Promised date passed32 floorsRERA P51700005653
Indigo, Orovia Phase 1
Deedo IDDP-THN-2BQ3-INDIGOMahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.
Median saleNot on recordneeds 3 or more sales
Booked87%136 of 157 · MahaRERA
Completion30 Mar 2023as registered
Units & parking in Indigo
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2.5BHK | 64.4 m² (693 sq.ft) | 54 | 44 |
| 2BHK LUXURY | 57.6 m² (619 sq.ft) | 22 | 13 |
| 2BHK LUXURY | 60.7 m² (653 sq.ft) | 27 | 26 |
| 3BHK | 68.4 m² (736 sq.ft) | 54 | 53 |
As registered with MahaRERA
- RERA registration
- P51700005653 · registered 11 Aug 2017
- Promised completion
- 30 Mar 2023
- Revised completion
- 30 Mar 2023
- Sanctioned habitable floors
- 32
- Sanctioned floors (incl. basement, stilt, podium)
- 32
- Units declared
- 0
- Homes
- 0
- Shops and offices
- 0
- MahaRERA status
- Certificate Signed
- Deedo ID
- DP-THN-2BQ3-INDIGO
Questions about Indigo
When is Indigo due for completion?
The MahaRERA registration promises 30 Mar 2023.
How many floors does Indigo have?
32 sanctioned habitable floors, as registered with MahaRERA.
Data through13 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Report a problemMethodology