Not yet due2 floorsRERA P50900045831
B2, Yashodhan Vihar
Deedo IDDP-CHA-86B2-B2MahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.
Median saleNot on recordneeds 3 or more sales
Completion31 Dec 2026as registered
Units & parking in B2
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 30 m² (323 sq.ft) | 16 | Not on record |
Parking: Closed/Covered 0 · Open Space 21 (as declared to MahaRERA)
Construction progress (declared)
Work completed, as the promoter reported it to MahaRERA (Form 1). Not verified on site.
- Excavation82%
- Basement (if any)82%
- Podiums (if any)0%
- Plinth82%
- Stilt Floor0%
- Slabs of Super Structure11%
- Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
- Sanitary Fittings within the flats / premises0%
- Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
- External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
- Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
As registered with MahaRERA
- Sanctioned habitable floors
- 2
- Deedo ID
- DP-CHA-86B2-B2
Questions about B2
When is B2 due for completion?
The MahaRERA registration promises 31 Dec 2026.
How many floors does B2 have?
2 sanctioned habitable floors, as registered with MahaRERA.
Data through10 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Report a problemMethodology