Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P52100009535

VTP Beaumonde-Nation R2 T1 · Manjari Kh, Pune · Ashdan Developers Private Limited

Promised for 30 Jun 2024, extended once to 24 Oct 2024 — and that date has passed without the project marked complete on MahaRERA.

2 years and 5 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Jun 2024 to 24 Oct 2024 (1 extension certificate on record).
  • Risk: The latest completion date on record, 24 Oct 2024, has passed.
  • Caution: 1 other MahaRERA order names this registration.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 3

Registration certificate31 Jan 2024View
Extension certificate12 Dec 2024View
OtherView

Orders 1

Regulatory order

Regulatory order: PROJECT NAME:VTP BEAUMONDE-NATION R2 T1 (Regulatory Case No.119 of 2023) dated 28 December 2023.

28 Dec 2023 · matched by RERA number

View order →

Questions about P52100009535

Is VTP Beaumonde-Nation R2 T1 delayed?

Yes. MahaRERA records a promised completion of 30 Jun 2024, revised to 24 Oct 2024, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100009535. The completion date moved from 30 Jun 2024 to 24 Oct 2024.

Who is the promoter?

MahaRERA records Ashdan Developers Private Limited as the promoter of P52100009535.

Is it on any MahaRERA regulatory list?

1 MahaRERA order or list names P52100009535.

Answers are generated from the record.

Data through9 Nov 2026, 01:48SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology