Geras Island of Joy Project
Completion due Jun 2029Wagholi, Pune 412207 |Promoter: Gera Developments Private Limited
Project summary
As registered with MahaRERA
- RERA registrations
- 3
- Phases
- 3
Location
Coordinates as published by MahaRERA
Also registered as
Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 15 May 2028
P52100052259- Registered
- 9 Aug 2023
- Promised
- 15 May 2028
Completion promised for 15 Jun 2028
P52100052474- Registered
- 8 Sep 2023
- Promised
- 15 Jun 2028
Completion pushed back 7 months
P52100056106- Registered
- 10 May 2024
- Promised
- 30 Nov 2028
- Revised
- 2 Jun 2029
3 RERA registrations
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100052259 | 9 Aug 2023 | 15 May 2028 | — | Gera Developments Private Limited | Project page |
| P52100052474 | 8 Sep 2023 | 15 Jun 2028 | — | Gera Developments Private Limited | Project page |
| P52100056106 | 10 May 2024 | 30 Nov 2028 | 2 Jun 2029 | Gera Developments Private Limited | Project page |
Documents
4 documents held by Deedo
Registration certificate (3)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Wagholi
Survey, CTS, gat or plot numbers
Source: registration certificates, as stated there.