Gera Developments Private Limited

Company or firm · 17 projects · 25 MahaRERA registrations

Also appears as Gera Developments P Ltd · Grandwell Properties And Leasing Private Limited

17Projects25 RERA registrations
0Completedas reported on MahaRERA project pages
93%Kept RERA date14 of 15 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 9 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Geras Misty WatersP52100001176Keshavnagarmundwa2017Certificate Signed14 Jun 202214 Jun 2023+12 months
Geras Imperium RiseP52100001786Man2017Certificate Signed30 May 202230 May 2022On date
A3, Song of Joy, Geras Greensville2P52100001789Pune (M Corp.)2017Certificate Signed30 Jun 201930 Jun 2019On date
B1 Song Of Joy Geras Greenville 2P52100002048Haveli2017Certificate Signed31 Dec 201931 Dec 2019On date
Geras AffiniaP52100005399Baner2017Certificate Signed30 Dec 202630 Apr 2027+4 months
Geras Isle RoyaleP52100009870Bavadhan Bk2017Certificate Signed30 Dec 202130 Dec 2021On date
Geras Isle RoyaleP52100011031Bavadhan Bk2017Certificate Signed31 Dec 203031 Dec 2030On date
Geras Imperium AlphaP52100015242Kharadi2018Certificate Signed30 Jan 202330 Jan 2023On date
Geras Imperium OasisP52100015514Pimpri Chinchawad (M Corp.)2018Certificate Signed30 Dec 202230 Dec 2022On date
Geras World of JoyP52100022499Wagholi2019Certificate Signed15 Sep 202515 Sep 2025On date
Geras World of Joy CP52100022522Wagholi2019Certificate Signed15 Sep 202515 Sep 2025On date
Geras World of JoyP52100022530Wagholi2019Certificate Signed15 Sep 202515 Sep 2025On date
Geras World of JoyP52100022598Wagholi2019Certificate Signed30 Oct 202530 Oct 2025On date
Geras World of JoyP52100022744Wagholi2019Certificate Signed30 Dec 202730 Dec 2027On date
ShrishtiP52100026148Wagholi2020Certificate Signed15 Sep 202515 Sep 2025On date
Geras Imperium GatewayP52100030167Bhosari2021Certificate Signed31 Mar 202631 Mar 2026On date
Geras Imperium GatewayP52100030184Bhosari2021Certificate Signed31 Mar 202631 Mar 2026On date
Geras Planet of Joy Project IP52100031802Haveli2021Certificate Signed31 Dec 202531 Dec 2025On date
Geras Planet of Joy Project IIP52100031809Wagholi2021Certificate Signed31 Dec 202630 Apr 2027+4 months
Geras Planet of Joy ProjectP52100031875Wagholi2021Certificate Signed31 Dec 202630 Apr 2027+4 months
Geras Planet of Joy ProjectP52100031876Wagholi2021Certificate Signed31 Dec 202630 Apr 2027+4 months
Geras Island of Joy ProjectP52100052259Wagholi2023Certificate Signed15 May 202815 Sep 2028+4 months
Geras Island of Joy ProjectP52100052474Wagholi2023Certificate Signed15 Jun 202815 Oct 2028+4 months
Geras Island of Joy ProjectP52100056106Wagholi2024Not reported30 Nov 20282 Jun 2029+7 months
The Joy Street Geras Island Of JoyP52100079470Haveli2025Certificate Signed30 Sep 202730 Jan 2028+4 months
Show all 25 registrationsShow fewer

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Geras Misty Waters+12 mo
  • Geras Imperium RiseOn date
  • A3, Song of Joy, Geras Greensville2On date
  • B1 Song Of Joy Geras Greenville 2On date
  • Geras Affinia+4 mo
  • Geras Isle RoyaleOn date
  • Geras Isle RoyaleOn date
  • Geras Imperium AlphaOn date
  • Geras Imperium OasisOn date
  • Geras World of JoyOn date
Show all 25 registrations
  • Geras World of Joy COn date
  • Geras World of JoyOn date
  • Geras World of JoyOn date
  • Geras World of JoyOn date
  • ShrishtiOn date
  • Geras Imperium GatewayOn date
  • Geras Imperium GatewayOn date
  • Geras Planet of Joy Project IOn date
  • Geras Planet of Joy Project II+4 mo
  • Geras Planet of Joy Project+4 mo
  • Geras Planet of Joy Project+4 mo
  • Geras Island of Joy Project+4 mo
  • Geras Island of Joy Project+4 mo
  • Geras Island of Joy Project+7 mo
  • The Joy Street Geras Island Of Joy+4 mo

Track record notes

  • 14 of 15 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 12 months, for Geras Misty Waters (P52100001176).
  • No MahaRERA regulatory order or list names these registrations.
  • MahaRERA records spell this promoter's name 3 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology