Rajaram Construction
Company or firm · 5 projects · 5 MahaRERA registrations
5Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date3 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Sukur Enclave Phase 1P51700001982 | Thane (M Corp.) | 2017 | Certificate Signed | 31 Dec 2018 | 31 Dec 2018 | On date |
| Sukur Sapphire Phase IP51700027081 | Thane (M Corp.) | 2020 | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | On date |
| Shree Shankheshwar AshishP51700045694 | Thane (M Corp.) | 2022 | Not reported | 31 Dec 2026 | — | On date |
| Sukur Sapphire Phase IIP51700045743 | Thane (M Corp.) | 2022 | Certificate Signed | 30 Jun 2024 | 30 Jun 2024 | On date |
| Shivam EnclaveP51700077726 | Thane (M Corp.) | 2024 | Certificate Signed | 30 Sep 2027 | 30 Jan 2028 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 3 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 4 months, for Shivam Enclave (P51700077726).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology