Deedo IDDP-THN-NEG7Completion was pushed back 4 months, to Apr 2027; no MahaRERA orders on record; 71% of its units are booked.
Titwala, Thane 421605 · by Jay Ganesh Developers
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2027
- This projectRegistered 17 Mar 2022, completion promised 31 Dec 2026, revised to 30 Apr 2027.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
8 buildings
Open a building to see every flat, floor by floor.
- Tower 18 floors · 107 units49% booked
- Tower 28 floors · 196 units55% booked
- Tower 38 floors · 198 units54% booked
- Tower 49 floors · 198 units99% booked
- Tower 59 floors · 268 units99% booked
- Tower 69 floors · 268 units72% booked
- Tower 77 floors · 88 units92% booked
- Tower 812 floors · 88 units0% booked
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700034000
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700034000 | 17 Mar 2022 | 31 Dec 2026 | 30 Apr 2027 | Jay Ganesh Developers | Project page |
Documents144
1 document held by Deedo, 143 filings listed on MahaRERA's project page
Finance
- PAN Cardpan card jay ganesh dev.pdf · uploaded 20 Feb 2024Source
Legal
Migrated
- 1 Details of encumbrancesDecleration of Encumbrances_Jay Ganesh.pdf · uploaded 9 Mar 2022Source
- 1 Copy of Layout Approval (in case of layout)Final Layout Approval-MHADA.pdf · uploaded 9 Mar 2022Source
- 1 Building Plan Approval / NA Order for plotted developmentT2 01_A1_merged.pdf · uploaded 9 Mar 2022Source
- 2 Building Plan Approval / NA Order for plotted developmentilovepdf_merged (4).pdf · uploaded 9 Mar 2022Source
Show all 144 documentsShow fewer documents
Migrated
- 3 Building Plan Approval / NA Order for plotted developmentSP 01_A0 COLOUR_merged.pdf · uploaded 9 Mar 2022Source
- 4 Building Plan Approval / NA Order for plotted developmentilovepdf_merged (7).pdf · uploaded 9 Mar 2022Source
- 5 Building Plan Approval / NA Order for plotted developmentCS3 01_A1_merged.pdf · uploaded 9 Mar 2022Source
- 6 Building Plan Approval / NA Order for plotted developmentT8 01_A0_merged.pdf · uploaded 9 Mar 2022Source
- 7 Building Plan Approval / NA Order for plotted developmentT4 01_A1_merged_11zon.pdf · uploaded 9 Mar 2022Source
- 8 Building Plan Approval / NA Order for plotted developmentT1B 06_merged-1.pdf · uploaded 9 Mar 2022Source
- 9 Building Plan Approval / NA Order for plotted developmentT1B 01_merged -02.pdf · uploaded 9 Mar 2022Source
- 10 Building Plan Approval / NA Order for plotted developmentT5 01_A0_merged-03.pdf · uploaded 9 Mar 2022Source
- 11 Building Plan Approval / NA Order for plotted developmentT5 04_A0_merged.pdf · uploaded 9 Mar 2022Source
- 1 Commencement Certificates / NA Order for plotted developmentcommencement certificate MHADA.pdf · uploaded 9 Mar 2022Source
- 1 Declaration about Commencement CertificateDeclaration of commencement certificate layout approval_Jay Ganesh.pdf · uploaded 9 Mar 2022Source
- 1 Declaration in FORM Bform B affidavits declaration (1).pdf · uploaded 9 Mar 2022Source
- 1 CERSAI detailsCREDAI CERT.pdf · uploaded 9 Mar 2022Source
- 1 Proforma of Allotment letterAgreement Draft for Titwala.pdf · uploaded 9 Mar 2022Source
- 1 Copy of the legal title reportLegal Tital Report jay ganesh developrs_compressed.pdf · uploaded 14 Mar 2022Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Unsold Inventory_.pdf · uploaded 14 Mar 2022Source
- 12 Building Plan Approval / NA Order for plotted developmentBuilding Approval.pdf · uploaded 11 Apr 2022Source
- 13 Building Plan Approval / NA Order for plotted developmentBUILDING PERMISSION AND PLANS-9_compressed.pdf · uploaded 11 Apr 2022Source
- 14 Building Plan Approval / NA Order for plotted developmentBUILDING PERMISSION AND PLANS-10_compressed.pdf · uploaded 11 Apr 2022Source
- 15 Building Plan Approval / NA Order for plotted developmentBUILDING PERMISSION AND PLANS-11_compressed.pdf · uploaded 11 Apr 2022Source
- 16 Building Plan Approval / NA Order for plotted developmentBUILDING PERMISSION AND PLANS-12.pdf · uploaded 11 Apr 2022Source
- 17 Building Plan Approval / NA Order for plotted developmentBUILDING PERMISSION AND PLANS-13.pdf · uploaded 11 Apr 2022Source
- 18 Building Plan Approval / NA Order for plotted developmentBUILDING PERMISSION AND PLANS-14.pdf · uploaded 11 Apr 2022Source
- 19 Building Plan Approval / NA Order for plotted developmentBUILDING PERMISSION AND PLANS-15.pdf · uploaded 11 Apr 2022Source
- 20 Building Plan Approval / NA Order for plotted developmentBUILDING PERMISSION AND PLANS-16.pdf · uploaded 11 Apr 2022Source
- 21 Building Plan Approval / NA Order for plotted developmentBUILDING PERMISSION AND PLANS-17.pdf · uploaded 11 Apr 2022Source
- 22 Building Plan Approval / NA Order for plotted developmentBUILDING PERMISSION AND PLANS-18.pdf · uploaded 11 Apr 2022Source
- 23 Building Plan Approval / NA Order for plotted developmentBUILDING PERMISSION AND PLANS-19.pdf · uploaded 11 Apr 2022Source
- 24 Building Plan Approval / NA Order for plotted developmentBUILDING PERMISSION AND PLANS-20.pdf · uploaded 11 Apr 2022Source
- 25 Building Plan Approval / NA Order for plotted developmentBUILDING PERMISSION AND PLANS-21.pdf · uploaded 11 Apr 2022Source
- 26 Building Plan Approval / NA Order for plotted developmentBUILDING PERMISSION AND PLANS-22.pdf · uploaded 11 Apr 2022Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect's Certificate.pdf · uploaded 1 Feb 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect's Certificate.pdf · uploaded 2 Feb 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)08-07-2022- Engineer_COMPRESSED.pdf · uploaded 2 Feb 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate Scanned (2).pdf · uploaded 2 Feb 2023Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect's Certificate Q2.pdf · uploaded 25 Apr 2023Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect's Certificate -Q3.pdf · uploaded 25 Apr 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)QUARTER-2-Engineer-COMPRESSED.pdf · uploaded 25 Apr 2023Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)QUARTER-3-engineer_COMPRESSED.pdf · uploaded 25 Apr 2023Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate-Form 3 Q2-signed.pdf · uploaded 26 Apr 2023Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate -Form 3- Q3-signed.pdf · uploaded 26 Apr 2023Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)ilovepdf_merged_11zon-sign.pdf · uploaded 11 Oct 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 for FY 2022-23.pdf · uploaded 8 Feb 2024Source
- 1 PAN Cardpan card jay ganesh dev.pdf · uploaded 20 Feb 2024Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3 for Q1 FY 2023-24_11zon-DS.pdf · uploaded 4 Mar 2024Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3 for Q2 FY 2023-24_11zon-DS.pdf · uploaded 4 Mar 2024Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3 for Q3 FY 2023-24_11zon-DS.pdf · uploaded 4 Mar 2024Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1 Q4-new.pdf · uploaded 5 Mar 2024Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1 Q1_new.pdf · uploaded 5 Mar 2024Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1 Q2-new.pdf · uploaded 5 Mar 2024Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1 Q3-new.pdf · uploaded 5 Mar 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2 Q-4_11zon.pdf · uploaded 5 Mar 2024Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2 Q-1_11zon.pdf · uploaded 5 Mar 2024Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2 Q-2_11zon.pdf · uploaded 5 Mar 2024Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2 Q-3_11zon.pdf · uploaded 5 Mar 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM -1 30-06-2024.pdf · uploaded 6 Feb 2025Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM -1 30-09-2024.pdf · uploaded 6 Feb 2025Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM -1 31-12-2024.pdf · uploaded 6 Feb 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM -1 31-03-2024.pdf · uploaded 6 Feb 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM-3 31 MARCH 2024.pdf · uploaded 6 Feb 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM-3 30 JUNE 2024.pdf · uploaded 6 Feb 2025Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM-3 30 SEPTEMBER 2024.pdf · uploaded 6 Feb 2025Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM-3 31 DECEMBER 2024.pdf · uploaded 6 Feb 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM -2 31-03-2024.pdf · uploaded 6 Feb 2025Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM -2 31-12-2024.pdf · uploaded 6 Feb 2025Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM -2 30-09-2024.pdf · uploaded 6 Feb 2025Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM -2 30-06-2024.pdf · uploaded 6 Feb 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM-05 01-04-2021 TO 31-03-2022.pdf · uploaded 6 Feb 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)FORM -2A 2021-22.pdf · uploaded 6 Feb 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM -2A 2022-23.pdf · uploaded 6 Feb 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM -2A 2023-24.pdf · uploaded 6 Feb 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)FORM-3 31 DECEMBER 2024.pdf · uploaded 6 Feb 2025Source
- Form 1FORM 1 - JAY GANESH - MAR 2025.pdf · uploaded 15 Jul 2025Source
- Form 2FORM 2 - JAY GANESH - MAR 2025- SIGN.pdf · uploaded 15 Jul 2025Source
- Form 3FORM 3 - JAY GANESH - MAR 2025- 1_11zon.pdf · uploaded 15 Jul 2025Source
- Disclosure of Sold and Booked InventoryDisclosure for Sold-Unsold-31 March, 2025_11zon.pdf · uploaded 15 Jul 2025Source
- Self-declaration of Quarterly ProgressSELF DECL - JAY GANESH JAN TO MARCH - PDF- SIGN.pdf · uploaded 15 Jul 2025Source
- Form 2A (FY 2024-2025)FORM 2A-31 March, 2025-Q4-F.Y.2024-25 (1)_11zon.pdf · uploaded 15 Jul 2025Source
- Form 5 (FY 2024-2025)FORM 5 - JAY GANESH - FY 24-25.pdf · uploaded 15 Jul 2025Source
- Form 1FORM 1 - JAY GANESH - JUN 25.pdf · uploaded 5 Aug 2025Source
- Form 2FORM 2 - JAY GANESH - JUN 25_11zon.pdf · uploaded 5 Aug 2025Source
- Form 3FORM 3 - JAY GANESH - JUN 25_11zon.pdf · uploaded 5 Aug 2025Source
- Disclosure of Sold and Booked InventoryDISCL FOR SOLD UNSOLD - UPLOADATION - JUNE 2025.pdf · uploaded 5 Aug 2025Source
- Form 1FORM 1 - SEPT 25 - JAYGANESH.pdf · uploaded 18 Feb 2026Source
- Form 2FORM 2 - SEPT 25 - JAYGANESH_11zon.pdf · uploaded 18 Feb 2026Source
- Form 3FORM 3 - SEPT 25 - JAYGANESH_11zon.pdf · uploaded 18 Feb 2026Source
- Disclosure of Sold and Booked InventoryDISCL FOR SOLD UNSOLD - JAY GANESH - SEPT 25_11zon.pdf · uploaded 18 Feb 2026Source
- Form 1FORM 1 - JAY GANESH - DEC 25.pdf · uploaded 15 Apr 2026Source
- Form 2FORM 2 - JAY GANESH - DEC 25_11zon.pdf · uploaded 15 Apr 2026Source
- Form 3FORM 3 - JAY GANESH - DEC 25_11zon.pdf · uploaded 15 Apr 2026Source
- Disclosure of Sold and Booked InventoryDISCL FOR SOLD UNSOLD - DEC 25_11zon (1).pdf · uploaded 15 Apr 2026Source
- Form 1FORM 1 - JAY GANESH - MARCH 2026.pdf · uploaded 29 Jun 2026Source
- Form 2FORM 2 - JAY GANESH - MARCH 2026_11zon.pdf · uploaded 29 Jun 2026Source
- Form 3FORM 3 - JAY GANESH - MARCH 2026_11zon.pdf · uploaded 29 Jun 2026Source
- Disclosure of Sold and Booked InventoryFORM 3 - JAY GANESH - MARCH 2026_11zon.pdf · uploaded 29 Jun 2026Source
- Form 1Form 1- jay ganesh - jun 2026_11zon.pdf · uploaded 7 Sep 2026Source
- Form 2FORM-2- jay ganesh - jun 2026_11zon.pdf · uploaded 7 Sep 2026Source
- Form 3form 3 - jay ganesh - june 2026 - signed_11zon.pdf · uploaded 7 Sep 2026Source
- Disclosure of Sold and Booked Inventoryform 3 - jay ganesh - june 2026 - signed_11zon.pdf · uploaded 7 Sep 2026Source
Technical
- DocumentT2 01_A1_merged.pdf · uploaded 9 Mar 2022Source
- Documentilovepdf_merged (4).pdf · uploaded 9 Mar 2022Source
- DocumentSP 01_A0 COLOUR_merged.pdf · uploaded 9 Mar 2022Source
- Documentilovepdf_merged (7).pdf · uploaded 9 Mar 2022Source
- DocumentCS3 01_A1_merged.pdf · uploaded 9 Mar 2022Source
- DocumentT8 01_A0_merged.pdf · uploaded 9 Mar 2022Source
- DocumentT4 01_A1_merged_11zon.pdf · uploaded 9 Mar 2022Source
- DocumentT1B 06_merged-1.pdf · uploaded 9 Mar 2022Source
- DocumentT1B 01_merged -02.pdf · uploaded 9 Mar 2022Source
- DocumentFinal Layout Approval-MHADA.pdf · uploaded 9 Mar 2022Source
- DocumentT5 01_A0_merged-03.pdf · uploaded 9 Mar 2022Source
- DocumentT5 04_A0_merged.pdf · uploaded 9 Mar 2022Source
- DocumentBuilding Approval.pdf · uploaded 11 Apr 2022Source
- DocumentBUILDING PERMISSION AND PLANS-9_compressed.pdf · uploaded 11 Apr 2022Source
- DocumentBUILDING PERMISSION AND PLANS-10_compressed.pdf · uploaded 11 Apr 2022Source
- DocumentBUILDING PERMISSION AND PLANS-11_compressed.pdf · uploaded 11 Apr 2022Source
- DocumentBUILDING PERMISSION AND PLANS-12.pdf · uploaded 11 Apr 2022Source
- DocumentBUILDING PERMISSION AND PLANS-13.pdf · uploaded 11 Apr 2022Source
- DocumentBUILDING PERMISSION AND PLANS-14.pdf · uploaded 11 Apr 2022Source
- DocumentBUILDING PERMISSION AND PLANS-15.pdf · uploaded 11 Apr 2022Source
- DocumentBUILDING PERMISSION AND PLANS-16.pdf · uploaded 11 Apr 2022Source
- DocumentBUILDING PERMISSION AND PLANS-17.pdf · uploaded 11 Apr 2022Source
- DocumentBUILDING PERMISSION AND PLANS-18.pdf · uploaded 11 Apr 2022Source
- DocumentBUILDING PERMISSION AND PLANS-19.pdf · uploaded 11 Apr 2022Source
- DocumentBUILDING PERMISSION AND PLANS-20.pdf · uploaded 11 Apr 2022Source
- DocumentBUILDING PERMISSION AND PLANS-21.pdf · uploaded 11 Apr 2022Source
- DocumentBUILDING PERMISSION AND PLANS-22.pdf · uploaded 11 Apr 2022Source
Technical (Architect)
Technical (Engineer)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 7/1, 7/2
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, Not sanctioned, Not sanctioned yet, Not santioned yet1,411 units in all
- Address
- 7/1, 7/2, 7/3, 73/4/A, 73/4/B, 73/4/C, 73/2/A, 73/5/A, Titwala, TitwalaPIN 421605
- Village
- Titwala, Kalyan taluka
- Land area for this project
- 59,800 sq m (6,43,681 sq ft)
- Permissible built-up area
- 1,25,166 sq m (13,47,278 sq ft)
- Sanctioned built-up area
- 1,25,166 sq m (13,47,278 sq ft)
- Designated bank account
- 76
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
7/1,7/2,7/3,73/4/A,73/4/B,73/4/C,73/2/A,73/5/A
Boundaries
- North
- S No 73 2b 2c 2d S No 8
- South
- S No 6 S No 73
- East
- S No 8
- West
- S No 5
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking1,411 units
1,003 of 1,411 units booked (71%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Tower 1 | 1BHK | 29.99 sq m · 323 sq ft | 107 | 52 |
| Tower 2 | 1BHK | 29.99 sq m · 323 sq ft | 196 | 107 |
| Tower 3 | 1BHK | 29.99 sq m · 323 sq ft | 198 | 107 |
| Tower 4 | 1BHK | 29.99 sq m · 323 sq ft | 198 | 197 |
| Tower 5 | 1BHK | 29.99 sq m · 323 sq ft | 268 | 266 |
| Tower 6 | 1BHK | 29.99 sq m · 323 sq ft | 268 | 193 |
| Tower 7 | 1BHK | 29.99 sq m · 323 sq ft | 88 | 81 |
| Tower 8 | 1BHK | 29.99 sq m · 323 sq ft | 88 | 0 |
Show all 11 unit rowsShow fewer unit rows
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| — | Not sanctioned | — | 0 | 0 |
| — | Not sanctioned yet | — | 0 | 0 |
| — | Not santioned yet | — | 0 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Ujwal S Bhole | — |
| Chartered accountant | Mukesh Soni | — |
| Chartered accountant | NITIN DHAVAN balaji dhavan | — |
| Engineer | Prathamesh Egade | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Titwala
- Raj Vaibhav ParkRERA PM1330002600949
- Sai Valley ResidencyRERA PR1330002600405
- Vedant Millenia Blue Moon Phase IVRERA PM1330002502281
- Adwait AvanyaRERA PR1330002502050
- Sai VrindavanRERA PM1330002501327
- Anand Homes - Phase 3RERA P51700080465
- Vedaant Ashiyana Building 3 Wing ERERA P51700080354
- Mangalmurti HeightsRERA P51700077306
All 94 projects in Titwala · Compare Kalas Darshan with another project