RegisteredCompletion date passedMahaRERA status: Lapsed

P50000028388

Jayshree Building · Motala, Buldana · Rajesh Gulabchand Rathi

Promised for 15 Dec 2023 — that date has passed and MahaRERA does not mark the project complete.

2 years and 10 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: The latest completion date on record, 15 Dec 2023, has passed.

Documents 10

Title report15 Feb 2021View
Encumbrance details15 Feb 2021View
Commencement certificate15 Feb 2021View
Form B17 Feb 2021View
Registration certificate8 Sep 2021View
OtherView
OtherView
Layout planView
Show all 10 documents
Building planView
Allotment letterView

Orders 0

No MahaRERA order or list names this number.

Questions about P50000028388

Is Jayshree Building delayed?

Yes. MahaRERA records a promised completion of 15 Dec 2023, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P50000028388.

Who is the promoter?

MahaRERA records Rajesh Gulabchand Rathi as the promoter of P50000028388.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P50000028388.

Answers are generated from the record.

Data through23 Oct 2026, 01:35SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology