Company or firm · first RERA registration 2017

Mhada(Nagpur Board)

Deedo IDDD-SN3P

Of 18 registrations whose promised date has arrived, 16 kept it (89%). The rest ran a median 26 mo late.

Projects2222 RERA registrations
Kept RERA date89%Maharashtra: 73%
Median delay26 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

4 of 22 registrations with dates moved or missed their RERA date · months late against the original promise

Show all 22 registrations

22 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Site No.124, Datala, New ChandrapurP50900000159DatalaCertificate Signed30 Oct 202030 Oct 2020On date
Construction of 29 HIG Bunglow at Waddhamna, NagpurP50500000774HingnaCertificate Signed31 Jul 201831 Jul 2018On date
Construction of 240 T/S under LIGP50500000792WaddhamnaCertificate Signed30 Jul 201830 Jul 2018On date
Construction of 42 MIG Ts at Surabardi S.No.20/1,20/2P50500000920SurabardiCertificate Signed31 Jul 201831 Jul 2018On date
Construction of 96Ts EWS 36Ts MIG 8 Shops and 4 Office Chambers at site No 125 Datala New ChandrapurP50900001085DatalaCertificate Signed30 Oct 202030 Oct 2020On date
Constuction of 56 flats under EWS and 21 LIG at S.No. 11-12/3 at Mouza- Wanjara, NagpurP50500002554Nagpur (M Corp.)Certificate Signed30 Apr 202230 Apr 2022On date
Construction of 100 Flats under MIG on site No.134 at New ChandrapurP50900003200DatalaCertificate Signed30 Aug 201830 Aug 2018On date
Construction of 20 MIG flats on S.No.42,60 at Nari, NagpurP50500006157Nagpur (M Corp.)Certificate Signed18 Mar 201818 Mar 2018On date
Construction of 14 Rowhouses at Waddhamna NagpurP50500012638WaddhamnaCompleted31 Dec 2017—On date
Construction of 320 flats under HIGHS at MHADA City Empress Mill No.-5, Subhash Road, Nagpur. Ph IP50500012639Nagpur (M Corp.)Completed31 Jul 2018—On date
construction of 26 shops and 03 halls at khat road BhandaraP50600012640Bhandara (M Cl)Completed28 Feb 2018—On date
Construction of 534 EWS T/s under PMAY, mauza Pimpalgaon, Tah. Hinganghat, Dist. WardhaP50400016042Pimpalgaon (534386)Certificate Signed30 Nov 201930 Nov 2019On date
P50500016949P50500016949BeltarodiNot on record30 Jun 2026—On date
Construction of 264 flats under EWS and 32 flats under MIG at chikhali D NagpurP50500016984Nagpur (M Corp.)Lapsed30 Jun 2022—On date
Construction of 24 flats and 9 row houses at mauza Digdoh, NagpurP50500028482Digdoh (Devi)Certificate Signed30 Sep 202231 Dec 2023+50 mo*
Const of 96 HIG ts and 140 MIG ts on plot No.5 and 6, Empress Mill no.5, Subhash Road, NagpurP50500031918Nagpur (M Corp.)Certificate Signed31 Dec 202224 May 2023+47 mo*
Plot no 3 and 4 house no.175, ward no.6, city survey no.101,154,155,159 sheet no.233,227 Mouza-NagpurP50500052608Nagpur (M Corp.)Certificate Signed31 Dec 202331 Dec 2023On date
Plot No.02, House No.175, Ward No.06, C.S. No.101,154 and 159, Sheet No.233 and 227 Of Mouza-NagpurP50500052672Nagpur (M Corp.)Certificate Signed31 Dec 202331 Dec 2023On date
Construction of 40 Flats under EWS on kh no 13/3 part at mouza bhamti dist nagpur.P50500053887Sonegaon (Nipani)Certificate Signed31 Dec 202631 Dec 2026On date
Construction of 584 EWS flat under PMAY on kh no. 395, 396, 397, 398, 399 and 400 mouza BhandaraP50600055513TakaliCertificate Signed31 Dec 202630 Apr 2027+4 mo
to erect building no1 CTS no 101,154,155,159 sheetno 233 and 227 NMC h no 933 ward no 56 NagpurP50500079963Nagpur (M Corp.)Certificate Signed31 Dec 202930 Apr 2030+4 mo
Construction of 56 flats under EWS & 112 flats (G+7) under MIG Residential Tenements on land bearing Survey No. 92/3, at Mouza- Hazaripahad, Nagpur, Tal & Dist. – Nagpur.PR1190002602647Mouza - HazaripahadNot on record30 Sep 2031—On date
Show all 22 registrationsShow fewer

Mhada(Nagpur Board), in questions

Does Mhada(Nagpur Board) finish projects on time?

Of 18 MahaRERA registrations whose promised completion date has arrived, 16 kept it (89%). The rest ran a median 26 mo late. Across Maharashtra, 73% kept their date.

How many projects has Mhada(Nagpur Board) registered with MahaRERA?

22 projects under 22 MahaRERA registrations; 15 completed on MahaRERA.

Does Mhada(Nagpur Board) have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology