Geras Affinia
Completion was pushed back 4 months, to Apr 2027; no MahaRERA orders on record; 0% of its units are booked.
Baner, Pune 411007 · Property rates in Baner · Promoter: Gera Developments Private Limited
Completion was pushed back 4 months, to Apr 2027
- This projectRegistered 11 Aug 2017, completion promised 30 Dec 2026, revised to 30 Apr 2027.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100005399
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100005399 | 11 Aug 2017 | 30 Dec 2026 | 30 Apr 2027 | Gera Developments Private Limited | Project page |
Documents96
1 document held by Deedo, 95 filings listed on MahaRERA's project page
Finance
- PAN CardGDPL PAN.pdf · uploaded 31 Jul 2017Source
Legal
- Declaration Form BForm B- Affinia.pdf · uploaded 31 Jul 2017Source
- Legal Title reportAffinia Title Report.PDF · uploaded 31 Jul 2017Source
- Declaration Form BForm B- Affinia_Oct-20.pdf · uploaded 23 Nov 2020Source
- OtherAffinia.pdf · uploaded 17 Jan 2022Source
- OtherFORM 5 Notes_Affinia_Signed.pdf · uploaded 28 Sep 2022Source
Migrated
- 1 PAN CardGDPL PAN.pdf · uploaded 31 Jul 2017Source
Show all 96 documentsShow fewer documents
Migrated
- 1 Copy of the legal title reportAffinia Title Report.PDF · uploaded 31 Jul 2017Source
- 1 Details of encumbrancesEncumbrance 15-07-17.pdf · uploaded 31 Jul 2017Source
- 1 Copy of Layout Approval (in case of layout)(1-1) CC - 19221-15 - DT 21-9-15 (Layout).pdf · uploaded 31 Jul 2017Source
- 1 Building Plan Approval (IOD)( 1-2 ) CC No CC-3757-15 Dated 10Feb2016.pdf · uploaded 31 Jul 2017Source
- 2 Building Plan Approval (IOD)( 2-2 ) CC No CC-3757-15 Dated 10Feb2016.pdf · uploaded 31 Jul 2017Source
- 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate No 2117-15 dated 08Oct2015.PDF · uploaded 31 Jul 2017Source
- 2 Commencement Certificates / NA Order for plotted developmentCommencement Certificate No 3296-13 dated 31Dec2013.PDF · uploaded 31 Jul 2017Source
- 3 Commencement Certificates / NA Order for plotted developmentCommencement Certificate No CC 1269-14 dated 23July2014.PDF · uploaded 31 Jul 2017Source
- 4 Commencement Certificates / NA Order for plotted developmentCommencement Certificate- CC-3757-15 dated 10Feb2016.PDF · uploaded 31 Jul 2017Source
- 5 Commencement Certificates / NA Order for plotted developmentCommencement Certificate No1922-15 dated 21Sep2015.PDF · uploaded 31 Jul 2017Source
- 1 Declaration in FORM BForm B- Affinia.pdf · uploaded 31 Jul 2017Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 31 Jul 2017Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Eng Certificate- Affinia.pdf · uploaded 31 Jul 2017Source
- 1 Certificates of CA (Form 3)Geras Affinia -Form-3.pdf · uploaded 31 Jul 2017Source
- 1 Proforma of Allotment letterAffinia Agreement 31072017.pdf · uploaded 31 Jul 2017Source
- 2 Proforma of Allotment letterAffinia Application form 31072017.pdf · uploaded 31 Jul 2017Source
- 1 Certificates of CA (Form 5)GDPL Affinia.pdf · uploaded 30 Sep 2018Source
- 2 Certificates of CA (Form 5)Affinia-2019.pdf · uploaded 30 Sep 2019Source
- 1 Details of Restarting of Construction work post lockdownAffinia.pdf · uploaded 20 Jun 2020Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Affinia-2019.pdf · uploaded 30 Sep 2020Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Affinia-Audit-2019-20.pdf · uploaded 30 Sep 2020Source
- 2 Declaration in FORM BForm B- Affinia_Oct-20.pdf · uploaded 23 Nov 2020Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5_GDPL Affinia.pdf · uploaded 29 Sep 2021Source
- 2 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Notes to Form 5_GDPL Affinia.pdf · uploaded 29 Sep 2021Source
- 1 OtherAffinia.pdf · uploaded 17 Jan 2022Source
- 1 Declaration about Commencement CertificateAffinia-declaration.pdf · uploaded 12 May 2022Source
- 1 Disclosure of sold/ booked inventoryImventory-Affinia.pdf · uploaded 12 May 2022Source
- 2 Details of encumbrancesCERSAI Declaration - Gera's Affinia.pdf · uploaded 18 May 2022Source
- 1 CERSAI detailsCERSAI Declaration - Gera's Affinia.pdf · uploaded 18 May 2022Source
- 2 CERSAI detailsCERSAI Declaration - Gera's Affinia.pdf · uploaded 8 Jul 2022Source
- 3 Certificates of CA (Form 5)FORM 5 Notes_Affinia_Signed.pdf · uploaded 27 Sep 2022Source
- 2 OtherFORM 5 Notes_Affinia_Signed.pdf · uploaded 28 Sep 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM 5 Notes_Affinia_Signed.pdf · uploaded 17 Oct 2022Source
- 2 Disclosure of sold/ booked inventoryAffinia.pdf · uploaded 27 Apr 2023Source
- 3 Disclosure of sold/ booked inventoryDisc Sold Unsold Aff.pdf · uploaded 21 Jul 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 Geras Affinia.pdf · uploaded 11 Sep 2023Source
- 4 Disclosure of sold/ booked inventoryAffinia Q2.pdf · uploaded 20 Oct 2023Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)31122023-Affina.pdf · uploaded 18 Jan 2024Source
- 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Affinia Enginner Certificate 31122023.pdf · uploaded 18 Jan 2024Source
- 5 Disclosure of sold/ booked inventoryDIsc of Sold Unsold Affinia.pdf · uploaded 18 Jan 2024Source
- 2 Certificates of CA (Form 3)Affinia 31122023-compressed.pdf · uploaded 18 Jan 2024Source
- 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Affinia.pdf · uploaded 20 Apr 2024Source
- 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Affinia.pdf · uploaded 20 Apr 2024Source
- 6 Disclosure of sold/ booked inventoryAffinia.pdf · uploaded 20 Apr 2024Source
- 3 Certificates of CA (Form 3)Affinia.pdf · uploaded 20 Apr 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Affinia.pdf · uploaded 29 Jun 2024Source
- 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Affinia.pdf · uploaded 19 Jul 2024Source
- 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer certificate Affinia 30062024.pdf · uploaded 19 Jul 2024Source
- 4 Certificates of CA (Form 3)Affinia.pdf · uploaded 19 Jul 2024Source
- 7 Disclosure of sold/ booked inventoryAffinia.pdf · uploaded 20 Jul 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Affinia_compressed.pdf · uploaded 9 Oct 2024Source
- 2 Certificates of CA (Form 3)Gera Affinia Towers 30092024.pdf · uploaded 20 Oct 2024Source
- 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate Affinia 30092024.pdf · uploaded 20 Oct 2024Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Affinia Baner- RERA Certi- AOR.pdf · uploaded 20 Jan 2025Source
- 1 Certificates of CA (Form 3)Affinia.pdf · uploaded 20 Jan 2025Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate Affinia -31122024.pdf · uploaded 20 Jan 2025Source
- 1 Disclosure of sold/ booked inventoryAffinia.pdf · uploaded 20 Jan 2025Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Affinia March 2025.pdf · uploaded 19 Apr 2025Source
- 1 Certificates of CA (Form 3)CA Certificate Affinia 31032025_11zon.pdf · uploaded 19 Apr 2025Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)AFFINIA ENGINEER CERTIFICATE 31032025.pdf · uploaded 19 Apr 2025Source
- 1 Disclosure of sold/ booked inventoryAffinia Sold Unsold.pdf · uploaded 24 Apr 2025Source
- Form 5 (FY 2024-2025)Affinia FY24-25.pdf · uploaded 22 Sep 2025Source
- Withdrawal Update Form 1AFFINIA_RERA CERTIFICATE.pdf · uploaded 20 Jan 2026Source
- Withdrawal Update Form 2Engineer Certificate- Affinia.pdf · uploaded 20 Jan 2026Source
- Withdrawal Update Form 3CA Certificate- Affinia 31122025.pdf · uploaded 20 Jan 2026Source
- Withdrawal Update Form 1FORM 1 Q2 Affinia.pdf · uploaded 27 Feb 2026Source
- Withdrawal Update Form 1AFFINIA_RERA CERTIFICATE.pdf · uploaded 27 Feb 2026Source
- Withdrawal Update Form 2FORM 2 Affinia Q2.pdf · uploaded 27 Feb 2026Source
- Withdrawal Update Form 2Engineer Certificate- Affinia.pdf · uploaded 27 Feb 2026Source
- Withdrawal Update Form 3FORM 3 Q2 Affinia.pdf · uploaded 27 Feb 2026Source
- Withdrawal Update Form 3CA Certificate- Affinia 31122025.pdf · uploaded 27 Feb 2026Source
- Withdrawal Update Form 1AFFINIA.pdf · uploaded 20 Apr 2026Source
- Withdrawal Update Form 2Engineer Certificate Affinia 31032026.pdf · uploaded 20 Apr 2026Source
- Withdrawal Update Form 3CA Certificate Affinia 31032026.pdf · uploaded 20 Apr 2026Source
- Withdrawal Update Form 1RERA CERTIFICATE_GERAS AFFINIA_20260630.pdf · uploaded 20 Jul 2026Source
- Withdrawal Update Form 2Engineers Certificate Affinia 30062026.pdf · uploaded 20 Jul 2026Source
- Withdrawal Update Form 3CA Certificate Affinia 30062026.pdf · uploaded 20 Jul 2026Source
- Form 5 (FY 2025-2026)Form 5 Affinia FY 25-26.pdf · uploaded 28 Sep 2026Source
Technical
Technical (Architect)
Technical (Engineer)
- DocumentEngineer Certificate Affinia 30092024.pdf · uploaded 20 Oct 2024Source
- DocumentEngineer Certificate Affinia -31122024.pdf · uploaded 20 Jan 2025Source
- DocumentAFFINIA ENGINEER CERTIFICATE 31032025.pdf · uploaded 19 Apr 2025Source
- DocumentEngineers Certificate Affinia 30062026.pdf · uploaded 20 Jul 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsPlot A2 S No 66 1 to 5 Baner
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- A, B, C, D, E, F, G, H, I, J38 units in all
- Address
- Plot A2 S No 66 1 to 5 Baner, Baner, BanerPIN 411007
- Village
- Baner, Haveli taluka
- Location
- 18.56070, 73.77696
- Designated bank account
- 85
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- Plot boundary and adjacent nala beyond
- South
- Plot boundary and adjacent amenity space
- East
- Plot Boundary and adjacent plot A1 S No 66 1 to5
- West
- Plot Boundary and 30 mts wide DP road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking38 units
0 of 38 units booked (0%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| A | 67.79 sq m · 730 sq ft | 5 | 0 |
| B | 67.62 sq m · 728 sq ft | 5 | 0 |
| C | 68.42 sq m · 736 sq ft | 5 | 0 |
| D | 68.43 sq m · 737 sq ft | 5 | 0 |
| E | 104.84 sq m · 1,128 sq ft | 5 | 0 |
| F | 104.8 sq m · 1,128 sq ft | 5 | 0 |
| G | 139.06 sq m · 1,497 sq ft | 1 | 0 |
| H | 159.93 sq m · 1,721 sq ft | 5 | 0 |
| I | 67.41 sq m · 726 sq ft | 1 | 0 |
| J | 68.17 sq m · 734 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals21
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Anshu Shukla | — |
| Architect | Prasad Doiphode | — |
| Chartered accountant | Jain Doshi and Associates | — |
| Chartered accountant | Khandelwal Jain & Associates | — |
| Chartered accountant | K Ray & Co | — |
| Engineer | Ashish Rajigare | — |
| Engineer | Santosh Tiwatne | — |
| Other | Invental Projects and Constructions | — |
Show all 21 professionalsShow fewer professionals
| Role | Name | Registration no. |
|---|---|---|
| Registered real estate agent | Ashok Kumar Rama Shnakar Kushwaha | — |
| Registered real estate agent | Big Deal Properties (India) Pvt. Ltd | — |
| Registered real estate agent | Charudatta Satish Lakhamade | — |
| Registered real estate agent | Job Daniel Jadhav | — |
| Registered real estate agent | Jones Lang Lasalle Residential Private Limited | — |
| Registered real estate agent | Loyalie IT-Solutions Pvt. Ltd | — |
| Registered real estate agent | Nelson Dsouza | — |
| Registered real estate agent | prashanta pratim das | — |
| Registered real estate agent | Propbuying Realtors Pvt Ltd | — |
| Registered real estate agent | Property Pointer Private Limited | — |
| Registered real estate agent | Rahul Anand Gaikwad | — |
| Registered real estate agent | Sauraj Tiwari | — |
| Registered real estate agent | Vijay Anand | — |
Source: MahaRERA project page. Contact details are not shown.