RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P50500028482

Construction of 24 flats and 9 row houses at mauza Digdoh, Nagpur · Digdoh (Devi), Nagpur · Mhada(Nagpur Board)

Promised for 30 Sep 2022, extended once to 31 Dec 2023 — and that date has passed without the project marked complete on MahaRERA.

4 years and 1 month past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Sep 2022 to 31 Dec 2023 (1 extension certificate on record).
  • Risk: The latest completion date on record, 31 Dec 2023, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 8

Registration certificate8 Sep 2021View
Extension certificate12 Aug 2023View
OtherView
Commencement certificateView
OtherView
OtherView
OtherView
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P50500028482

Is Construction of 24 flats and 9 row houses at mauza Digdoh, Nagpur delayed?

Yes. MahaRERA records a promised completion of 30 Sep 2022, revised to 31 Dec 2023, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P50500028482. The completion date moved from 30 Sep 2022 to 31 Dec 2023.

Who is the promoter?

MahaRERA records Mhada(Nagpur Board) as the promoter of P50500028482.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P50500028482.

Answers are generated from the record.

Data through25 Oct 2026, 02:30SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology