Prakash Raman Chaudhari
Individual promoter · 9 projects · 9 MahaRERA registrations · 1 reported completed
Projects99 RERA registrations
Completed1as reported on MahaRERA project pages
Kept RERA date100%7 of 7 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| GenesisP51600005245 | Nashik (M Corp.) | 2017 | Not reported | 1 Feb 2021 | — | On date |
| Shree Ganesh ImperialP49700008973 | Shahade (R) | 2017 | Completed | 1 Jul 2019 | — | On date |
| Shree Ganesh BlissP51600015415 | Nashik (M Corp.) | 2018 | Not reported | 17 Feb 2022 | — | On date |
| Shree Ganesh GalaxyyP51600023120 | Aanandwali | 2019 | Not reported | 18 Oct 2024 | — | On date |
| Shree Ganesh CrownP49700025399 | Shahade (R) | 2020 | Lapsed | 30 Jun 2025 | — | On date |
| Shree Ganesh UniverseP51600031309 | Aanandwali | 2021 | Not reported | 3 Oct 2025 | — | On date |
| Shree Ganesh SuyashyaP51600033180 | Nashik (M Corp.) | 2022 | Not reported | 31 Dec 2024 | — | On date |
| Meghaa SquareP51600051952 | Aanandwali | 2023 | Not reported | 31 Dec 2026 | — | On date |
| Shree Ganesh FortuneP51600076611 | Aanandwali | 2024 | Not reported | 30 May 2027 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 7 of 7 registrations whose RERA proposed completion date has passed were never extended beyond it.
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology