Tokyo Bay Phase 2B
Deedo IDDP-THN-K2CSCompletion was pushed back 4 months, to Apr 2036; no MahaRERA orders on record; 38% of its units are booked.
Thane (M Corp.), Thane 400615 · by Puranik Tokyo Bay Private Limited
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2036
- This projectRegistered 3 Jul 2025, completion promised 31 Dec 2035, revised to 30 Apr 2036.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationPR1332022500196
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| PR1332022500196 | 3 Jul 2025 | 31 Dec 2035 | 30 Apr 2036 | Puranik Tokyo Bay Private Limited | Project page |
Documents57
1 document held by Deedo, 56 filings listed on MahaRERA's project page
Finance
Legal
- OthersSelf declaration - name change FINAL.pdf · uploaded 30 May 2025Source
- OthersDetails of Encumbrances legal.pdf · uploaded 30 May 2025Source
- Declaration Form BPromoter Declaration.pdf · uploaded 30 May 2025Source
- Declaration Form B21-11a Conveyance Deed.pdf · uploaded 30 May 2025Source
- Declaration Form B22-5 Conveyance Deed.pdf · uploaded 30 May 2025Source
Show all 57 documentsShow fewer documents
Legal
- Declaration Form B20-1 Deed Of Conveyance 1-12.pdf · uploaded 30 May 2025Source
- Declaration Form B20-1 Deed Of Conveyance 13-23.pdf · uploaded 30 May 2025Source
- Declaration Form BConveyance Deed 3621-2019.pdf · uploaded 30 May 2025Source
- Declaration Form BCon Deed 588-2016.pdf · uploaded 30 May 2025Source
- Othersself declaration co-promoter payment.pdf · uploaded 16 Jun 2025Source
- Others1 Rera Disclosure of other Real Estate Organization.pdf · uploaded 26 Jun 2025Source
- Others2 Rera Disclosure of other Real Estate Organization.pdf · uploaded 26 Jun 2025Source
- Others3 Rera Disclosure of other Real Estate Organization.pdf · uploaded 26 Jun 2025Source
- Others4 Rera Disclosure of other Real Estate Organization.pdf · uploaded 26 Jun 2025Source
- OthersTitle Report -TB 2B 26062025.pdf · uploaded 26 Jun 2025Source
- Declaration Form BTitle Report 27062025.pdf · uploaded 28 Jun 2025Source
Migrated
- Withdrawal Update Form 12025-09-30 Architects Certificate FORM-1 TB 2B.pdf · uploaded 23 Jan 2026Source
- Withdrawal Update Form 2Form 2 Engineers Certificate TB2 B1 - 30092025.pdf · uploaded 23 Jan 2026Source
- Withdrawal Update Form 3Mirai - TB - 2B (B1 Bldg).pdf · uploaded 23 Jan 2026Source
- Withdrawal Update Form 1Architects Certificate FORM-1 TB 2B.pdf · uploaded 6 Feb 2026Source
- Withdrawal Update Form 2Form 2 Engineers Certificate TB2 B1.pdf · uploaded 6 Feb 2026Source
- Withdrawal Update Form 3CA Certificates -B1 Final sing.pdf · uploaded 6 Feb 2026Source
- Withdrawal Update Form 1FORM-1 TB 2B.pdf · uploaded 20 Apr 2026Source
- Withdrawal Update Form 2Form 2.pdf · uploaded 20 Apr 2026Source
- Withdrawal Update Form 3CA Certificates -B1 20042026 Final.pdf · uploaded 20 Apr 2026Source
- Withdrawal Update Form 1Form 1 Architects Certificate TB 2B.pdf · uploaded 20 Jul 2026Source
- Withdrawal Update Form 2Form 2 Engineers Certificate TB2 B1.pdf · uploaded 20 Jul 2026Source
- Withdrawal Update Form 3Form 3 CA Certificates -B1.pdf · uploaded 20 Jul 2026Source
- Form 2A (FY 2025-2026)Form 2A TB2B.pdf · uploaded 2 Sep 2026Source
- Form 5 (FY 2025-2026)Form 5Tokyo Bay 2B.pdf · uploaded 29 Sep 2026Source
Technical
- DocumentSanctioned layout.pdf · uploaded 23 May 2025Source
- Document7 Declaration one plot one registration final.pdf · uploaded 30 May 2025Source
- OthersSelf declaration - name change FINAL.pdf · uploaded 30 May 2025Source
- OthersDeclaration about CC (Format D).pdf · uploaded 30 May 2025Source
- DocumentAll Floor plan.pdf · uploaded 16 Jun 2025Source
- DocumentB1 Sheet 1.pdf · uploaded 1 Aug 2025Source
- DocumentB1 Sheet 2.pdf · uploaded 1 Aug 2025Source
- DocumentB1 Sheet 3.pdf · uploaded 1 Aug 2025Source
- DocumentGr floor Parking Plan Sheet 4.pdf · uploaded 1 Aug 2025Source
- DocumentLG 2 Parking - Sheet 5.pdf · uploaded 1 Aug 2025Source
- DocumentLG1 Parking - Sheet 6.pdf · uploaded 1 Aug 2025Source
- OthersArch declaration for CC dt 24072025.pdf · uploaded 1 Aug 2025Source
- DocumentLOI plan.pdf · uploaded 4 Sep 2025Source
- DocumentPLAN-1- Layout.pdf · uploaded 9 Sep 2026Source
- DocumentPLAN-2 Lower Gr 1 Parking Plan.pdf · uploaded 9 Sep 2026Source
- DocumentPLAN-3 - Lower Gr 2 Parking Plan.pdf · uploaded 9 Sep 2026Source
- DocumentPLAN-4 - Gr Stilt Floor Parking Plan.pdf · uploaded 9 Sep 2026Source
- DocumentPLAN-5 Typical Floor Plan.pdf · uploaded 9 Sep 2026Source
- DocumentPLAN-6 Break Pressure and Refuge.pdf · uploaded 9 Sep 2026Source
- OthersArchitect Certificate.pdf · uploaded 9 Sep 2026Source
- OthersCC Declaration.pdf · uploaded 9 Sep 2026Source
- DocumentParking Declaration - B1 Bldg.pdf · uploaded 21 Sep 2026Source
Technical (Architect)
- DocumentForm 1 Architects Certificate TB 2B.pdf · uploaded 20 Jul 2026Source
Technical (Engineer)
- DocumentForm 2 Engineers Certificate TB2 B1.pdf · uploaded 20 Jul 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel on part of the land bearing S.NO. -20/1/B S.NO.20/2/B/1, S.NO.20/2/B/2
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- —373 units in all
- Address
- Ghodbunder Road, Near Euro SchoolPIN 400615
- Village
- Thane (M Corp.), Thane taluka
- Location
- 19.20929, 73.43692
- Land area for this project
- 5,557 sq m (59,815 sq ft)
- Approved layout area
- 19,493 sq m (2,09,816 sq ft)
- Permissible built-up area
- 83,727 sq m (9,01,225 sq ft)
- Sanctioned built-up area
- 23,869 sq m (2,56,924 sq ft)
- Recreational open space
- 5,562 sq m (59,864 sq ft)
- Designated bank account
- 76
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
on part of the land bearing S.NO. -20/1/B S.NO.20/2/B/1,S.NO.20/2/B/2,S.NO. 21/11A, S.NO. - 22/5, S.NO. - 21/9,S.NO. - 23/2/1, S.NO. - 23/3/1, S.NO. - 23/4,S.NO. - 22/1
Boundaries
- North
- S. No. 21/9
- South
- Podium RG
- East
- Building No. B2
- West
- Aarambh Project
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking373 units
373 units registered
| Type | Carpet area | Units |
|---|---|---|
| — | — | 373 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Ameeta Shashank Ambekar | — |
| Engineer | Kedar Yernalkar | — |
| Engineer | Saurabh Raikar | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Thane (M Corp.)
- Metro MilleniaRERA PM1330002602679
- Kalyani Krupa Co.op Hsg Soc LtdRERA PR1330002602399
- Shreeji's Laxmi Jyot CHSLRERA PR1330002602306
- RivantaRERA PM1330002601984
- Shree Gangadhar ChslRERA PM1330002601922
- The Lake CornerRERA PM1330002601899
- Shree AudumbarRERA PR1330002601484
- Shreyas Co-Op Hsg. Soc. Ltd.RERA PR1330002601418
All 898 projects in Thane (M Corp.) · Compare Tokyo Bay Phase 2B with another project