Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredCompletion date passedMahaRERA status: Certificate Signed

P50900000159

Site No.124, Datala, New Chandrapur · Datala, Chandrapur · Mhada(Nagpur Board)

Promised for 30 Oct 2020 — that date has passed and MahaRERA does not mark the project complete.

6 years and 1 month past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 30 Oct 2020, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 7

Registration certificate18 May 2020View
Building planView
Form BView
Form 1View
Form 2View
Building planView
Title reportView

Orders 0

No MahaRERA order or list names this number.

Questions about P50900000159

Is Site No.124, Datala, New Chandrapur delayed?

Yes. MahaRERA records a promised completion of 30 Oct 2020, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P50900000159.

Who is the promoter?

MahaRERA records Mhada(Nagpur Board) as the promoter of P50900000159.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P50900000159.

Answers are generated from the record.

Data through23 Nov 2026, 01:35SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology