Gera Developments Private Limited
Deedo IDDD-43Q1Of 15 registrations whose promised date has arrived, 11 kept it (73%). The rest ran a median 4 mo late.
Delivery record
12 of 25 registrations with dates moved or missed their RERA date · months late against the original promise
Show all 25 registrations
25 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| complaint | Geras Imperium AlphaComplaint CC005000000228403 | Not on record |
| complaint | Geras Imperium AlphaComplaint CC005000000238608 | Not on record |
| complaint | Geras Imperium AlphaComplaint CC005000000269326 | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Geras Misty WatersP52100001176 | Keshavnagarmundwa | Certificate Signed | 14 Jun 2022 | 14 Jun 2023 | +53 mo* |
| Geras Imperium RiseP52100001786 | Man | Certificate Signed | 30 May 2022 | 30 May 2022 | On date |
| A3, Song of Joy, Geras Greensville2P52100001789 | Kharadi | Certificate Signed | 30 Jun 2019 | 30 Jun 2019 | On date |
| B1 Song Of Joy Geras Greenville 2P52100002048 | Kharadi | Certificate Signed | 31 Dec 2019 | 31 Dec 2019 | On date |
| Geras AffiniaP52100005399 | Baner | Certificate Signed | 30 Dec 2026 | 30 Apr 2027 | +4 mo |
| Geras Isle RoyaleP52100009870 | Bavadhan Bk | Certificate Signed | 30 Dec 2021 | 30 Dec 2021 | On date |
| Geras Isle RoyaleP52100011031 | Bavadhan Bk | Certificate Signed | 31 Dec 2030 | 31 Dec 2030 | On date |
| Geras Imperium AlphaP52100015242 | Kharadi | Completed | 30 Jan 2023 | 30 Jan 2023 | On date |
| Geras Imperium OasisP52100015514 | Pimpri Chinchawad (M Corp.) | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | On date |
| Geras World of JoyP52100022499 | Wagholi | Certificate Signed | 15 Sep 2025 | 15 Sep 2025 | On date |
| Geras World of Joy CP52100022522 | Wagholi | Certificate Signed | 15 Sep 2025 | 15 Sep 2025 | On date |
| Geras World of JoyP52100022530 | Wagholi | Certificate Signed | 15 Sep 2025 | 15 Sep 2025 | +14 mo* |
| Geras World of JoyP52100022598 | Wagholi | Certificate Signed | 30 Oct 2025 | 30 Oct 2025 | +13 mo* |
| Geras World of JoyP52100022744 | Wagholi | Certificate Signed | 30 Dec 2027 | 30 Dec 2027 | On date |
| ShrishtiP52100026148 | Wagholi | Certificate Signed | 15 Sep 2025 | 15 Sep 2025 | On date |
| Geras Imperium GatewayP52100030167 | Bhosari | Certificate Signed | 31 Mar 2026 | 31 Mar 2026 | On date |
| Geras Imperium GatewayP52100030184 | Bhosari | Certificate Signed | 31 Mar 2026 | 31 Mar 2026 | On date |
| Geras Planet of Joy Project IP52100031802 | Wagholi | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | +11 mo* |
| Geras Planet of Joy Project IIP52100031809 | Wagholi | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
| Geras Planet of Joy ProjectP52100031875 | Wagholi | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
| Geras Planet of Joy ProjectP52100031876 | Wagholi | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
| Geras Island of Joy ProjectP52100052259 | Wagholi | Certificate Signed | 15 May 2028 | 15 Sep 2028 | +4 mo |
| Geras Island of Joy ProjectP52100052474 | Wagholi | Certificate Signed | 15 Jun 2028 | 15 Oct 2028 | +4 mo |
| Geras Island of Joy ProjectP52100056106 | Wagholi | Certificate Signed | 30 Nov 2028 | 2 Jun 2029 | +7 mo |
| The Joy Street Geras Island Of JoyP52100079470 | Wagholi | Certificate Signed | 30 Sep 2027 | 30 Jan 2028 | +4 mo |
Show all 25 registrationsShow fewer
Gera Developments Private Limited, in questions
Does Gera Developments Private Limited finish projects on time?
Of 15 MahaRERA registrations whose promised completion date has arrived, 11 kept it (73%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.
How many projects has Gera Developments Private Limited registered with MahaRERA?
17 projects under 25 MahaRERA registrations; 12 completed on MahaRERA.
Does Gera Developments Private Limited have MahaRERA regulatory cases?
3 regulatory cases name its registrations.