Skip to content
Deedo home
Menu

Vasantpushpa

Completed

Amravati (M Corp.), Amravati 444604 |Promoter: Abhishek Vasantrao Vinchurkar

Residential / Group HousingRERAP50300048791
17 Jan 2023Registered with MahaRERA
11 Dec 2025Promised completion
1Building
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Completed
Buildings
1
Land area for this project
441 sq m (4,745 sq ft)
Permissible built-up area
773 sq m (8,318 sq ft)
Sanctioned built-up area
773 sq m (8,318 sq ft)
Planning authority
Amravati Muncipal Corporation
Address
Plot No. 17 Survey No. 175, Mauje Rahatgaon, Pragane Nandgaon PethPIN 444604
Designated bank account
The Cosmos Co Operative Bank Limited
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 20.93198, 77.75230
Vasantpushpa is at latitude 20.93198, longitude 77.75230.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 11 Dec 2025

The latest completion date on record passed 10 months ago.

Registered
17 Jan 2023
Promised
11 Dec 2025

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5030004879117 Jan 202311 Dec 2025—Abhishek Vasantrao VinchurkarProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Vasantpushpa4—

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 units registered

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00001
Open Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Vasantpushpa

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure30%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyBOREWELL0%
  • Sewerage (Chamber, Lines, Septic Tank , STP)AS PER PLAN20%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingNot applicable
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingAS PER PLAN0%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationNot applicable
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

5 documents held by Deedo, 28 filings listed on MahaRERA's project page

Registration certificate

Others

Layout plan

Document library

  • Copy of the legal title reportsearch report.pdf · uploaded 29 Nov 2022Source
  • Copy of Layout Approval (in case of layout)sanctioned plan_compressed.pdf · uploaded 29 Nov 2022View
  • Building Plan Approval / NA Order for plotted developmentsanctioned plan_compressed.pdf · uploaded 29 Nov 2022View
  • Commencement Certificates / NA Order for plotted developmentsanction letter.pdf · uploaded 29 Nov 2022Source
  • Declaration about Commencement Certificatedeclaration about commencement certificate.pdf · uploaded 29 Nov 2022Source
  • Deviation Report with respect to model copy of AgreementDeviation with model copy of agreement.pdf · uploaded 29 Nov 2022Source
  • Deviation Report with respect to Allotment letterDeviation with model copy of allotment.pdf · uploaded 29 Nov 2022Source
  • Proforma of Allotment letterAllotment Letter.pdf · uploaded 30 Nov 2022Source
  • Proforma of Agreement for saleAgreement.pdf · uploaded 30 Nov 2022Source
  • Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBank.pdf · uploaded 30 Nov 2022Source
  • a Details of encumbrances concerned to FinanceDetails of encumbrances concerned to Finance.pdf · uploaded 30 Nov 2022Source
  • b Details of encumbrances concerned to LegalDetails of encumbrances concerned to Finance.pdf · uploaded 30 Nov 2022Source
  • a Details of encumbrances concerned to FinanceDetails of encumbrances concerned to Legal.pdf · uploaded 30 Nov 2022Source
  • b Details of encumbrances concerned to LegalDetails of encumbrances concerned to Legal.pdf · uploaded 30 Nov 2022Source
  • CERSAI detailscombinepdf.pdf · uploaded 30 Nov 2022Source
  • Declaration in FORM BForm B.pdf · uploaded 2 Dec 2022Source
  • CERSAI detailsCersai undertaking.pdf · uploaded 16 Dec 2022Source
  • Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest in Other Real Estate Organizations.pdf · uploaded 2 Jan 2023Source
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 march.pdf · uploaded 19 Aug 2023Source
  • Disclosure of sold/ booked inventoryUnsold Inventory.pdf · uploaded 19 Aug 2023Source
  • Disclosure of sold/ booked inventoryStock.pdf · uploaded 7 Dec 2023Source
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect Certificate.pdf · uploaded 7 Dec 2023Source
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOC.pdf · uploaded 22 Jan 2025Source

Promoter documents

  • Legal Title reportsearch report.pdf · uploaded 29 Nov 2022Source
  • Declaration Form BForm B.pdf · uploaded 2 Dec 2022Source

Technical documents

  • Layout Approvalsanctioned plan_compressed.pdfView
  • Building Plan Approvalsanctioned plan_compressed.pdfView

Proforma allotment letter

  • Proforma allotment letterAllotment Letter.pdfSource

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Amravati (M Corp.), Amravati taluka

Survey, CTS, gat or plot numbers

17175PLOT NO. 17 SURVEY NO. 175

As published on MahaRERA's project page

PLOT NO. 17 SURVEY NO. 175

Boundaries

North
Road
South
Plot No 9-A And 9-B
East
Road
West
Plot No 16-B

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAbhishek Vinchurkar—
Chartered accountantShubham Wankhade—
EngineerAnant Saurkar—

Source: MahaRERA project page. Contact details are not shown.

Data through9 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology