Chandrapur
Deedo IDDL-CHA-CHANDRAPUR5 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects227in 35 localities
Registrations229some projects hold several
Completion still due34137 past their date
Median extension4 months21% of registrations extended
Regulatory cases16on 16 projects
5 in 10 registrations run late here
229 MahaRERA registrations in Chandrapur and the places within it
37 completed13 not yet due21 extended, not yet due100 past even the latest date58 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Chandrapur
227 projects registered with MahaRERA in this district and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Gaurav Nagari 2PMG Associates | 1 yr 11 mo late | — | — |
| Gayatri NagarBandu Laxmanrao Ahirkar | Completed | — | — |
| Shree Niwas ApartmentShree Gurukrupa Builders And Developers | Completed | — | 89% |
| Rajwada Township Phase IISkyline Builders And Developers | Due Apr 2029, extended 4 mo | — | — |
| Astha NagriShakuntala Shamrao Urade | Completed | — | — |
| Mauli Park-2VInod P Dhoble, Savita A Chafale and Prakash S Jumde | Completed | — | — |
| Gajanan NagariPMG Associates | Completed | — | — |
| Shree Sai Krupa LayoutAmit Vasantrao Mendhule | Completed | — | — |
| KshitijBlack Pearl | 2 yrs 4 mo late | — | — |
| Gaurav Nagari 3PMG Associates | 3 yrs 2 mo late | — | — |
| Gajanan Plaza 3S V Builders | Completed | — | — |
| Riddhi Nagri Township - 3Vibha Rajesh Thakur | Completed | — | 100% |
| Sidheshwar NagariSidheshwar Bhayyaji Bharre And Yogesh Balaji Misar | Completed | — | — |
| Vaibhav HeightPuspraj Developers | 2 yrs 6 mo late | — | — |
| Sai NagariRajendra Arjun Shetiya | Completed | — | — |
| Mauli ParkVInod P Dhoble, Savita A Chafale and Prakash S Jumde | Completed | — | — |
| Yashodhan Vehar Part - 1Pm Infraventures | Completed | — | — |
| Urkude Nagari -2Manohar Marotrao Urkude | Completed | — | — |
| Ganpati PrimeBhaskar Manohar Wadaskar | Completed | — | — |
| Star PrimeMustafa Hatimbhai Maimoon | 4 yrs 2 mo late | — | — |
| Shri SaiVinod Nawghade and Rajendra Nimje | 4 yrs 8 mo late | — | — |
| Shree Gurukrupa LayoutAnup Mendhule, Sarang Mendhule & Husain Abid Karori | Completed | — | — |
| Vaibhav LaxmiNamdeo T Kapgate, Meghendra H kapgate & Ravikumar H Sonwane | 4 yrs 8 mo late | — | — |
| Urkude Nagari - 1VINODINI MANOHAR Urkude | Completed | — | — |
| Adtiya PlazaAnklesh Natthuji Khaire | Completed | — | — |
Localities in Chandrapur
- Chandrapur (M Cl)46 projects
- Brahmapuri (M Cl)36 projects
- Chandrapur31 projects
- Kosara13 projects
- Ballarpur (M Cl)8 projects
- Beldati7 projects
- Datala6 projects
- Bhadravati (M Cl)5 projects
- Brahmapuri5 projects
- Navegaon Makta5 projects
- Ballarpur4 projects
- Khanji4 projects
Other districts
Most active promoters
- Pmg Associates6 projects
- Vibha Rajesh Thakur6 projects
- Vidarbha Town Developers6 projects
- Gajanan Moreshwar Nilawar5 projects
- Shree Gurukrupa Builders And Developers4 projects
- Synergy Plotters And Structures4 projects
- Tushar Santosh Kumar Agarwal4 projects
- Darshan Erectors Pvt Ltd3 projects
- Mhada(Nagpur Board)3 projects
- Niraj Pralhadrao Padgilwar3 projects
Chandrapur, in questions
How many projects in Chandrapur run late?
5 in 10 MahaRERA registrations (121 of 229): their completion date was extended or has passed, data through 21 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Chandrapur by Deedo. Medians on fewer than 3 deeds are not shown.
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology