Company or firm · first RERA registration 2017
Puranik Tokyo Bay Private Limited
Deedo IDDD-P63AOf 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 4 mo late.
Projects66 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay4 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases2no insolvency
Delivery record
4 of 6 registrations with dates moved or missed their RERA date · months late against the original promise
6 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Suo motu order | Tokyo Bay Phase - 2ASuo motu order: Secretary, MahaRERA Versus Puranik Buitders Pvt. Ltd. (Suo Motu Case No. 5 of 2018) dated 8th Feb 2018 | 8 Feb 2018 |
| Deregistered | Tokyo Bay Phase - 2CDeregistered: Tokyo Bay Phase - 2C | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Tokyo Bay Phase - 2AP51700000520 | Thane (M Corp.) | Certificate Signed | 30 Dec 2024 | 31 May 2025 | +23 mo* |
| Tokyo Bay Phase - 1P51700000618 | Thane (M Corp.) | Certificate Signed | 30 Oct 2023 | 30 Oct 2023 | On date |
| IKIGAI - Phase 1P51700006605 | Thane | Certificate Signed | 30 Dec 2031 | 30 Apr 2032 | +4 mo |
| Tokyo Bay Phase - 2CP51700020265 | Thane (M Corp.) | Certificate Signed | 28 Feb 2027 | 28 Feb 2027 | On date |
| IKIGAI Phase 2P51700051124 | Thane (M Corp.) | Certificate Signed | 31 Dec 2030 | 30 Apr 2031 | +4 mo |
| Tokyo Bay Phase 2BPR1332022500196 | Thane (M Corp.) | Certificate Signed | 31 Dec 2035 | 30 Apr 2036 | +4 mo |
Puranik Tokyo Bay Private Limited, in questions
Does Puranik Tokyo Bay Private Limited finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.
How many projects has Puranik Tokyo Bay Private Limited registered with MahaRERA?
6 projects under 6 MahaRERA registrations; 1 completed on MahaRERA.
Does Puranik Tokyo Bay Private Limited have MahaRERA regulatory cases?
2 regulatory cases name its registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology