Sai Kanishk
Completion date passedThane (M Corp.), Thane 400612 |Promoter: Om Sai Infra & Om Sai Group
Project summary
As registered with MahaRERA
- RERA registrations
- 2
- Phases
- 2
Location
Coordinates as published by MahaRERA
Also registered as
Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion pushed back 6 years and 3 months
P51700012436The latest completion date on record passed 1 year and 4 months ago.
- Registered
- 1 Sep 2017
- Promised
- 31 Mar 2019
- Revised
- 30 Jun 2025
Completion pushed back 5 months
P51700006847The latest completion date on record passed 8 years and 5 months ago.
- Registered
- 13 Nov 2017
- Promised
- 31 Dec 2017
- Revised
- 31 May 2018
2 RERA registrations
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700012436 | 1 Sep 2017 | 31 Mar 2019 | 30 Jun 2025 | Om Sai Infra & Om Sai Group | Project page |
| P51700006847 | 13 Nov 2017 | 31 Dec 2017 | 31 May 2018 | Om Sai Infra & Om Sai Group | Project page |
Documents
4 documents held by Deedo
Registration certificates
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
What MahaRERA has published about this project. A listing records what the authority published; it is not a judgment of the project.
- Regulatory order24 May 2023Matched by RERA number
Regulatory order: PROJECT NAME: SAI KANISHK PHASE II (Regulatory Case No. 21 of 2023) dated 18 May 2023.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Thane (M Corp.)
Survey, CTS, gat or plot numbers
Source: registration certificates, as stated there.