Residential / Group Housing · 1 building · 8 unitsRERA P52100076686

Suryoday

Deedo IDDP-PUN-EXXW

Completion was pushed back 4 months, to Nov 2027; no MahaRERA orders on record; 0% of its units are booked.

Bhamburda, Pune 411004 · by Pandit Javdekar Associates · 96% of its projects kept the RERA date

DeliveryExtended 4 moPromised Jul 2027 · now due Nov 2027RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 8 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Nov 2027

  • This projectRegistered 20 Jun 2024, completion promised 31 Jul 2027, revised to 30 Nov 2027.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100076686
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210007668620 Jun 202431 Jul 202730 Nov 2027Pandit Javdekar AssociatesProject page
Documents104

1 document held by Deedo, 103 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPan card PJA.pdf · uploaded 22 May 2024Source

Legal

  • Declaration Form BDeclaration Form B - RERA - PJA - Suryoday.pdf · uploaded 22 May 2024Source
  • Legal Title reportTitle Search.pdf · uploaded 30 May 2024Source

Migrated

  • 1 PAN CardPan card PJA.pdf · uploaded 22 May 2024Source
  • 1 a Details of encumbrances concerned to FinanceNo Finance Encumbrance Certificate - RERA - PJA - Suryoday.pdf · uploaded 22 May 2024Source
  • 2 a Details of encumbrances concerned to FinanceNo Legal Encumbrance Certificate - RERA - PJA - Suryoday.pdf · uploaded 22 May 2024Source
  • 1 b Details of encumbrances concerned to LegalNo Finance Encumbrance Certificate - RERA - PJA - Suryoday.pdf · uploaded 22 May 2024Source
Show all 104 documentsShow fewer documents

Migrated

  • 2 b Details of encumbrances concerned to LegalNo Legal Encumbrance Certificate - RERA - PJA - Suryoday.pdf · uploaded 22 May 2024Source
  • 1 Copy of Layout Approval (in case of layout)1.pdf · uploaded 22 May 2024Source
  • 2 Copy of Layout Approval (in case of layout)2.pdf · uploaded 22 May 2024Source
  • 1 Building Plan Approval / NA Order for plotted development1.pdf · uploaded 22 May 2024Source
  • 2 Building Plan Approval / NA Order for plotted development2.pdf · uploaded 22 May 2024Source
  • 1 Declaration about Commencement CertificateSuryoday Format D.PDF · uploaded 22 May 2024Source
  • 1 Declaration in FORM BDeclaration Form B - RERA - PJA - Suryoday.pdf · uploaded 22 May 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.PDF · uploaded 22 May 2024Source
  • 1 CERSAI detailsSuryoday UNDERTAKING Cersai.PDF · uploaded 22 May 2024Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A Suryoday Disclosure of Interest Rahul Pandit.PDF · uploaded 22 May 2024Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A Suryoday Disclosure of Interest Shivkumar Javdekar.PDF · uploaded 22 May 2024Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFormat A Suryoday Declaration about Separate Bank Account- PJA.PDF · uploaded 22 May 2024Source
  • 1 Deviation Report with respect to Allotment letterNo Deviation of Allotment letter - RERA - Suryoday.pdf · uploaded 22 May 2024Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation.pdf · uploaded 22 May 2024Source
  • 1 Copy of the legal title reportTitle Search.pdf · uploaded 30 May 2024Source
  • 1 Commencement Certificates / NA Order for plotted developmentSURYODAY 1ST SANCTION CC (1).pdf · uploaded 30 May 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 30 May 2024Source
  • 1 Proforma of Agreement for saleAgreement.pdf · uploaded 30 May 2024Source
  • 1 Proforma of Allotment letterAlottment Letter.pdf · uploaded 30 May 2024Source
  • 1 Other – Technical2024 Declaration.pdf · uploaded 12 Jun 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.PDF · uploaded 24 Jul 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 24 Jul 2024Source
  • 1 Disclosure of sold/ booked inventorySales.PDF · uploaded 24 Jul 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 24 Jul 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Suryoday Form 1.PDF · uploaded 21 Oct 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Suryoday Form 2.PDF · uploaded 21 Oct 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Suryoday Form 3.PDF · uploaded 12 Nov 2024Source
  • 1 Commencement Certificates / NA Order for plotted developmentPandit Javdekar Associates_Suryoday_2nd Sanction CC.pdf · uploaded 10 Jan 2025Source
  • 1 Building Plan Approval / NA Order for plotted developmentPandit Javdekar Associates_Suryoday_2nd Sanction Plan_1-2_compressed.pdf · uploaded 10 Jan 2025Source
  • 2 Building Plan Approval / NA Order for plotted developmentPandit Javdekar Associates_Suryoday_2nd Sanction Plan_2-2_compressed.pdf · uploaded 10 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Suryoday Form - 1 31-12-2024.PDF · uploaded 21 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Suryoday Form - 3 31-12-2024.pdf · uploaded 21 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Suryoday Form - 2 31-12-2024.pdf · uploaded 21 Jan 2025Source
  • 1 Disclosure of sold/ booked inventorySales Disclosure Suryoday 31-12-24.PDF · uploaded 21 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Suryoday Form 3.pdf · uploaded 23 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Suryoday Form - 2.pdf · uploaded 24 Apr 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Suryoday Form 1 31-03-2025.PDF · uploaded 28 Apr 2025Source
  • 1 Disclosure of sold/ booked inventorySuryoday Sales Disclosure 31-03-2025.PDF · uploaded 28 Apr 2025Source
  • 1 Commencement Certificates / NA Order for plotted development3RD SANCTION CC SURYODAY.pdf · uploaded 10 May 2025Source
  • 1 Building Plan Approval / NA Order for plotted development3RD SANCTION PLAN 1 2 SURYODAY.pdf · uploaded 10 May 2025Source
  • 2 Building Plan Approval / NA Order for plotted development3RD SANCTION PLAN 2 2 SURYODAY.pdf · uploaded 10 May 2025Source
  • Form 1Form 1 - Arch Sandeep Hardikar - 24-25 Q1.pdf · uploaded 9 Jul 2025Source
  • Form 2Form 2 - Engg uday Aradhye - 24-25 Q1.pdf · uploaded 9 Jul 2025Source
  • Form 3Form 3 - CA Nitesh Mukadam - 24-25 Q1.pdf · uploaded 9 Jul 2025Source
  • Disclosure of Sold and Booked InventoryDisclosure of Sold and booked Inventory 24-25 Q1.pdf · uploaded 9 Jul 2025Source
  • Form 1Form 1 - Arch Sandeep Hardikar - 24-25 Q3.pdf · uploaded 9 Jul 2025Source
  • Form 2Form 2 - Engg uday Aradhye - 24-25 Q3.pdf · uploaded 9 Jul 2025Source
  • Form 3Form 3 - CA Nitesh Mukadam - 24-25 Q3.pdf · uploaded 9 Jul 2025Source
  • Disclosure of Sold and Booked InventoryDisclosure of Sold and booked Inventory 24-25 Q3.pdf · uploaded 9 Jul 2025Source
  • Form 1Form 1 - Arch Sandeep Hardikar - 24-25 Q4.pdf · uploaded 9 Jul 2025Source
  • Form 2Form 2 - Engg uday Aradhye - 24-25 Q4.pdf · uploaded 9 Jul 2025Source
  • Form 3Form 3 - CA Nitesh Mukadam - 24-25 Q4.pdf · uploaded 9 Jul 2025Source
  • Disclosure of Sold and Booked InventoryDisclosure of Sold and booked Inventory 24-25 Q4.pdf · uploaded 9 Jul 2025Source
  • Form 1Form 1 - Arch Sandeep Hardikar - 24-25 Q2.pdf · uploaded 11 Aug 2025Source
  • Form 2Form 2 - Engg uday Aradhye - 24-25 Q2.pdf · uploaded 11 Aug 2025Source
  • Form 3Form 3 - CA Nitesh Mukadam - 24-25 Q3.pdf · uploaded 11 Aug 2025Source
  • Disclosure of Sold and Booked InventoryDisclosure of Sold and Booked Inventory 24-25 Q2.pdf · uploaded 11 Aug 2025Source
  • Withdrawal Update Form 1Suryoday Form - 1 30-6-2025.PDF · uploaded 12 Aug 2025Source
  • Withdrawal Update Form 2Suryoday Form - 2 30-06-2025.PDF · uploaded 12 Aug 2025Source
  • Withdrawal Update Form 3Suryoday Form - 3 30-06-2025_compressed.pdf · uploaded 12 Aug 2025Source
  • Form 5 (FY 2024-2025)Suryoday Form 5.PDF · uploaded 30 Sep 2025Source
  • Form 2A (FY 2024-2025)Suryoday 2A 31.3.2025.PDF · uploaded 6 Oct 2025Source
  • Withdrawal Update Form 1Suryoday Form-1 30-9-25.PDF · uploaded 16 Oct 2025Source
  • Withdrawal Update Form 2Form 2 Suryoday-30-9-25.PDF · uploaded 16 Oct 2025Source
  • Withdrawal Update Form 3Form-3 Suryoday 30-9-25_compressed.pdf · uploaded 16 Oct 2025Source
  • Withdrawal Update Form 1Form 1 Suryoday 31 12 25.PDF · uploaded 19 Jan 2026Source
  • Withdrawal Update Form 2Form 2 Suryoday 31 12 25.PDF · uploaded 19 Jan 2026Source
  • Withdrawal Update Form 3Form 3 Suryoday 31 12 25.PDF · uploaded 19 Jan 2026Source
  • Withdrawal Update Form 1Form 1 Suryoday - 31-03-2026.pdf · uploaded 27 Apr 2026Source
  • Withdrawal Update Form 2Suryoday Form 2 - 31 03 2026.PDF · uploaded 27 Apr 2026Source
  • Withdrawal Update Form 3Suryoday From 3 as on 31 03 2026.pdf · uploaded 27 Apr 2026Source
  • Form 2A (FY 2025-2026)Suryoday 2A 2025-26.PDF · uploaded 30 Jun 2026Source
  • Withdrawal Update Form 1Form 1 Suryoday Q1.PDF · uploaded 15 Jul 2026Source
  • Withdrawal Update Form 2Suryoday Form 2 Q1.pdf · uploaded 15 Jul 2026Source
  • Withdrawal Update Form 3Suryoday Form 3 Q1.pdf · uploaded 15 Jul 2026Source
  • Form 5 (FY 2025-2026)PJA_Suryoday_Form-5_ FY 2025-26.PDF · uploaded 30 Sep 2026Source

Technical

  • Document1.pdf · uploaded 22 May 2024Source
  • Document2.pdf · uploaded 22 May 2024Source
  • Document1.pdf · uploaded 22 May 2024Source
  • Document2.pdf · uploaded 22 May 2024Source
  • Other – Technical2024 Declaration.pdf · uploaded 12 Jun 2024Source
  • DocumentPandit Javdekar Associates_Suryoday_2nd Sanction Plan_1-2_compressed.pdf · uploaded 10 Jan 2025Source
  • DocumentPandit Javdekar Associates_Suryoday_2nd Sanction Plan_2-2_compressed.pdf · uploaded 10 Jan 2025Source
  • Document3RD SANCTION PLAN 1 2 SURYODAY.pdf · uploaded 10 May 2025Source
  • Document3RD SANCTION PLAN 2 2 SURYODAY.pdf · uploaded 10 May 2025Source
  • Document4TH SANCTION CC - SURYODAY.pdf · uploaded 15 Jul 2026Source
  • Document4TH SANCTION PLAN 1 2 SURYODAY.pdf · uploaded 15 Jul 2026Source
  • Document4TH SANCTION PLAN 2 2 SURYODAY.pdf · uploaded 15 Jul 2026Source

Technical (Architect)

  • DocumentSuryoday Form 1.PDF · uploaded 21 Oct 2024Source
  • DocumentSuryoday Form - 1 31-12-2024.PDF · uploaded 21 Jan 2025Source
  • DocumentSuryoday Form 1 31-03-2025.PDF · uploaded 28 Apr 2025Source
  • DocumentForm 1 Suryoday Q1.PDF · uploaded 15 Jul 2026Source

Technical (Engineer)

  • DocumentSuryoday Form 2.PDF · uploaded 21 Oct 2024Source
  • DocumentSuryoday Form - 2 31-12-2024.pdf · uploaded 21 Jan 2025Source
  • DocumentSuryoday Form - 2.pdf · uploaded 24 Apr 2025Source
  • DocumentSuryoday Form 2 Q1.pdf · uploaded 15 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel CTS NO.768/4, F.P. NO.243/4

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
3BHK, Landowner share8 units in all
Address
Plot No 4, F.p. No.243/4, Tps-1, Cts No.768/4, Shivajinagar, (Bhamburda), Pune, Shivajinagar, BhamburdaPIN 411004
Village
Pune (M Corp.), Pune City taluka
Land area for this project
752 sq m (8,091 sq ft)
Permissible built-up area
2,616 sq m (28,161 sq ft)
Sanctioned built-up area
1,202 sq m (12,940 sq ft)
Designated bank account
85
Developed in phases
No

Survey, CTS, gat or plot numbers

CTS NO.768/4F.P. NO.243/4PLOT NO 4TPS1

Land as published on MahaRERA's project page

PLOT NO 4, F.P. NO.243/4, TPS-1, CTS NO.768/4, SHIVAJINAGAR, (BHAMBURDA), PUNE

Boundaries

North
Fp No 242-13 And Fp No 242-12
South
6 Mtr Wide Road
East
7-5 Mtrs Wide Road
West
Fp No 243-5 In House No 4

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking8 units

0 of 8 units booked (0%), as the promoter reported to MahaRERA

3BHK · 5 unitsLandowner share · 3 units
TypeCarpet areaUnitsBooked
3BHK117.62 sq m · 1,266 sq ft10
3BHK122.01 sq m · 1,313 sq ft30
3BHK241.76 sq m · 2,602 sq ft10
Landowner share121.67 sq m · 1,310 sq ft20
Landowner share121.68 sq m · 1,310 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals6

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectArch Sandeep Hardikar—
ArchitectPradeep Kosumbar—
Chartered accountantCa Nitesh Mukadam And Company—
Chartered accountantNitesh A Mukadam And Company Chartered Accountants—
EngineerMr Uday Aradhye—
EngineerNiranjan S Oak—

Source: MahaRERA project page. Contact details are not shown.