Sukur Enclave Phase 1
Deedo IDDP-THN-X8MKMahaRERA shows it completed; no MahaRERA orders on record; 8% of its units are booked.
Thane (M Corp.), Thane 400607 · by Rajaram Construction · 100% of its projects kept the RERA date
Buying a flat here?
See every deed registered on it.
MahaRERA shows it completed
- This projectRegistered 31 Jul 2017, completion promised 31 Dec 2018.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700001982
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700001982 | 31 Jul 2017 | 31 Dec 2018 | 31 Dec 2018 | Rajaram Construction | Project page |
Documents27
1 document held by Deedo, 26 filings listed on MahaRERA's project page
Finance
- PAN CardRAJARAM CONT PAN CARD.pdf · uploaded 29 Jul 2017Source
Legal
Migrated
- 1 PAN CardRAJARAM CONT PAN CARD.pdf · uploaded 29 Jul 2017Source
- 1 Copy of the legal title reportRajaram Project Title Report.pdf · uploaded 29 Jul 2017Source
- 1 Details of encumbrancesCIVIL APEEAL (2).pdf · uploaded 29 Jul 2017Source
- 2 Details of encumbrancesRajaram RELIANCE LOAN LETTER.pdf · uploaded 29 Jul 2017Source
Show all 27 documentsShow fewer documents
Migrated
- 1 Copy of Layout Approval (in case of layout)MYSCAN_20170727_0016.pdf · uploaded 29 Jul 2017Source
- 2 Copy of Layout Approval (in case of layout)MYSCAN_20170727_0018 (1).pdf · uploaded 29 Jul 2017Source
- 3 Copy of Layout Approval (in case of layout)Phase 1 Lay Out.pdf · uploaded 29 Jul 2017Source
- 1 Building Plan Approval (IOD)SUKUR D CC COPY.pdf · uploaded 29 Jul 2017Source
- 1 Commencement Certificates / NA Order for plotted developmentSUKUR D CC COPY.pdf · uploaded 29 Jul 2017Source
- 1 Declaration in FORM BForm B.pdf · uploaded 29 Jul 2017Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Rajaram Architect Certificate_20170729_0001.pdf · uploaded 29 Jul 2017Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate.pdf · uploaded 29 Jul 2017Source
- 1 Certificates of CA (Form 3)C A REPORT RAJARAM.pdf · uploaded 29 Jul 2017Source
- 1 Proforma of Allotment letterAgreement for Sale.pdf · uploaded 29 Jul 2017Source
- 2 Proforma of Allotment letterBuilders Allotment Letter.pdf · uploaded 29 Jul 2017Source
- 1 Certificates of Architect (Form 4)JD Form 4.pdf · uploaded 25 May 2018Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)annual report on statment of account.pdf · uploaded 25 Nov 2019Source
Technical
Technical (Architect)
- DocumentRajaram Architect Certificate_20170729_0001.pdf · uploaded 29 Jul 2017Source
Technical (Engineer)
- DocumentEngineer Certificate.pdf · uploaded 29 Jul 2017Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel SRNO 722 723 725 726 SRNO 117 VADAVLI SRNO 1144 OWALE SRNO 24211C KAVESAR
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 1BHKS72 units in all
- Address
- Srno 7-22 7-23 7-25 7-26 Srno 11-7 Vadavli Srno 114-4 Owale Srno 242-1-1c KavesarPIN 400607
- Village
- Thane (M Corp.), Thane taluka
- Location
- 19.26769, 72.97053
- Land area for this project
- 1,650 sq m (17,760 sq ft)
- Permissible built-up area
- 2,976 sq m (32,038 sq ft)
- Sanctioned built-up area
- 2,976 sq m (32,038 sq ft)
- Designated bank account
- 76
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
SRNO 7-22 7-23 7-25 7-26 SRNO 11-7 VADAVLI SRNO 114-4 OWALE SRNO 242-1-1C KAVESAR
Boundaries
- North
- Srno 11-2
- South
- Sukur Residency
- East
- Sukur Enclave Building C
- West
- Tmt Reservation
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking72 units
6 of 72 units booked (8%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 32.77 sq m · 353 sq ft | 19 | 0 |
| 1BHK | 34.5 sq m · 371 sq ft | 16 | 3 |
| 1BHKS | 44.95 sq m · 484 sq ft | 19 | 0 |
| 1BHKS | 44.95 sq m · 484 sq ft | 18 | 3 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals9
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Joshi Deshaware & Associate | — |
| Engineer | Associate Consutant | — |
| Other | Ashirwad Enterprises | — |
| Other | Golden Tin & Fabrication Work | — |
| Other | Komal Enterprises | — |
| Other | Ruhaan Skyscrapers India P Ltd | — |
| Other | Sangeeta Construction | — |
| Other | Sateri Electricals | — |
| Registered real estate agent | Jaiprakash Radhakishan Kotwani | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Thane (M Corp.)
- Metro MilleniaRERA PM1330002602679
- Kalyani Krupa Co.op Hsg Soc LtdRERA PR1330002602399
- Shreeji's Laxmi Jyot CHSLRERA PR1330002602306
- RivantaRERA PM1330002601984
- Shree Gangadhar ChslRERA PM1330002601922
- The Lake CornerRERA PM1330002601899
- Shree AudumbarRERA PR1330002601484
- Shreyas Co-Op Hsg. Soc. Ltd.RERA PR1330002601418
All 898 projects in Thane (M Corp.) · Compare Sukur Enclave Phase 1 with another project