Rajesh Gulabchand Rathi

Deedo IDDD-2DE3

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 34 mo late.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay34 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Jayshree BuildingP50000028388MotalaLapsed15 Dec 2023—+34 mo*

Rajesh Gulabchand Rathi, in questions

Does Rajesh Gulabchand Rathi finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 34 mo late. Across Maharashtra, 73% kept their date.

How many projects has Rajesh Gulabchand Rathi registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Rajesh Gulabchand Rathi have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.