Skip to content

Shreya

Certificate Signed

Punawale, Pune 411033 |Promoter: Sai Samarttha Properties

Residential / Group HousingRERAP52100005125
9 Aug 2017Registered with MahaRERA
26 Jul 2019Promised completion
25 Jan 2021Revised completionPushed back 1 year and 6 months
3Buildings
175Units registered119 booked (68%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
3
Unit types
Row house, Shop1, Shop2, 1BHK, 2BHK175 units in all
Address
S NO 43 12 1 A, Pavana Nagar, PunavalePIN 411033
Designated bank account
109
Developed in phases
Yes

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.63645, 73.73410
Shreya is at latitude 18.63645, longitude 73.73410.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 1 year and 6 months

The latest completion date on record passed 5 years and 9 months ago.

Registered
9 Aug 2017
Promised
26 Jul 2019
Revised
25 Jan 2021

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000051259 Aug 201726 Jul 201925 Jan 2021Sai Samarttha PropertiesProject page

3 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Commercial And Row House46
E F Wing13127
Mhada942

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

119 of 175 units booked (68%), as the promoter reported to MahaRERA

Row house · 2 unitsShop1 · 2 unitsShop2 · 2 units1BHK · 83 units2BHK · 86 units
BuildingTypeCarpet areaUnitsBooked
Commercial And Row HouseRow house145 sq m · 1,561 sq ft22
Commercial And Row HouseShop122.9 sq m · 246 sq ft22
Commercial And Row HouseShop220.39 sq m · 219 sq ft22
E F Wing1BHK36.25 sq m · 390 sq ft99
E F Wing1BHK36.25 sq m · 390 sq ft109
E F Wing1BHK38.45 sq m · 414 sq ft64
E F Wing1BHK38.65 sq m · 416 sq ft55
E F Wing1BHK39.79 sq m · 428 sq ft1110
Show all 20 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
E F Wing2BHK44.05 sq m · 474 sq ft1917
E F Wing2BHK46.65 sq m · 502 sq ft1211
E F Wing2BHK46.9 sq m · 505 sq ft109
E F Wing2BHK48.5 sq m · 522 sq ft129
E F Wing2BHK48.55 sq m · 523 sq ft129
E F Wing2BHK50.26 sq m · 541 sq ft1212
E F Wing2BHK50.6 sq m · 545 sq ft99
Mhada1BHK37.03 sq m · 399 sq ft70
Mhada1BHK38.03 sq m · 409 sq ft70
Mhada1BHK38.51 sq m · 415 sq ft70
Mhada1BHK39.17 sq m · 422 sq ft140
Mhada1BHK39.84 sq m · 429 sq ft70

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

2 documents held by Deedo, 111 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Finance

  • PAN CardPAN.pdf · uploaded 29 Jun 2017Source

Legal

  • Legal Title reportTitle Report.pdf · uploaded 29 Jun 2017Source
  • Declaration Form BSHREYA-Affidavit Cum Declaration.pdf · uploaded 28 Jul 2017Source
  • OtherMHADA LETTER.pdf · uploaded 26 Oct 2017Source
  • Declaration Form BShreya -Form B.pdf · uploaded 26 Oct 2017Source
  • OtherOC.pdf · uploaded 13 Jun 2018Source
Show all 113 documentsShow fewer documents

Legal

  • OtherShreya OC.pdf · uploaded 5 Aug 2019Source

Migrated

  • 1 PAN CardPAN.pdf · uploaded 29 Jun 2017Source
  • 1 Copy of the legal title reportTitle Report.pdf · uploaded 29 Jun 2017Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement.pdf · uploaded 29 Jun 2017Source
  • 2 Commencement Certificates / NA Order for plotted developmentCommencement.pdf · uploaded 29 Jun 2017Source
  • 3 Commencement Certificates / NA Order for plotted developmentCommencement.pdf · uploaded 29 Jun 2017Source
  • 4 Commencement Certificates / NA Order for plotted developmentCommencement.pdf · uploaded 29 Jun 2017Source
  • 1 Copy of Layout Approval (in case of layout)layout.pdf · uploaded 30 Jun 2017Source
  • 1 Building Plan Approval (IOD)2.pdf · uploaded 30 Jun 2017Source
  • 2 Building Plan Approval (IOD)3.pdf · uploaded 30 Jun 2017Source
  • 3 Building Plan Approval (IOD)4.pdf · uploaded 30 Jun 2017Source
  • 4 Building Plan Approval (IOD)5.pdf · uploaded 30 Jun 2017Source
  • 5 Building Plan Approval (IOD)6.pdf · uploaded 30 Jun 2017Source
  • 6 Building Plan Approval (IOD)7.pdf · uploaded 30 Jun 2017Source
  • 7 Building Plan Approval (IOD)8.pdf · uploaded 30 Jun 2017Source
  • 8 Building Plan Approval (IOD)9.pdf · uploaded 30 Jun 2017Source
  • 9 Building Plan Approval (IOD)10.pdf · uploaded 30 Jun 2017Source
  • 1 Declaration in FORM BSHREYA-Affidavit Cum Declaration.pdf · uploaded 28 Jul 2017Source
  • 1 Certificates of CA (Form 3)CA Certificate - Shreya.pdf · uploaded 28 Jul 2017Source
  • 1 Proforma of Allotment letterAgreement - Phase III - Shreya - Residential Unit - As per RERA for registration - 20-07-2017 - Final.pdf · uploaded 28 Jul 2017Source
  • 1 Details of encumbrancesEncumbrance.pdf · uploaded 29 Jul 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architech's Certificate.pdf · uploaded 29 Jul 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer's Certificate.pdf · uploaded 29 Jul 2017Source
  • 2 Declaration in FORM BShreya -Form B.pdf · uploaded 26 Oct 2017Source
  • 2 Proforma of Allotment letterAgreement - Phase III - Shreya - Residential Unit - As per RERA for registration - 26-10-2017 - Final.pdf · uploaded 26 Oct 2017Source
  • 1 OtherMHADA LETTER.pdf · uploaded 26 Oct 2017Source
  • 10 Building Plan Approval (IOD)HPSC6155-compressed (1).pdf · uploaded 30 Jan 2018Source
  • 11 Building Plan Approval (IOD)HPSC6155-compressed (2).pdf · uploaded 30 Jan 2018Source
  • 12 Building Plan Approval (IOD)HPSC6155-compressed (3).pdf · uploaded 30 Jan 2018Source
  • 13 Building Plan Approval (IOD)HPSC6155-compressed (4).pdf · uploaded 30 Jan 2018Source
  • 14 Building Plan Approval (IOD)HPSC6155-compressed (5).pdf · uploaded 30 Jan 2018Source
  • 15 Building Plan Approval (IOD)HPSC6155-compressed (6).pdf · uploaded 30 Jan 2018Source
  • 16 Building Plan Approval (IOD)HPSC6155-compressed (7).pdf · uploaded 30 Jan 2018Source
  • 17 Building Plan Approval (IOD)HPSC6155-compressed (8).pdf · uploaded 30 Jan 2018Source
  • 18 Building Plan Approval (IOD)HPSC6155-compressed (9).pdf · uploaded 30 Jan 2018Source
  • 19 Building Plan Approval (IOD)HPSC6155-compressed (10).pdf · uploaded 30 Jan 2018Source
  • 20 Building Plan Approval (IOD)HPSC6155-compressed (10).pdf · uploaded 30 Jan 2018Source
  • 21 Building Plan Approval (IOD)HPSC6155-compressed (11).pdf · uploaded 30 Jan 2018Source
  • 22 Building Plan Approval (IOD)HPSC6155-compressed (12).pdf · uploaded 30 Jan 2018Source
  • 5 Commencement Certificates / NA Order for plotted developmentcommencement.pdf · uploaded 30 Jan 2018Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)arch certi shreya oct 2017.pdf · uploaded 1 Feb 2018Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENGINEER's Certificate 3.pdf · uploaded 1 Feb 2018Source
  • 2 Certificates of CA (Form 3)CA Certificate _ Shreya _ October 2017.pdf · uploaded 1 Feb 2018Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect certificate Shreya dec 2017.pdf · uploaded 3 Feb 2018Source
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)engineer certificate Shreya Oct 2017.pdf · uploaded 3 Feb 2018Source
  • 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer certificate Shreya dec 2017.pdf · uploaded 3 Feb 2018Source
  • 3 Certificates of CA (Form 3)CA Certificate _ Shreya _ December 2017.pdf · uploaded 3 Feb 2018Source
  • 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCH SHREYA.pdf · uploaded 7 Jun 2018Source
  • 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENGR SHREYA.pdf · uploaded 7 Jun 2018Source
  • 4 Certificates of CA (Form 3)CA SHREYA.pdf · uploaded 7 Jun 2018Source
  • 2 OtherOC.pdf · uploaded 13 Jun 2018Source
  • 1 Certificates of CA (Form 5)New Doc 2018-10-15_2_shreya.pdf · uploaded 15 Oct 2018Source
  • 1 Form 2ASHREYA QUALITY 01_compressed.pdf · uploaded 19 Apr 2019Source
  • 2 Form 2ASHREYA QUALITY 02_compressed.pdf · uploaded 19 Apr 2019Source
  • 3 Form 2ASHREYA QUALITY 03_compressed.pdf · uploaded 19 Apr 2019Source
  • 3 OtherShreya OC.pdf · uploaded 5 Aug 2019Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentShreya OC.pdf · uploaded 8 Aug 2019Source
  • 2 Architect’s Certificate on Completion of Project (Form 4)New Doc 2019-08-08_1.pdf · uploaded 5 Oct 2019Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)SOCIETY.pdf · uploaded 5 Oct 2019Source
  • 4 Form 2AShreya Quality Assu Cert April-June 19_compressed.pdf · uploaded 11 Oct 2019Source
  • 5 Form 2AShreya Quality Assu Cert July-Sept 19_compressed.pdf · uploaded 11 Oct 2019Source
  • 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)shreya26062018.pdf · uploaded 7 Nov 2019Source
  • 6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)shreya27092018.pdf · uploaded 7 Nov 2019Source
  • 7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)shreya26122018.pdf · uploaded 7 Nov 2019Source
  • 8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)shreya 26032019.pdf · uploaded 7 Nov 2019Source
  • 6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)SHREYA RERA Engg Certficate July 2018 - 2019 1st Quarter_compressed.pdf · uploaded 7 Nov 2019Source
  • 7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)SHREYA RERA Engg Certficate OCT 2018 - 2019 2nd Quarter_compressed.pdf · uploaded 7 Nov 2019Source
  • 8 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)SHREYA RERA Engg Certficate Jan 2018 - 2019 3rd Quarter_compressed.pdf · uploaded 7 Nov 2019Source
  • 9 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)SHREYA RERA Engg Certficate April 2018 - 2019 4th Quarter_compressed.pdf · uploaded 7 Nov 2019Source
  • 5 Certificates of CA (Form 3)shreya ca certificate.pdf · uploaded 7 Nov 2019Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Form 5 (UT) Sarisha 2018-19.pdf · uploaded 26 Nov 2019Source
  • 9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)architects certificate 2-min-min_compressed.pdf · uploaded 18 Feb 2021Source
  • 10 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)New Doc 2021-04-16.pdf · uploaded 16 Apr 2021Source
  • 6 Certificates of CA (Form 3)Form 3_ Shreeya June 2019-compressed.pdf · uploaded 16 Apr 2021Source
  • 6 Form 2Aengineers certificate shreya sept 2020.pdf · uploaded 21 Apr 2021Source
  • 7 Form 2Aengineers certificate shreya dec 2020.pdf · uploaded 21 Apr 2021Source
  • 8 Form 2Aengineers certificate shreya march 2021.pdf · uploaded 21 Apr 2021Source
  • 2 Status of Formation of Legal Entity (Society/Co Op etc.)Shreya society Certificate.pdf · uploaded 2 Aug 2021Source
  • 1 Status of ConveyanceDraft of Final Conveyance of Land _ Phase III - Shreya.pdf · uploaded 30 Apr 2025Source
  • 2 Status of ConveyanceDraft of Final Conveyance of Land _ Phase III - Shreya-2.pdf · uploaded 30 Apr 2025Source

Technical

  • Documentlayout.pdf · uploaded 30 Jun 2017Source
  • Document2.pdf · uploaded 30 Jun 2017Source
  • Document3.pdf · uploaded 30 Jun 2017Source
  • Document4.pdf · uploaded 30 Jun 2017Source
  • Document5.pdf · uploaded 30 Jun 2017Source
  • Document6.pdf · uploaded 30 Jun 2017Source
  • Document7.pdf · uploaded 30 Jun 2017Source
  • Document8.pdf · uploaded 30 Jun 2017Source
  • Document9.pdf · uploaded 30 Jun 2017Source
  • Document10.pdf · uploaded 30 Jun 2017Source
  • DocumentHPSC6155-compressed (1).pdf · uploaded 30 Jan 2018Source
  • DocumentHPSC6155-compressed (2).pdf · uploaded 30 Jan 2018Source
  • DocumentHPSC6155-compressed (3).pdf · uploaded 30 Jan 2018Source
  • DocumentHPSC6155-compressed (4).pdf · uploaded 30 Jan 2018Source
  • DocumentHPSC6155-compressed (5).pdf · uploaded 30 Jan 2018Source
  • DocumentHPSC6155-compressed (6).pdf · uploaded 30 Jan 2018Source
  • DocumentHPSC6155-compressed (7).pdf · uploaded 30 Jan 2018Source
  • DocumentHPSC6155-compressed (8).pdf · uploaded 30 Jan 2018Source
  • DocumentHPSC6155-compressed (9).pdf · uploaded 30 Jan 2018Source
  • DocumentHPSC6155-compressed (10).pdf · uploaded 30 Jan 2018Source
  • DocumentHPSC6155-compressed (10).pdf · uploaded 30 Jan 2018Source
  • DocumentHPSC6155-compressed (11).pdf · uploaded 30 Jan 2018Source
  • DocumentHPSC6155-compressed (12).pdf · uploaded 30 Jan 2018Source

Technical (Architect)

  • Documentarchitects certificate 2-min-min_compressed.pdf · uploaded 18 Feb 2021Source

Technical (Engineer)

  • DocumentNew Doc 2021-04-16.pdf · uploaded 16 Apr 2021Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Punawale, Mulshi taluka

Survey, CTS, gat or plot numbers

S NO 43 12 1 A

Boundaries

North
By Land Bearing S No 43 12 1a
South
By Land Bearing S No 40
East
By 18 Meter Wide Dp Road
West
By Remaining Part Of Land Bearing S No 43 12 1 A

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectA B Architects—
ArchitectUnusual Spaces—
EngineerHansal Parikh And Associates—
OtherColour Arts—
OtherDighe Electricals—
OtherG C Godbole & Co—
OtherMalik Group Of Construction—
OtherNamrata Kalpesh Dhruve & Co—
Show all 14 professionalsShow fewer professionals
RoleNameRegistration no.
OtherNoor Construction—
OtherSai Akash Ganga Enterprises—
OtherShrikrushna Construction—
OtherSiddivinayak Mep Consultants—
OtherYash Constrotech—
OtherYashshree Electricals—

Source: MahaRERA project page. Contact details are not shown.