Om Sai Infra & Om Sai Group

Company or firm · 1 project · 2 MahaRERA registrations

1Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 2 past their proposed date, not extended
+40 moMedian delayvs RERA proposed date · 2 extended
1Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Sai KanishkP51700012436Thane (M Corp.)2017Certificate Signed31 Mar 201930 Jun 2025+75 months
Sai KanishkP51700006847Thane (M Corp.)2017Certificate Signed31 Dec 201731 May 2018+5 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Sai Kanishk+75 mo
  • Sai Kanishk+5 mo

Track record notes

  • 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 75 months, for Sai Kanishk (P51700012436).

Regulatory cases across projects

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology