Company or firm · first RERA registration 2017

Pandit Javdekar Associates

Deedo IDDD-C7KG

Of 26 registrations whose promised date has arrived, 24 kept it (92%). The rest ran a median 4 mo late.

Projects3737 RERA registrations
Kept RERA date92%Maharashtra: 73%
Median delay4 mowhen late
First sales on record38registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

9 of 37 registrations with dates moved or missed their RERA date · months late against the original promise

Show all 37 registrations

37 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
RajashreeP52100000457Pune (M Corp.)Certificate Signed30 Sep 201830 Sep 2018On date
CassiaP52100000620Pune (M Corp.)Certificate Signed31 Dec 201830 Jun 2019+6 mo
Yamuna NiwasP52100000729Pune (M Corp.)Certificate Signed31 Dec 201731 Dec 2017On date
NandanvanP52100004325Pune (M Corp.)Certificate Signed30 Jun 201930 Jun 2019On date
CressidaP52100005160Pune (M Corp.)Certificate Signed31 Dec 201931 Dec 2019On date
MohorP52100012438Pune (M Corp.)Certificate Signed30 Jun 201830 Jun 2018On date
GandhakutiP52100013891Pune (M Corp.)Certificate Signed30 Jun 201930 Jun 2019On date
VisavaP52100015689ErandwanaCertificate Signed30 Mar 202130 Mar 2021On date
YashodhanP52100015721ErandwanaCertificate Signed30 Mar 202230 Mar 2022On date
NeelprabhaP52100017935ErandwanaCertificate Signed30 Jan 202230 Jan 2022On date
PreranaP52100019072AundhCertificate Signed30 Jun 202230 Jun 2022On date
OmP52100019965Pune (M Corp.)Certificate Signed30 Jun 202230 Jun 2022On date
AshayogP52100022758Pune (M Corp.)Certificate Signed30 Dec 202330 Dec 2023On date
RevantaP52100024934Pune (M Corp.)Certificate Signed30 Jun 202330 Jun 2023On date
Shree Datta KrupaP52100026047KothrudCertificate Signed30 Dec 202330 Dec 2023On date
LataP52100026103KothrudCertificate Signed30 Dec 202330 Dec 2023On date
PasaayadanP52100026670Pune (M Corp.)Certificate Signed30 Dec 202330 Dec 2023On date
SurabhiP52100027270Pune (M Corp.)Certificate Signed30 Dec 202330 Dec 2023On date
AquilaP52100027346Pune (M Corp.)Certificate Signed30 Dec 202330 Dec 2023On date
AnjaliP52100028635Pune (M Corp.)Certificate Signed30 Mar 202430 Mar 2024On date
SantoshP52100029363ParvatiCertificate Signed30 Sep 202330 Sep 2023On date
Matoshri SulbhaP52100030000KothrudCertificate Signed31 Dec 202331 Dec 2023On date
RasikP52100031298ErandwanaCertificate Signed30 Jun 202430 Jun 2024On date
DharmeshP52100033046PethCertificate Signed28 Nov 202628 Nov 2026On date
NawalP52100046893ErandwanaCertificate Signed31 Oct 202531 Oct 2025On date
ManoramaP52100049035Erandwane SouthCertificate Signed31 Jul 202631 Jul 2026On date
ToranP52100051254AundhCertificate Signed31 Dec 202631 Dec 2026On date
Sheela AshishP52100055189Karve NagarCertificate Signed30 May 202730 Sep 2027+4 mo
NandviharP52100055797BhagatwadiCertificate Signed30 May 202730 May 2027On date
SuryodayP52100076686BhamburdaCertificate Signed31 Jul 202730 Nov 2027+4 mo
MayflowerP52100077064BakoriCertificate Signed30 Jun 202730 Oct 2027+4 mo
Mahavir ParkP52100077101AundhCertificate Signed30 Nov 202830 Nov 2028On date
WestwindP52100077340BanerCertificate Signed31 Aug 202731 Dec 2027+4 mo
Clover Co Operative Housing Society LimitedP52100079206Pune (M Corp.)Certificate Signed31 Dec 202830 Apr 2029+4 mo
VayjanathP52100079292ParvatiCertificate Signed6 Dec 20276 Apr 2028+4 mo
Prabhat GarimaPR1260002501155ErandwanaCertificate Signed30 Apr 202930 Aug 2029+4 mo
PushkariniPR1260002601310Erandwane SouthCertificate Signed31 Jan 202931 May 2029+4 mo
Show all 37 registrationsShow fewer

Pandit Javdekar Associates, in questions

Does Pandit Javdekar Associates finish projects on time?

Of 26 MahaRERA registrations whose promised completion date has arrived, 24 kept it (92%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.

How many projects has Pandit Javdekar Associates registered with MahaRERA?

37 projects under 37 MahaRERA registrations; 25 completed on MahaRERA.

Does Pandit Javdekar Associates have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology