft | 1 | 1 |
| Hotel | 2,475.78 sq m · 26,649 sq ft | 1 | 0 |
| Office F1 | 43.21 sq m · 465 sq ft | 1 | 0 |
| Office F10 F12 | 60.32 sq m · 649 sq ft | 1 | 1 |
| Office F11 F13 | 68.3 sq m · 735 sq ft | 1 | 1 |
| Office F14 F17 F19 | 129.4 sq m · 1,393 sq ft | 1 | 1 |
| Office F15 | 46.46 sq m · 500 sq ft | 1 | 1 |
| Office F16 | 35.15 sq m · 378 sq ft | 1 | 1 |
| Office F18 F20 | 74.8 sq m · 805 sq ft | 1 | 1 |
| Office F2 | 45.06 sq m · 485 sq ft | 1 | 1 |
| Office F3 | 40.6 sq m · 437 sq ft | 1 | 1 |
| Office F4 | 41.82 sq m · 450 sq ft | 1 | 1 |
| Office F5 F6 | 76.34 sq m · 822 sq ft | 1 | 1 |
| Office F7 F9 | 80.39 sq m · 865 sq ft | 1 | 0 |
| Office F8 | 41.08 sq m · 442 sq ft | 1 | 1 |
| Ub01 | 29.64 sq m · 319 sq ft | 1 | 1 |
| Ub02 | 25.83 sq m · 278 sq ft | 1 | 0 |
| Ub03 | 28.72 sq m · 309 sq ft | 1 | 1 |
| Ub04 | 26.11 sq m · 281 sq ft | 1 | 1 |
| Ub05 | 28.72 sq m · 309 sq ft | 1 | 0 |
| Ub06 | 26.11 sq m · 281 sq ft | 1 | 1 |
| Ub07 | 40.12 sq m · 432 sq ft | 1 | 1 |
| Ub08 | 28.81 sq m · 310 sq ft | 1 | 0 |
| Ub09 | 26.11 sq m · 281 sq ft | 1 | 1 |
| Ub10 | 38.84 sq m · 418 sq ft | 1 | 1 |
| Ub11 | 34.95 sq m · 376 sq ft | 1 | 1 |
| Ub12 and ub14 | 54.65 sq m · 588 sq ft | 1 | 1 |
| Ub13 and ub15 | 63.2 sq m · 680 sq ft | 1 | 1 |
| Ub16 | 26.2 sq m · 282 sq ft | 1 | 1 |
| Ub17 and ub18 | 54.91 sq m · 591 sq ft | 1 | 1 |
| Ub19 | 29.45 sq m · 317 sq ft | 1 | 1 |
| Ub20 | 40.33 sq m · 434 sq ft | 1 | 0 |
| Ub21 | 26.1 sq m · 281 sq ft | 1 | 1 |
| Ub22 | 29.34 sq m · 316 sq ft | 1 | 1 |
| Ub23 | 34.94 sq m · 376 sq ft | 1 | 1 |
| Ub24 | 38.83 sq m · 418 sq ft | 1 | 1 |
| Ub25 | 8.36 sq m · 90 sq ft | 1 | 0 |
| Ub26 | 8.36 sq m · 90 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals2
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Vikramkumar Pukhraj Jain | — |
| Engineer | Banderao Datta Vibhute | — |
Source: MahaRERA project page. Contact details are not shown.