Ashdan Developers Private Limited
Company or firm · 10 projects · 17 MahaRERA registrations
Also appears as Ashdan Developers Private Ltd
Projects1017 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date33%2 of 6 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 4 extended
Regulatory cases3MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Vtp Beaumonde- Nation R2 Tower5P52100007384 | Manjari Kh | 2017 | Not reported | 19 Jul 2023 | — | On date |
| Vtp Cygnus Nation R1P52100007401 | Manjari Kh | 2017 | Not reported | 18 Jul 2025 | — | On date |
| Vtp Cygnus Nation R1P52100007722 | Manjari Kh | 2017 | Not reported | 14 Jan 2024 | 14 Jul 2024 | +6 months |
| Vtp Cygnus- Nation R1-Tower7P52100009524 | Manjari Kh | 2017 | Not reported | 16 Jul 2021 | 15 Jan 2023 | +18 months |
| VTP Beaumonde-Nation R2 Tower4P52100009533 | Manjari Kh | 2017 | Not reported | 29 Apr 2021 | 31 Jan 2023 | +21 months |
| VTP Beaumonde-Nation R2 T1P52100009535 | Manjari Kh | 2017 | Not reported | 30 Jun 2024 | 24 Oct 2024 | +4 months |
| Vtp Euphoria Phase 1P52100031691 | Haveli | 2021 | Not reported | 31 Dec 2026 | — | On date |
| Velvet VillasP52100031829 | Manjari Kh | 2021 | Not reported | 31 Dec 2026 | — | On date |
| VTP EuphoriaP52100045848 | Manjari Kh | 2022 | Not reported | 30 Jun 2027 | — | On date |
| VTP EuphoriaP52100047312 | Manjari Kh | 2022 | Not reported | 31 Mar 2028 | — | On date |
| Velvet VillasP52100047370 | Manjari Kh | 2022 | Not reported | 31 Dec 2026 | — | On date |
| Vtp Euphoria Phase 4P52100049849 | Haveli | 2023 | Not reported | 31 Mar 2028 | — | On date |
| Vtp Dolce VitaP52100051819 | Haveli | 2023 | Not reported | 31 Dec 2028 | — | On date |
| Vtp Dolce VitaP52100055405 | Haveli | 2024 | Not reported | 30 Jun 2029 | — | On date |
| Vtp Dolce VitaP52100055407 | Haveli | 2024 | Not reported | 30 Jun 2029 | — | On date |
| Vtp Dolce VitaP52100055619 | Haveli | 2024 | Not reported | 30 Jun 2029 | — | On date |
| VTP EuphoriaP52100077637 | Manjari Kh | 2024 | Not reported | 31 Dec 2028 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 2 of 6 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 21 months, for VTP Beaumonde-Nation R2 Tower4 (P52100009533).
- MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
- Regulatory orderRegulatory order: PROJECT NAME:VTP CYGNUS- NATION R1-TOWER 8 (Regulatory Case No. 203 OF 2024) dated 30 May 2024. · Vtp Cygnus Nation R1 · P52100007722 · 30 May 2024
- Regulatory orderRegulatory order: PROJECT NAME:VTP BEAUMONDE-NATION R2 T1 (Regulatory Case No.119 of 2023) dated 28 December 2023. · VTP Beaumonde-Nation R2 T1 · P52100009535 · 28 Dec 2023
- Regulatory orderRegulatory order: PROJECT NAME:VTP BEAUMONDE- NATION R2 TOWER 5 (Regulatory Case No.118 of 2023) dated 28 December 2023. · Vtp Beaumonde- Nation R2 Tower5 · P52100007384 · 28 Dec 2023
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology