Genesis
Deedo IDDP-NSK-4EP6MahaRERA shows it completed; no MahaRERA orders on record; 43% of its units are booked.
Nashik (M Corp.), Nashik 422002 · by Prakash Raman Chaudhari · 86% of its projects kept the RERA date
Buying a flat here?
See every deed registered on it.
MahaRERA shows it completed
- This projectRegistered 11 Aug 2017, completion promised 1 Feb 2021.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
2 buildings
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51600005245
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51600005245 | 11 Aug 2017 | 1 Feb 2021 | 1 Feb 2021 | Prakash Raman Chaudhari | Project page |
Documents56
2 documents held by Deedo, 54 filings listed on MahaRERA's project page
Show all 56 documentsShow fewer documents
Legal
Migrated
- 1 PAN CardPAN Card - PRC.pdf · uploaded 3 Aug 2017Source
- 1 Copy of the legal title reportTitle Certificate - Genesis.pdf · uploaded 3 Aug 2017Source
- 1 Details of encumbrancesEncumbrance Affidavit.pdf · uploaded 3 Aug 2017Source
- 1 Copy of Layout Approval (in case of layout)Layout Plan.pdf · uploaded 3 Aug 2017Source
- 2 Copy of Layout Approval (in case of layout)Mojani Nakasha.pdf · uploaded 3 Aug 2017Source
- 3 Copy of Layout Approval (in case of layout)CTS Mojani Nakasha.pdf · uploaded 3 Aug 2017Source
- 1 Building Plan Approval (IOD)Sanctioned Building Plan Part - 1.pdf · uploaded 3 Aug 2017Source
- 2 Building Plan Approval (IOD)Sanctioned Building Plan Part - 2.pdf · uploaded 3 Aug 2017Source
- 1 Commencement Certificates / NA Order for plotted developmentBuilding Permission Continuity letter.pdf · uploaded 3 Aug 2017Source
- 2 Commencement Certificates / NA Order for plotted developmentBuilding Permission.pdf · uploaded 3 Aug 2017Source
- 1 Declaration in FORM BForm - B.pdf · uploaded 3 Aug 2017Source
- 1 Certificates of CA (Form 3)Form - 3 CA Certificate.pdf · uploaded 3 Aug 2017Source
- 1 Proforma of Allotment letterDraft - Allottment Letter.pdf · uploaded 3 Aug 2017Source
- 2 Proforma of Allotment letterDraft Agreement of Sale Genesis.pdf · uploaded 3 Aug 2017Source
- 1 Other7-12 extract Genesis.pdf · uploaded 3 Aug 2017Source
- 2 OtherProperty Card.pdf · uploaded 3 Aug 2017Source
- 3 OtherADTP Order.pdf · uploaded 3 Aug 2017Source
- 4 OtherAakar Phod.pdf · uploaded 3 Aug 2017Source
- 5 OtherNA Order.pdf · uploaded 3 Aug 2017Source
- 3 Building Plan Approval (IOD)BP Revised Sanctioned Part -1.pdf · uploaded 29 Jan 2018Source
- 4 Building Plan Approval (IOD)BP Revised Sanctioned Part -2.pdf · uploaded 29 Jan 2018Source
- 3 Commencement Certificates / NA Order for plotted developmentRevised Building Permission.pdf · uploaded 29 Jan 2018Source
- 6 OtherNMC Order dated 22-08-2017.pdf · uploaded 29 Jan 2018Source
- 1 Certificates of CA (Form 5)Genesis.pdf · uploaded 15 Oct 2018Source
- 1 Certificates of Architect (Form 4)Form 4 Genesis c.pdf · uploaded 13 Mar 2019Source
- 1 Status of Formation of Legal Entity (Society/Co Op etc.)Genesis.pdf · uploaded 12 Oct 2019Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentGenesis Occupancy - Completion Certificate.pdf · uploaded 25 Nov 2019Source
- 1 Declaration about Commencement CertificateForm D Genesis.pdf · uploaded 6 Feb 2023Source
- 1 Disclosure of sold/ booked inventoryDisclosure of Sold Unsold Genesis.pdf · uploaded 6 Feb 2023View
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Genesis RA 18-19.pdf · uploaded 13 Apr 2023Source
- 2 Certificates of CA (Form 3)CA Certificate_ GENESIS 17-18.pdf · uploaded 16 May 2023Source
- 3 Certificates of CA (Form 3)CA Certificate_ GENESIS 18-19.pdf · uploaded 16 May 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate FY17 18 genesis.pdf · uploaded 17 May 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate FY18 19 genesis.pdf · uploaded 17 May 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate FY 17 18 genesis.pdf · uploaded 17 May 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate FY18 19 genesis.pdf · uploaded 17 May 2023Source
Technical
- DocumentSanctioned Building Plan Part - 1.pdf · uploaded 3 Aug 2017Source
- DocumentSanctioned Building Plan Part - 2.pdf · uploaded 3 Aug 2017Source
- DocumentLayout Plan.pdf · uploaded 3 Aug 2017Source
- DocumentMojani Nakasha.pdf · uploaded 3 Aug 2017Source
- DocumentCTS Mojani Nakasha.pdf · uploaded 3 Aug 2017Source
- DocumentBP Revised Sanctioned Part -1.pdf · uploaded 29 Jan 2018Source
- DocumentBP Revised Sanctioned Part -2.pdf · uploaded 29 Jan 2018Source
Technical (Architect)
- DocumentArchitect Certificate FY18 19 genesis.pdf · uploaded 17 May 2023Source
Technical (Engineer)
- DocumentEngineer Certificate FY18 19 genesis.pdf · uploaded 17 May 2023Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel CTS NO 7293/1A, FP NO 140 TPS2
As registered with MahaRERA and published on its project page
- Project type
- Commercial
- Status on MahaRERA
- Certificate Signed
- Unit types
- Office type 1, Office type 2, Office type 3, Office type 4, Showroom type 1, Showroom type 230 units in all
- Address
- S NO 603/3A, CTS NO 7293/1A, FP NO 140 TPS2, Off. Shri Hari Narayan Kute Marg, Kute MargPIN 422002
- Village
- Nashik (M Corp.), Nashik taluka
- Location
- 19.99094, 73.77811
- Land area for this project
- 1,210 sq m (13,024 sq ft)
- Permissible built-up area
- 2,192 sq m (23,591 sq ft)
- Sanctioned built-up area
- 1,836 sq m (19,766 sq ft)
- Designated bank account
- 82
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
S NO 603/3A, CTS NO 7293/1A, FP NO 140 TPS2
Boundaries
- North
- Fp 141 Darga Side Of Fp 140 Sno 603 Ob 1a 618
- South
- Fp 139 132 Sno 603 Ob 2 604
- East
- Adj S No 617 And S No 603 Oblique 3b
- West
- 15 Mtr Wide Dp Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking30 units
13 of 30 units booked (43%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Office type 1 | 100.59 sq m · 1,083 sq ft | 5 | 2 |
| Office type 2 | 26.46 sq m · 285 sq ft | 10 | 2 |
| Office type 3 | 38.58 sq m · 415 sq ft | 5 | 3 |
| Office type 4 | 33.75 sq m · 363 sq ft | 5 | 3 |
| Showroom type 1 | 50.22 sq m · 541 sq ft | 4 | 2 |
| Showroom type 2 | 146.25 sq m · 1,574 sq ft | 1 | 1 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals2
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Vijaya Consultant Through Er Ashok N Jamdar | — |
| Engineer | Strucon Designers Pvt Ltd Through Er Rajendra B Chopda | — |
Source: MahaRERA project page. Contact details are not shown.