Completion was pushed back 4 months, to Jan 2028; no MahaRERA orders on record; 0% of its units are booked.

Thane (M Corp.), Thane 410203 · by Rajaram Construction · 100% of its projects kept the RERA date

DeliveryExtended 4 moPromised Sep 2027 · now due Jan 2028RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 95 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Jan 2028

  • This projectRegistered 23 Oct 2024, completion promised 30 Sep 2027, revised to 30 Jan 2028.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700077726
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170007772623 Oct 202430 Sep 202730 Jan 2028Rajaram ConstructionProject page
Documents102

1 document held by Deedo, 101 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN.pdf · uploaded 8 Oct 2024Source
  • OthersSHIVAM FORM NO3 CA CERTIFICATE Q1 FY 25-26.pdf · uploaded 4 Aug 2025Source

Legal

  • Legal Title reportTitle Certificate 26082024.pdf · uploaded 8 Oct 2024Source
  • Declaration Form BForm B_Revise Dated.pdf · uploaded 11 Oct 2024Source
  • Declaration Form BLegal Title Report dated 09th Feb 2026.pdf · uploaded 9 Feb 2026Source
  • Declaration Form B47 - 1 - B.pdf · uploaded 9 Feb 2026Source
  • Declaration Form B47 - 1 - C.pdf · uploaded 9 Feb 2026Source
Show all 102 documentsShow fewer documents

Migrated

  • 1 PAN CardPAN.pdf · uploaded 8 Oct 2024Source
  • 1 Copy of the legal title reportTitle Certificate 26082024.pdf · uploaded 8 Oct 2024Source
  • 1 a Details of encumbrances concerned to FinanceNon Encumbrance - Financial .pdf · uploaded 8 Oct 2024Source
  • 1 Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 8 Oct 2024Source
  • 1 Building Plan Approval / NA Order for plotted developmentShivam Enclave shilphata Commencement Certificate.pdf · uploaded 8 Oct 2024Source
  • 2 Building Plan Approval / NA Order for plotted developmentLayout.pdf · uploaded 8 Oct 2024Source
  • 1 Declaration about Commencement CertificateDecl of CC.pdf · uploaded 8 Oct 2024Source
  • 1 CERSAI detailsCERSAI_Search_Report_200323496328_For_Asset_Based_Search_08_10_2024_20_42_10_007.pdf · uploaded 8 Oct 2024Source
  • 1 Deviation Report with respect to Allotment letterDeviation report - Allotment letter.pdf · uploaded 8 Oct 2024Source
  • 1 b Details of encumbrances concerned to LegalNon Encumbrance - Financial .pdf · uploaded 8 Oct 2024Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation Report - Agr for Sale.pdf · uploaded 8 Oct 2024Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)Format B.pdf · uploaded 8 Oct 2024Source
  • 1 Disclosure for secured/unsecured finance availed for the projectDeclaration of Finance.pdf · uploaded 8 Oct 2024Source
  • 1 Proforma of Allotment letterFinal Allotment Letter.pdf · uploaded 11 Oct 2024Source
  • 1 Declaration in FORM BForm B_Revise Dated.pdf · uploaded 11 Oct 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_13092024_At the time of Registration.pdf · uploaded 11 Oct 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final_Form 3_At the time of Registration_compressed.pdf · uploaded 11 Oct 2024Source
  • 2 CERSAI detailsDebtor Based Search_SS.pdf · uploaded 11 Oct 2024Source
  • 3 CERSAI detailsCersai - Asset based.pdf · uploaded 11 Oct 2024Source
  • 4 CERSAI detailsCersai - Debtor based.pdf · uploaded 11 Oct 2024Source
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)Format A_On Promoter Letterhead.pdf · uploaded 11 Oct 2024Source
  • 1 Proforma of Agreement for saleAFS.pdf · uploaded 11 Oct 2024Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest - Ramesh Bhekare.pdf · uploaded 11 Oct 2024Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest - Vilas Gaikar.pdf · uploaded 11 Oct 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 14 Oct 2024Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommence Certificate.pdf · uploaded 14 Oct 2024Source
  • 3 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest - Subhash Bhoir.pdf · uploaded 14 Oct 2024Source
  • 1 Other – TechnicalCC Verification.pdf · uploaded 18 Oct 2024Source
  • 2 Other – TechnicalOne Plot One Registration.pdf · uploaded 18 Oct 2024Source
  • 1 a Details of encumbrances concerned to FinanceAnnexure K- Non Encumbrance Concerned to Legal and Finance.pdf · uploaded 30 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 Q3 FY 24-25.pdf · uploaded 30 Jan 2025Source
  • 1 Disclosure of sold/ booked inventoryAnnexure B-Disclosure of Sold or Unsold Inventory.pdf · uploaded 30 Jan 2025Source
  • 1 CERSAI detailsAnnexure G-Asset Based Declaration.pdf · uploaded 30 Jan 2025Source
  • 2 CERSAI detailsAnnexure L- Debtor Based Declaration.pdf · uploaded 30 Jan 2025Source
  • 1 b Details of encumbrances concerned to LegalAnnexure K- Non Encumbrance Concerned to Legal and Finance.pdf · uploaded 30 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)SHIVAM ENCLAVE FORM 2 Q3 FY 24-25.pdf · uploaded 3 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)SHIVAM ENCLAVE FORM 3 Q3 FY 24-25.pdf · uploaded 7 Feb 2025Source
  • 1 a Details of encumbrances concerned to FinanceAnnexure K-Non-Encumbrance Concerned to Finance and Legal.pdf · uploaded 24 Apr 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)SHIVAM ENCLAVE FORM 1 RERA Q4 FY 24-25 REV.pdf · uploaded 24 Apr 2025Source
  • 1 CERSAI detailsAnnexure G-Asset Based Declaration.pdf · uploaded 24 Apr 2025Source
  • 2 CERSAI detailsAnnexure L- Debtor Based Declaration.pdf · uploaded 24 Apr 2025Source
  • 1 b Details of encumbrances concerned to LegalAnnexure K-Non-Encumbrance Concerned to Finance and Legal.pdf · uploaded 24 Apr 2025Source
  • Form 1FORM 1 Q3 FY 24-25.pdf · uploaded 10 Jun 2025Source
  • Form 2SHIVAM ENCLAVE FORM 2 Q3 FY 24-25.pdf · uploaded 10 Jun 2025Source
  • Form 3SHIVAM ENCLAVE FORM 3 Q3 FY 24 25.pdf · uploaded 10 Jun 2025Source
  • Disclosure of Sold and Booked InventoryAnnexure B-Disclosure of Sold or Unsold Inventory.pdf · uploaded 10 Jun 2025Source
  • OthersDeclarations.pdf · uploaded 10 Jun 2025Source
  • Form 1SHIVAM ENCLAVE FORM 1 RERA Q4 FY 24-25 REV.pdf · uploaded 10 Jun 2025Source
  • Form 2SHIVAM ENCLAVE FORM 2 RERA Q4 FY 24-25.pdf · uploaded 10 Jun 2025Source
  • Form 3Final Form 3_Shivam Enclave_Q4_FY 2024-25.pdf · uploaded 10 Jun 2025Source
  • Disclosure of Sold and Booked InventoryAnnexure B-Disclosure of Sold or Unsold Inventory.pdf · uploaded 10 Jun 2025Source
  • OthersDeclarations.pdf · uploaded 10 Jun 2025Source
  • Form 2A (FY 2024-2025)Final Form 2A_FY 2024-25_Shivam Enclave.pdf · uploaded 2 Jul 2025Source
  • Withdrawal Update Form 1Form 1_Q1_FY 2025-26_Shivam Enclave.pdf · uploaded 4 Aug 2025Source
  • Withdrawal Update Form 2Shivam Enclave-Form-2 Engineer Certificate.pdf · uploaded 4 Aug 2025Source
  • Withdrawal Update Form 3SHIVAM FORM NO3 CA CERTIFICATE Q1 FY 25-26.pdf · uploaded 4 Aug 2025Source
  • Withdrawal Update Form 1Form 1_Q1_FY 2025-26_Shivam Enclave.pdf · uploaded 14 Aug 2025Source
  • Withdrawal Update Form 1Form 1_Q1_FY 2025-26_Shivam Enclave.pdf · uploaded 14 Aug 2025Source
  • Withdrawal Update Form 2Shivam Enclave-Form-2 Engineer Certificate.pdf · uploaded 14 Aug 2025Source
  • Withdrawal Update Form 2Shivam Enclave-Form-2 Engineer Certificate.pdf · uploaded 14 Aug 2025Source
  • Withdrawal Update Form 3SHIVAM FORM NO3 CA CERTIFICATE Q1 FY 25-26.pdf · uploaded 14 Aug 2025Source
  • Withdrawal Update Form 3SHIVAM FORM NO3 CA CERTIFICATE Q1 FY 25-26.pdf · uploaded 14 Aug 2025Source
  • Form 5 (FY 2024-2025)From 5 Shivam Enclave Final signed.pdf · uploaded 1 Dec 2025Source
  • Withdrawal Update Form 1Form 1 Architect Certificate Shivam Enclave Final.pdf · uploaded 8 Dec 2025Source
  • Withdrawal Update Form 2Form 2 Engineer Certificate Shivam Enclave Final.pdf · uploaded 8 Dec 2025Source
  • Withdrawal Update Form 3Form 3-Shivam Enclave Final.pdf · uploaded 8 Dec 2025Source
  • Withdrawal Update Form 1Form 1 Architect Certificate Shivam Enclave Final.pdf · uploaded 9 Dec 2025Source
  • Withdrawal Update Form 2Form 2 Engineer Certificate Shivam Enclave Final.pdf · uploaded 9 Dec 2025Source
  • Withdrawal Update Form 3scanned form 3 shivam enclave_SIGNED u0026 STAMPED final_compressed.pdf · uploaded 9 Dec 2025Source
  • Withdrawal Update Form 1Form 1 Architect Certificate Shivam Enclave Final.pdf · uploaded 26 Dec 2025Source
  • Withdrawal Update Form 2Form 2 Engineer Certificate Shivam Enclave Final.pdf · uploaded 26 Dec 2025Source
  • Withdrawal Update Form 3scanned form 3 shivam enclave_SIGNED u0026 STAMPED final_compressed.pdf · uploaded 26 Dec 2025Source
  • Withdrawal Update Form 1Shivam Enclave Form 1-Architect Certificate.pdf · uploaded 7 Mar 2026Source
  • Withdrawal Update Form 2Shivam Enclave-Form-2 Engineer Certificate.pdf · uploaded 7 Mar 2026Source
  • Withdrawal Update Form 3form 3_compressed.pdf · uploaded 7 Mar 2026Source
  • Withdrawal Update Form 1FORM 1 Shivam Enclave -Q4 FY 25-26 signed.pdf · uploaded 22 Jun 2026Source
  • Withdrawal Update Form 2FORM 2 Shivam Enclave Q4 FY 25-26 signed.pdf · uploaded 22 Jun 2026Source
  • Withdrawal Update Form 3FORM 3 Shivam Enclave Q4 FY 25-26 Signed.pdf · uploaded 22 Jun 2026Source
  • Form 2A (FY 2025-2026)FROM 2A Shivam Enclave FY 25-26.pdf · uploaded 6 Jul 2026Source
  • Withdrawal Update Form 1Q1 From 1 Shivam Enclave.pdf · uploaded 24 Jul 2026Source
  • Withdrawal Update Form 2Q1 From 2 Shivam Enclave.pdf · uploaded 24 Jul 2026Source
  • Withdrawal Update Form 3Q1 From 3 Shviam Encalve.pdf · uploaded 24 Jul 2026Source

Technical

  • DocumentLayout.pdf · uploaded 8 Oct 2024Source
  • DocumentShivam Enclave shilphata Commencement Certificate.pdf · uploaded 8 Oct 2024Source
  • DocumentLayout.pdf · uploaded 8 Oct 2024Source
  • Other – TechnicalOne Plot One Registration.pdf · uploaded 18 Oct 2024Source
  • Other – TechnicalCC Verification.pdf · uploaded 18 Oct 2024Source
  • OthersForm 1_Q1_FY 2025-26_Shivam Enclave.pdf · uploaded 4 Aug 2025Source
  • OthersShivam Enclave-Form-2 Engineer Certificate.pdf · uploaded 4 Aug 2025Source

Technical (Architect)

  • DocumentFORM 1 Q3 FY 24-25.pdf · uploaded 30 Jan 2025Source
  • DocumentSHIVAM ENCLAVE FORM 1 RERA Q4 FY 24-25 REV.pdf · uploaded 24 Apr 2025Source
  • DocumentQ1 From 1 Shivam Enclave.pdf · uploaded 24 Jul 2026Source

Technical (Engineer)

  • DocumentSHIVAM ENCLAVE FORM 2 Q3 FY 24-25.pdf · uploaded 3 Feb 2025Source
  • DocumentQ1 From 2 Shivam Enclave.pdf · uploaded 24 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel S. NO. 47/1/B, S. NO. 47/1/C

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK, 3BHK, Office space, Shop95 units in all
Address
S. No. 47/1/B, S. No. 47/1/C, Sector No 11, Mouje Shil ThanePIN 410203
Village
Thane (M Corp.), Thane taluka
Land area for this project
3,412 sq m (36,726 sq ft)
Permissible built-up area
6,830 sq m (73,517 sq ft)
Sanctioned built-up area
6,830 sq m (73,517 sq ft)
Recreational open space
0 sq m (0 sq ft)
Designated bank account
76
Developed in phases
No

Survey, CTS, gat or plot numbers

S. NO. 47/1/BS. NO. 47/1/C

Land as published on MahaRERA's project page

S. NO. 47/1/B, S. NO. 47/1/C

Boundaries

North
30 Mtr Wide Dp Rd
South
Part Of S No 47 Hissa No 2 And S No 45
East
Part Of S No 45
West
30 Mtr Wide Dp Rd And Part Of S No 47 Hissa No 2

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking95 units

0 of 95 units booked (0%), as the promoter reported to MahaRERA

1BHK · 38 units2BHK · 38 units3BHK · 3 unitsOffice space · 4 unitsShop · 12 units
TypeCarpet areaUnitsBooked
1BHK33.61 sq m · 362 sq ft30
1BHK33.74 sq m · 363 sq ft340
1BHK39.71 sq m · 427 sq ft10
2BHK46.07 sq m · 496 sq ft380
3BHK53.62 sq m · 577 sq ft30
Office space40.75 sq m · 439 sq ft20
Office space47.49 sq m · 511 sq ft20
Shop8.36 sq m · 90 sq ft20
Show all 16 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
Shop9.4 sq m · 101 sq ft10
Shop11.36 sq m · 122 sq ft10
Shop11.55 sq m · 124 sq ft10
Shop11.88 sq m · 128 sq ft10
Shop12.95 sq m · 139 sq ft10
Shop13.31 sq m · 143 sq ft10
Shop13.58 sq m · 146 sq ft20
Shop15.95 sq m · 172 sq ft20

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals2

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
EngineerSanjay Mangesh Chavan—
EngineerSanjay Vasant Patil—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Thane (M Corp.)

All 898 projects in Thane (M Corp.) · Compare Shivam Enclave with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology