Om Sai Infra & Om Sai Group
Company or firm · 1 project · 2 MahaRERA registrations
1Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 2 past their proposed date, not extended
+40 moMedian delayvs RERA proposed date · 2 extended
1Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Sai KanishkP51700012436 | Thane (M Corp.) | 2017 | Certificate Signed | 31 Mar 2019 | 30 Jun 2025 | +75 months |
| Sai KanishkP51700006847 | Thane (M Corp.) | 2017 | Certificate Signed | 31 Dec 2017 | 31 May 2018 | +5 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 75 months, for Sai Kanishk (P51700012436).
Regulatory cases across projects
- Regulatory orderRegulatory order: PROJECT NAME: SAI KANISHK PHASE II (Regulatory Case No. 21 of 2023) dated 18 May 2023. · Sai Kanishk · P51700012436 · 24 May 2023
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology