Sai Samarttha Properties
Deedo IDDD-TZQROf 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 4 mo late — the same as Maharashtra's 4 mo.
Delivery record
3 of 4 registrations with dates moved or missed their RERA date · months late against the original promise
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| ShreyaP52100005125 | Punawale | Certificate Signed | 26 Jul 2019 | 25 Jan 2021 | +18 mo |
| SarishaP52100010390 | Punawale | Certificate Signed | 26 Sep 2018 | 26 Sep 2018 | On date |
| SaishaP52100016985 | Punawale | Certificate Signed | 31 Jan 2027 | 31 May 2027 | +4 mo |
| Saisha Phase - 2P52100028374 | Punawale | Certificate Signed | 31 Jan 2027 | 31 May 2027 | +4 mo |
Sai Samarttha Properties, in questions
Does Sai Samarttha Properties finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.
How many projects has Sai Samarttha Properties registered with MahaRERA?
4 projects under 4 MahaRERA registrations; 2 completed on MahaRERA.
Does Sai Samarttha Properties have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.