Shree Ganesh Crown

Lapsed

Shahade (R), Nandurbar 425409 |Promoter: Prakash Raman Chaudhari

21 May 2020Registered with MahaRERA
30 Jun 2025Promised completion
1Building
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Lapsed
Buildings
1
Land area for this project
1,455 sq m (15,661 sq ft)
Permissible built-up area
2,037 sq m (21,926 sq ft)
Sanctioned built-up area
1,919 sq m (20,661 sq ft)
Planning authority
Sub Divisional Officer, Shahada Part
Address
101/1/2/6/7/15/Ab/16/Ab, Dondaicha Khetiya Diversion Road, Raman Nagar, Opp. Bhau Tatya Petrol PumpPIN 425409
Designated bank account
Bassein Catholic Cooperative Bank Limited
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 21.55139, 74.48622
Shree Ganesh Crown is at latitude 21.55139, longitude 74.48622.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 30 Jun 2025

The latest completion date on record passed 1 year and 4 months ago.

Registered
21 May 2020
Promised
30 Jun 2025

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P4970002539921 May 202030 Jun 2025—Prakash Raman ChaudhariProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Shree Ganesh Crown4—

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 units registered

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00000
Open Space0170017

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Shree Ganesh Crown

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
  • Sanitary Fittings within the flats / premises75%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyBOREWELL WILL BE DONE AS WORK STARTS50%
  • Sewerage (Chamber, Lines, Septic Tank , STP)WILL BE DONE BEFORE O.C.0%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingWILL BE DONE AS PER APPROVAL BEFORE O.C.0%
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterSEPTIC TANK AND SOAK PIT WILL BE CONSTRUCTED0%
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingRAIN WATER HARVESTING WILL BE DONE BEFORE O.C.0%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationNot applicable
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingWILL BE PAVED AND FINISHED AS PER APPROVED PLAN0%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

50 documents held by Deedo, 55 filings listed on MahaRERA's project page

Title

Encumbrance

Form b

Allotment letters

Registration certificate

Form 1s

Form 2s

Form 5s

Others

Form 2as

Layout plans

Building plans

Document library

  • Copy of Layout Approval (in case of layout)Layout Order.pdf · uploaded 13 May 2020View
  • Copy of Layout Approval (in case of layout)Layout Plan.pdf · uploaded 13 May 2020View
  • Building Plan Approval / NA Order for plotted developmentBuilding Permission.pdf · uploaded 13 May 2020View
  • Copy of the legal title reportTitle Report.pdf · uploaded 13 May 2020View
  • Details of encumbrancesAffidavit.pdf · uploaded 13 May 2020View
  • Declaration in FORM BForm B.pdf · uploaded 13 May 2020View
  • Commencement Certificates / NA Order for plotted developmentBuilding Permission.pdf · uploaded 13 May 2020View
  • Building Plan Approval / NA Order for plotted developmentSG Crown - Optimized.pdf · uploaded 13 May 2020View
  • Proforma of Allotment letterAgreement.pdf · uploaded 13 May 2020View
  • Proforma of Allotment letterAllotment Letter.pdf · uploaded 13 May 2020View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Ar Certificate - S G Crown - 12-21.pdf · uploaded 28 Feb 2023View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Ar Certificate - S G Crown - 03-22.pdf · uploaded 28 Feb 2023View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Er Certificate - S G Crown - 03-21.pdf · uploaded 28 Feb 2023View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Er Certificate - S G Crown - 06-21.pdf · uploaded 28 Feb 2023View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Er Certificate - S G Crown - 09-21.pdf · uploaded 28 Feb 2023View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Er Certificate - S G Crown - 09-21.pdf · uploaded 28 Feb 2023View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Er Certificate - S G Crown - 03-22.pdf · uploaded 28 Feb 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Shree ganesh Crown 1 AR.pdf · uploaded 28 Feb 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Shree ganesh crown AR.pdf · uploaded 28 Feb 2023View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)SG Crown ER June 22.pdf · uploaded 6 Jun 2023View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)SG Crown ER Sept 22.pdf · uploaded 6 Jun 2023View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)SG Crown AR June 22.pdf · uploaded 6 Jun 2023View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)SG Crown ER Dec 22.pdf · uploaded 6 Jun 2023View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)SG Crown AR Sept 22.pdf · uploaded 7 Jun 2023View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)SG Crown AR Dec 22.pdf · uploaded 7 Jun 2023View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Ar certificate crown- Mar'23.pdf · uploaded 22 Aug 2023View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Er certificate crown- Mar'23.pdf · uploaded 22 Aug 2023View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect's Certificate S G Crown FY 23-24-Q1.pdf · uploaded 23 Sep 2023View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate S G Crown FY 23-24 Q1.pdf · uploaded 23 Sep 2023View
  • Disclosure of sold/ booked inventoryDisclosure Sold Booked Interntory - S G Crown - June 23.pdf · uploaded 9 Oct 2023View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Er Certificate S G Crown Sept 23.pdf · uploaded 20 Oct 2023View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate-Sep 23 Crown.pdf · uploaded 25 Oct 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Shree Ganesh Crown.pdf · uploaded 22 Nov 2023View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Eng Certificate S G Crown.pdf · uploaded 20 Jan 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Ar Certificate S G Crown - Dec 23.pdf · uploaded 20 Jan 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Ar Certificate S G Crown - Dec 23-pages-deleted.pdf · uploaded 20 Apr 2024View
  • Disclosure of sold/ booked inventoryDisclosure of Sold Booked Inventory - Shree Ganesh Crown - DEC 23.pdf · uploaded 20 Apr 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate Mar'24 Crown.pdf · uploaded 20 Apr 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate- Mar 24 Crown.pdf · uploaded 20 Apr 2024View
  • Disclosure of sold/ booked inventoryDisclosure of Sold Booked Inventory - Shree Ganesh Crown - JUNE 24.pdf · uploaded 26 Jul 2024View
  • Disclosure of sold/ booked inventoryDisclosure of Sold Booked Inventory -.pdf · uploaded 26 Jul 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)AR CERT -.pdf · uploaded 26 Jul 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Er Certificate - S G Crown - Q1 - Apr 24 to June 24.pdf · uploaded 26 Jul 2024View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Shree Ganesh Crown - Audit Report 23-24.pdf · uploaded 5 Dec 2024View
  • Form 5 (FY 2023-2024)Shree Ganesh Crown - Audit Report 23-24.pdf · uploaded 4 Oct 2025View
  • Form 5 (FY 2024-2025)RERA audit report -Ganesh cresent24-25-Final.pdf · uploaded 25 Dec 2025View
  • Form 2A (FY 2023-2024)2A SGCrown Mar 24.pdf · uploaded 15 Apr 2026View
  • Form 2A (FY 2024-2025)2A SGCrown Mar 25.pdf · uploaded 15 Apr 2026View

Promoter documents

  • Legal Title reportTitle Report.pdf · uploaded 13 May 2020View
  • Declaration Form BForm B.pdf · uploaded 13 May 2020View

Technical documents

  • Layout ApprovalLayout Order.pdfView
  • Layout ApprovalLayout Plan.pdfView
  • Building Plan ApprovalBuilding Permission.pdfView
  • Building Plan ApprovalSG Crown - Optimized.pdfView

Proforma allotment letter

  • Proforma allotment letterAllotment Letter.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Shahade (r), Shahade taluka

Survey, CTS, gat or plot numbers

101/1/2/6/7/15/AB/16/AB

As published on MahaRERA's project page

101/1/2/6/7/15/AB/16/AB

Boundaries

North
Plot No 5 17a Of Same Sno
South
Shree Ganesh Imperial Apartment
East
12 Meter Wide Service Road
West
12 Meter Wide Road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectVinit Prakash Chaudhari—
Chartered accountantAmol Mishra—
Chartered accountantP N Sabadra and Associates—
Chartered accountantRSPH and Associates—
EngineerStrucon Designers Pvt Ltd Through Er Rajendra B Chopda—
EngineerVinit Chaudhari—

Source: MahaRERA project page. Contact details are not shown.

Data through8 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology