Certificate SignedThane (M Corp.), Thane 400607 |Promoter: Godrej Properties Limited
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- RERA registrations
- 4
- Phases
- 4
- Buildings
- 5
- Unit types
- 1BHK Onyx, 1BHK Scenic, 2BHK Exotic, 2BHK Luxe, 2BHK Omega, 2 BHK Air, 2 BHK Titan, 3 BHK Air, 3 BHK Aqua, 3 BHK Titan, Shop, 2BHK Regal, 2BHK Supreme, 3BHK Royal, 3BHK Supreme, 3BHK Luxe, 3BHK Premium, 3BHK Regal, 1BHK Premium, 2BHK Premium1,627 units in all
- Address
- 234/1, 234/2, 235, 39, 40, 41/1, Kolshet Road, Dhokali NakaPIN 400607
- Designated bank account
- 220
- Developed in phases
- Yes
Location
Coordinates as published by MahaRERA
Also registered as
Registered transactions
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion pushed back 4 months
P51700034608- Registered
- 20 Apr 2022
- Promised
- 30 Apr 2028
- Revised
- 30 Aug 2028
Completion pushed back 4 months
P51700046541- Registered
- 10 Aug 2022
- Promised
- 31 Dec 2028
- Revised
- 30 Apr 2029
Completion pushed back 4 months
P51700049514- Registered
- 15 Feb 2023
- Promised
- 31 Oct 2029
- Revised
- 28 Feb 2030
Completion pushed back 4 months
P51700053668- Registered
- 21 Nov 2023
- Promised
- 31 Dec 2029
- Revised
- 30 Apr 2030
4 RERA registrations
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700034608 | 20 Apr 2022 | 30 Apr 2028 | 30 Aug 2028 | Godrej Properties Limited | Project page |
| P51700046541 | 10 Aug 2022 | 31 Dec 2028 | 30 Apr 2029 | Godrej Properties Limited | Project page |
| P51700049514 | 15 Feb 2023 | 31 Oct 2029 | 28 Feb 2030 | Godrej Properties Limited | Project page |
| P51700053668 | 21 Nov 2023 | 31 Dec 2029 | 30 Apr 2030 | Godrej Properties Limited | Project page |
5 buildings
Buildings and wings named in the registration
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
1,284 of 1,627 units booked (79%), as the promoter reported to MahaRERA
| RERA | Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|---|
| P51700049514 | Adora | 1BHK Onyx | 37.17 sq m · 400 sq ft | 42 | 9 |
| P51700049514 | Adora | 1BHK Scenic | 36.39 sq m · 392 sq ft | 126 | 29 |
| P51700049514 | Adora | 2BHK Exotic | 55.66 sq m · 599 sq ft | 42 | 42 |
| P51700049514 | Adora | 2BHK Luxe | 54.71 sq m · 589 sq ft | 42 | 42 |
| P51700049514 | Adora | 2BHK Omega | 42.64 sq m · 459 sq ft | 77 | 71 |
| P51700049514 | Adora | 2BHK Omega | 43.38 sq m · 467 sq ft | 84 | 79 |
| P51700049514 | Adora | 2BHK Omega | 43.78 sq m · 471 sq ft | 84 | 75 |
| P51700053668 | Arise | 2 BHK Air | 62.24 sq m · 670 sq ft | 43 | 33 |
Show all 50 unit rowsShow fewer unit rows
| RERA | Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|---|
| P51700053668 | Arise | 2 BHK Titan | 64.72 sq m · 697 sq ft | 35 | 26 |
| P51700053668 | Arise | 3 BHK Air | 84.54 sq m · 910 sq ft | 43 | 32 |
| P51700053668 | Arise | 3 BHK Aqua | 74.67 sq m · 804 sq ft | 88 | 34 |
| P51700053668 | Arise | 3 BHK Titan | 84.99 sq m · 915 sq ft | 43 | 38 |
| P51700053668 | Arise | Shop | 26.2 sq m · 282 sq ft | 1 | 0 |
| P51700053668 | Arise | Shop | 26.77 sq m · 288 sq ft | 1 | 0 |
| P51700053668 | Arise | Shop | 35.75 sq m · 385 sq ft | 1 | 0 |
| P51700053668 | Arise | Shop | 36.3 sq m · 391 sq ft | 1 | 0 |
| P51700053668 | Arise | Shop | 47.5 sq m · 511 sq ft | 1 | 0 |
| P51700053668 | Arise | Shop | 49.8 sq m · 536 sq ft | 1 | 0 |
| P51700053668 | Arise | Shop | 61.21 sq m · 659 sq ft | 1 | 0 |
| P51700053668 | Arise | Shop | 64.87 sq m · 698 sq ft | 1 | 0 |
| P51700053668 | Arise | Shop | 67.1 sq m · 722 sq ft | 1 | 0 |
| P51700053668 | Arise | Shop | 74.48 sq m · 802 sq ft | 1 | 0 |
| P51700053668 | Arise | Shop | 96.59 sq m · 1,040 sq ft | 1 | 0 |
| P51700053668 | Arise | Shop | 111.97 sq m · 1,205 sq ft | 1 | 0 |
| P51700053668 | Arise | Shop | 112.18 sq m · 1,207 sq ft | 1 | 0 |
| P51700053668 | Arise | Shop | 132.04 sq m · 1,421 sq ft | 1 | 0 |
| P51700046541 | Panorama | 2BHK Regal | 55.56 sq m · 598 sq ft | 34 | 34 |
| P51700046541 | Panorama | 2BHK Supreme | 59.22 sq m · 637 sq ft | 41 | 40 |
| P51700046541 | Panorama | 3BHK Royal | 83.32 sq m · 897 sq ft | 82 | 72 |
| P51700046541 | Panorama | 3BHK Supreme | 81.07 sq m · 873 sq ft | 41 | 25 |
| P51700034608 | Tower 2 | 3BHK Luxe | 70.1 sq m · 755 sq ft | 46 | 19 |
| P51700034608 | Tower 2 | 3BHK Premium | 69.31 sq m · 746 sq ft | 113 | 101 |
| P51700034608 | Tower 2 | 3BHK Regal | 80.18 sq m · 863 sq ft | 82 | 72 |
| P51700034608 | Tower 2 | Shop | 33.72 sq m · 363 sq ft | 1 | 0 |
| P51700034608 | Tower 2 | Shop | 45.1 sq m · 485 sq ft | 2 | 1 |
| P51700034608 | Tower 2 | Shop | 46.81 sq m · 504 sq ft | 1 | 0 |
| P51700034608 | Tower 2 | Shop | 48.59 sq m · 523 sq ft | 1 | 1 |
| P51700034608 | Tower 2 | Shop | 60.68 sq m · 653 sq ft | 1 | 1 |
| P51700034608 | Tower 2 | Shop | 60.71 sq m · 653 sq ft | 1 | 1 |
| P51700034608 | Tower 2 | Shop | 61.77 sq m · 665 sq ft | 1 | 0 |
| P51700034608 | Tower 2 | Shop | 69.49 sq m · 748 sq ft | 1 | 1 |
| P51700034608 | Tower 2 | Shop | 84.83 sq m · 913 sq ft | 1 | 1 |
| P51700034608 | Tower 2 | Shop | 100.34 sq m · 1,080 sq ft | 1 | 1 |
| P51700034608 | Tower 2 | Shop | 115.89 sq m · 1,247 sq ft | 1 | 1 |
| P51700034608 | Tower 4 | 1BHK Premium | 35.41 sq m · 381 sq ft | 168 | 161 |
| P51700034608 | Tower 4 | 2BHK Luxe | 53.94 sq m · 581 sq ft | 42 | 42 |
| P51700034608 | Tower 4 | 2BHK Premium | 48.5 sq m · 522 sq ft | 77 | 75 |
| P51700034608 | Tower 4 | 2BHK Premium | 53.01 sq m · 571 sq ft | 42 | 41 |
| P51700034608 | Tower 4 | 2BHK Regal | 53.76 sq m · 579 sq ft | 42 | 42 |
| P51700034608 | Tower 4 | 2BHK Regal | 57.56 sq m · 620 sq ft | 42 | 42 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Documents
4 documents held by Deedo, 695 filings listed on MahaRERA's project page
Registration certificate (4)
Show all 699 documentsShow fewer documents
Legal
- Legal Title reportP51700034608 · Godrej Ascend Phase 1 Title Report 19032022.pdf · uploaded 17 Apr 2022Source
- Declaration Form BP51700034608 · Form B Part 1.pdf · uploaded 17 Apr 2022Source
- Declaration Form BP51700034608 · Form B Part 2.pdf · uploaded 17 Apr 2022Source
- Declaration Form BP51700034608 · Form B Part 3.pdf · uploaded 17 Apr 2022Source
- OtherP51700034608 · Common Areas and Amenities - for upload.pdf · uploaded 18 Apr 2022Source
- Declaration Form BP51700046541 · Form B_upload.pdf · uploaded 11 Jul 2022Source
- Other – LegalP51700046541 · Godrej Ascend - RERA promoter change_compressed2.pdf · uploaded 1 Aug 2022Source
- Legal Title reportP51700046541 · RERA Report dated 29072022 _upload.pdf · uploaded 1 Aug 2022Source
- Declaration Form BP51700049514 · Form B _ Godrej Ascend Phase 3_upload.pdf · uploaded 19 Jan 2023Source
- Legal Title reportP51700049514 · LEGAL TITEL REPORT .pdf · uploaded 6 Feb 2023Source
- Other – LegalP51700053668 · 1 Other – Legal.pdf · uploaded 2 Nov 2023Source
- Other – LegalP51700053668 · 2 Other – Legal.pdf · uploaded 2 Nov 2023Source
- Other – LegalP51700053668 · 3 Other – Legal.pdf · uploaded 2 Nov 2023Source
- Other – LegalP51700053668 · Common Area.pdf · uploaded 2 Nov 2023Source
- Legal Title reportP51700053668 · Legal Title Report.pdf · uploaded 2 Nov 2023Source
- Declaration Form BP51700053668 · Signed Form -B.pdf · uploaded 2 Nov 2023Source
- Other – LegalP51700046541 · Board Resolution Ascend RERA compliance 26 Sep 24.pdf · uploaded 19 Oct 2024Source
- Other – LegalP51700046541 · Board Resolution Ascend RERA compliance 26 Sep 24.pdf · uploaded 19 Oct 2024Source
- Other – LegalP51700046541 · Board Resolution Ascend RERA compliance 26 Sep 24.pdf · uploaded 19 Oct 2024Source
- OtherP51700034608 · Board Resolution Ascend RERA compliance 26 Sep 24.pdf · uploaded 19 Oct 2024Source
- OtherP51700034608 · Board Resolution Ascend RERA compliance 26 Sep 24.pdf · uploaded 19 Oct 2024Source
- OtherP51700034608 · Board Resolution Ascend RERA compliance 26 Sep 24.pdf · uploaded 19 Oct 2024Source
- Other – LegalP51700049514 · Board Resolution Ascend RERA compliance 26 Sep 24.pdf · uploaded 19 Oct 2024Source
- Other – LegalP51700049514 · Board Resolution Ascend RERA compliance 26 Sep 24.pdf · uploaded 19 Oct 2024Source
- Other – LegalP51700049514 · Board Resolution Ascend RERA compliance 26 Sep 24.pdf · uploaded 19 Oct 2024Source
- Other – LegalP51700053668 · Board Resolution Ascend RERA compliance 26 Sep 24.pdf · uploaded 19 Oct 2024Source
- Other – LegalP51700053668 · Board Resolution Ascend RERA compliance 26 Sep 24.pdf · uploaded 19 Oct 2024Source
- Other – LegalP51700053668 · Board Resolution Ascend RERA compliance 26 Sep 24.pdf · uploaded 19 Oct 2024Source
Migrated
- 1 PAN CardP51700034608 · PAN_ePAN_Ceear.pdf · uploaded 17 Apr 2022Source
- 1 Copy of the legal title reportP51700034608 · Godrej Ascend Phase 1 Title Report 19032022.pdf · uploaded 17 Apr 2022Source
- 1 Building Plan Approval / NA Order for plotted developmentP51700034608 · Godrej Ascend - DP CC.pdf · uploaded 17 Apr 2022Source
- 1 Commencement Certificates / NA Order for plotted developmentP51700034608 · Godrej Ascend - DP CC.pdf · uploaded 17 Apr 2022Source
- 1 Declaration in FORM BP51700034608 · Form B Part 1.pdf · uploaded 17 Apr 2022Source
- 2 Declaration in FORM BP51700034608 · Form B Part 2.pdf · uploaded 17 Apr 2022Source
- 3 Declaration in FORM BP51700034608 · Form B Part 3.pdf · uploaded 17 Apr 2022Source
- 1 CERSAI detailsP51700034608 · CERSAI_Search_Report_200235264343_For_Asset_Based_Search_17_04_2022_11_42_46_503.pdf · uploaded 17 Apr 2022Source
- 1 Proforma of Allotment letterP51700034608 · Application form allotment letter - for upload.pdf · uploaded 17 Apr 2022Source
- 2 Proforma of Allotment letterP51700034608 · Agreement for Sale - for upload.pdf · uploaded 17 Apr 2022Source
- 1 Details of encumbrancesP51700034608 · Non Encumbrance Certificate - for upload.pdf · uploaded 18 Apr 2022Source
- 1 Copy of Layout Approval (in case of layout)P51700034608 · Layout - compressed for upload.pdf · uploaded 18 Apr 2022Source
- 1 Declaration about Commencement CertificateP51700034608 · CC declaration - for upload.pdf · uploaded 18 Apr 2022Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700034608 · Architect certificate - for upload stamped.pdf · uploaded 18 Apr 2022Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700034608 · Engineer certificate - for upload stamped.pdf · uploaded 18 Apr 2022Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700034608 · CA certificate - for upload - stamped.pdf · uploaded 18 Apr 2022Source
- 1 OtherP51700034608 · Common Areas and Amenities - for upload.pdf · uploaded 18 Apr 2022Source
- 1 PAN CardP51700046541 · GPL_PAN Card.pdf · uploaded 11 Jul 2022Source
- 1 Copy of Layout Approval (in case of layout)P51700046541 · Layout Phase-II_upload.pdf · uploaded 11 Jul 2022Source
- 1 Commencement Certificates / NA Order for plotted developmentP51700046541 · Godrej Ascend - DP CC_upload.pdf · uploaded 11 Jul 2022Source
- 1 Declaration about Commencement CertificateP51700046541 · CC declaration new_upload.pdf · uploaded 11 Jul 2022Source
- 1 Declaration in FORM BP51700046541 · Form B_upload.pdf · uploaded 11 Jul 2022Source
- 1 CERSAI detailsP51700046541 · CERSAI_Search_Report_200242253182_For_Asset_Based_Search_15_07_2022_17_16_04_293.pdf · uploaded 15 Jul 2022Source
- 1 Proforma of Allotment letterP51700046541 · 19072022 Application Form - For RERA_upload.pdf · uploaded 20 Jul 2022Source
- 2 Proforma of Allotment letterP51700046541 · 19072022 Allotment Letter - For RERA_upload.pdf · uploaded 20 Jul 2022Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameP51700046541 · Non Encumbrance Certificate GPL Bank Account_upload.pdf · uploaded 25 Jul 2022Source
- 1 a Details of encumbrances concerned to FinanceP51700046541 · Non Encumbrance Certificate GPL _upload.pdf · uploaded 26 Jul 2022Source
- 1 b Details of encumbrances concerned to LegalP51700046541 · Non Encumbrance Certificate GPL LEGAL _upload.pdf · uploaded 26 Jul 2022Source
- 1 Deviation Report with respect to Allotment letterP51700046541 · 20072022 Deviation Report Allotment Letter - For RERA.pdf · uploaded 26 Jul 2022Source
- 1 Building Plan Approval / NA Order for plotted developmentP51700046541 · 13_compressed.pdf · uploaded 27 Jul 2022Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700046541 · CA Certificate Godrej Ascend Phase II_upload.pdf · uploaded 27 Jul 2022Source
- 1 Other – TechnicalP51700046541 · Godrej Ascend - RERA promoter change_compressed2.pdf · uploaded 27 Jul 2022Source
- 1 Copy of the legal title reportP51700046541 · RERA Report dated 29072022 _upload.pdf · uploaded 1 Aug 2022Source
- 3 Proforma of Allotment letterP51700046541 · 28072022 Agreement for Sale -for RERA_upload.pdf · uploaded 1 Aug 2022Source
- 1 Deviation Report with respect to model copy of AgreementP51700046541 · 29072022 Deviation Report AFS - For RERA-1-12.pdf · uploaded 1 Aug 2022Source
- 2 Deviation Report with respect to model copy of AgreementP51700046541 · 29072022 Deviation Report AFS - For RERA-13-25.pdf · uploaded 1 Aug 2022Source
- 1 Other – LegalP51700046541 · Godrej Ascend - RERA promoter change_compressed2.pdf · uploaded 1 Aug 2022Source
- 2 Building Plan Approval / NA Order for plotted developmentP51700046541 · 13_compressed.pdf · uploaded 23 Aug 2022Source
- 2 Commencement Certificates / NA Order for plotted developmentP51700046541 · Amended CC 03 08 2022.pdf · uploaded 23 Aug 2022Source
- 2 Declaration about Commencement CertificateP51700046541 · CC declaration new_upload.pdf · uploaded 23 Aug 2022Source
- 1 PAN CardP51700049514 · GPL_PAN Card.pdf · uploaded 16 Jan 2023Source
- 1 Building Plan Approval / NA Order for plotted developmentP51700049514 · Building Plan_Pg21_Upload.pdf · uploaded 16 Jan 2023Source
- 1 Commencement Certificates / NA Order for plotted developmentP51700049514 · Amended CC 03 08 2022.pdf · uploaded 16 Jan 2023Source
- 1 Declaration about Commencement CertificateP51700049514 · CC declaration new_upload.pdf · uploaded 16 Jan 2023Source
- 1 Proforma of Allotment letterP51700049514 · Application Form - 13012023_upload.pdf · uploaded 16 Jan 2023Source
- 2 Proforma of Allotment letterP51700049514 · 12012023 Allotment - with Highlights_upload.pdf · uploaded 16 Jan 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameP51700049514 · Non Encumbrance Certificate GPL Bank Account 10012023_upload.pdf · uploaded 16 Jan 2023Source
- 1 Deviation Report with respect to Allotment letterP51700049514 · 12012023 Deviation Report Allotment Letter_upload.pdf · uploaded 16 Jan 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700049514 · RERA certificate Ph 3 -Dec-22_R1_upload.pdf · uploaded 18 Jan 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700049514 · GODREJ ASCEND_PHASE3_CERTIFICATE DEC' 22-Final_upload.pdf · uploaded 18 Jan 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700049514 · CA CERTIFICATE_stamped_upload.pdf · uploaded 18 Jan 2023Source
- 1 Declaration in FORM BP51700049514 · Form B _ Godrej Ascend Phase 3_upload.pdf · uploaded 19 Jan 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsP51700049514 · Promoter Declaration_upload.pdf · uploaded 23 Jan 2023Source
- 1 Other – TechnicalP51700049514 · Other Technical_upload.pdf · uploaded 23 Jan 2023Source
- 1 a Details of encumbrances concerned to FinanceP51700049514 · Non Encumbrance Certificate Legal and Finance 30012023 _upload.pdf · uploaded 31 Jan 2023Source
- 1 b Details of encumbrances concerned to LegalP51700049514 · Non Encumbrance Certificate Legal and Finance 30012023 _upload.pdf · uploaded 31 Jan 2023Source
- 1 CERSAI detailsP51700049514 · CERSAI_Search_Report_200258949354_For_Asset_Based_Search_30_01_2023_14_35_18_103.pdf · uploaded 31 Jan 2023Source
- 1 Copy of the legal title reportP51700049514 · LEGAL TITEL REPORT .pdf · uploaded 6 Feb 2023Source
- 1 Copy of Layout Approval (in case of layout)P51700049514 · Layout ph3_uploadfile1.pdf · uploaded 6 Feb 2023Source
- 2 Copy of Layout Approval (in case of layout)P51700049514 · Layout ph3_uploadfile2.pdf · uploaded 6 Feb 2023Source
- 1 Proforma of Agreement for saleP51700049514 · 31012023 AFS- With Highlights_upload.pdf · uploaded 6 Feb 2023Source
- 1 Deviation Report with respect to model copy of AgreementP51700049514 · 31012023 Deviation Report AFS_upload-1-7.pdf · uploaded 6 Feb 2023Source
- 2 Deviation Report with respect to model copy of AgreementP51700049514 · 31012023 Deviation Report AFS_upload-8-14.pdf · uploaded 6 Feb 2023Source
- 3 Deviation Report with respect to model copy of AgreementP51700049514 · 31012023 Deviation Report AFS_upload-15-21.pdf · uploaded 6 Feb 2023Source
- 4 Deviation Report with respect to model copy of AgreementP51700049514 · 31012023 Deviation Report AFS_upload-22-28.pdf · uploaded 6 Feb 2023Source
- 2 a Details of encumbrances concerned to FinanceP51700049514 · Non Encumbrance Certificate Legal and Finance 090223.pdf · uploaded 9 Feb 2023Source
- 2 b Details of encumbrances concerned to LegalP51700049514 · Non Encumbrance Certificate Legal and Finance 090223.pdf · uploaded 9 Feb 2023Source
- 2 Building Plan Approval / NA Order for plotted developmentP51700049514 · Building Plan_Pg22_Upload.pdf · uploaded 9 Feb 2023Source
- 3 Building Plan Approval / NA Order for plotted developmentP51700049514 · Building Plan_Pg23_Upload.pdf · uploaded 9 Feb 2023Source
- 4 Building Plan Approval / NA Order for plotted developmentP51700049514 · Building Plan_Pg24_Upload.pdf · uploaded 9 Feb 2023Source
- 3 Proforma of Allotment letterP51700049514 · Application Form - 10032023_upload.pdf · uploaded 10 Mar 2023Source
- 2 Proforma of Agreement for saleP51700049514 · 10032023 AFS- With Highlights_upload.pdf · uploaded 10 Mar 2023Source
- 3 Commencement Certificates / NA Order for plotted developmentP51700046541 · Ascend amended Permission and Full CC.pdf · uploaded 1 Apr 2023Source
- 2 Commencement Certificates / NA Order for plotted developmentP51700049514 · Ascend amended Permission and Full CC.pdf · uploaded 1 Apr 2023Source
- 3 Declaration about Commencement CertificateP51700046541 · Ascend - CC Declaration Phase 2.pdf · uploaded 12 Apr 2023Source
- 2 Declaration about Commencement CertificateP51700049514 · Ascend - CC declaration Phase 3.pdf · uploaded 12 Apr 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700049514 · Architect Certificate Jun2023_upload.pdf · uploaded 6 Sep 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700049514 · Engineer Certificate Jun2023_upload.pdf · uploaded 6 Sep 2023Source
- 1 Disclosure of sold/ booked inventoryP51700049514 · Ascend Ph3 - Disclosure of sold inventory Jun23_upload.pdf · uploaded 6 Sep 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700049514 · CA Certificate Jun2023_upload.pdf · uploaded 6 Sep 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)P51700046541 · Phase 2 signed FORM 5_upload.pdf · uploaded 12 Sep 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)P51700034608 · Phase 1 signed FORM 5_upload.pdf · uploaded 12 Sep 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)P51700049514 · Phase 3 signed FORM 5_upload.pdf · uploaded 12 Sep 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700046541 · Ascend_Ph2_Arch Cert_Sep23_upload.pdf · uploaded 26 Oct 2023Source
- 1 Disclosure of sold/ booked inventoryP51700046541 · Godrej Ascend Phase 2_compressed_upload.pdf · uploaded 26 Oct 2023Source
- 1 Disclosure of sold/ booked inventoryP51700034608 · Godrej Ascend Phase 1_compressed_upload.pdf · uploaded 26 Oct 2023Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700049514 · Ascend_Ph3_Arch Cert_Sep23_upload.pdf · uploaded 26 Oct 2023Source
- 2 Disclosure of sold/ booked inventoryP51700049514 · Godrej Ascend Phase 3_compressed_upload.pdf · uploaded 26 Oct 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700046541 · PH 2_Engg Cert_Sep23_upload.pdf · uploaded 27 Oct 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700046541 · PH 2_CA Cert_Sep23_upload.pdf · uploaded 27 Oct 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700034608 · PH 1_Engg Cert_Sep23_upload.pdf · uploaded 27 Oct 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700034608 · PH 1_CA Cert_Sep23_upload.pdf · uploaded 27 Oct 2023Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700049514 · PH 3_Engg Cert_Sep23_upload.pdf · uploaded 27 Oct 2023Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700049514 · PH 3_CA Cert_Sep23_upload.pdf · uploaded 27 Oct 2023Source
- 1 PAN CardP51700053668 · 1 PAN Card.pdf · uploaded 2 Nov 2023Source
- 1 Copy of the legal title reportP51700053668 · Legal Title Report.pdf · uploaded 2 Nov 2023Source
- 1 a Details of encumbrances concerned to FinanceP51700053668 · Non Encumbrance Cer.pdf · uploaded 2 Nov 2023Source
- 1 b Details of encumbrances concerned to LegalP51700053668 · Non Encumbrance Cer.pdf · uploaded 2 Nov 2023Source
- 1 Copy of Layout Approval (in case of layout)P51700053668 · 1 GFA LAYOUT 01112023 Model NEW.pdf · uploaded 2 Nov 2023Source
- 2 Copy of Layout Approval (in case of layout)P51700053668 · 1 GFA LAYOUT 01112023 1 R.pdf · uploaded 2 Nov 2023Source
- 1 Building Plan Approval / NA Order for plotted developmentP51700053668 · Sheet 01_compressed_11zon.pdf · uploaded 2 Nov 2023Source
- 2 Building Plan Approval / NA Order for plotted developmentP51700053668 · Sheet 02_compressed.pdf · uploaded 2 Nov 2023Source
- 3 Building Plan Approval / NA Order for plotted developmentP51700053668 · Sheet 03_compressed.pdf · uploaded 2 Nov 2023Source
- 4 Building Plan Approval / NA Order for plotted developmentP51700053668 · Sheet 04_compressed.pdf · uploaded 2 Nov 2023Source
- 5 Building Plan Approval / NA Order for plotted developmentP51700053668 · Sheet 05_compressed.pdf · uploaded 2 Nov 2023Source
- 6 Building Plan Approval / NA Order for plotted developmentP51700053668 · Sheet 06_compressed.pdf · uploaded 2 Nov 2023Source
- 7 Building Plan Approval / NA Order for plotted developmentP51700053668 · Sheet 07_compressed.pdf · uploaded 2 Nov 2023Source
- 1 Commencement Certificates / NA Order for plotted developmentP51700053668 · Ascend amended CC for Tower 01112023.pdf · uploaded 2 Nov 2023Source
- 1 Declaration about Commencement CertificateP51700053668 · 02112023 CC declaration new 430 PM.pdf · uploaded 2 Nov 2023Source
- 1 Declaration in FORM BP51700053668 · Signed Form -B.pdf · uploaded 2 Nov 2023Source
- 1 CERSAI detailsP51700053668 · CERSAI_Search_Report_200285544961_For_Asset_Based_Search_02_11_2023_13_28_30_978.pdf · uploaded 2 Nov 2023Source
- 2 CERSAI detailsP51700053668 · 02112023 CERSAI Declaration V1 416 PM.pdf · uploaded 2 Nov 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700053668 · CA Certificate.pdf · uploaded 2 Nov 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsP51700053668 · Annexure - A.pdf · uploaded 2 Nov 2023Source
- 1 Proforma of Agreement for saleP51700053668 · 02112023 AFS V1 at 311 PM.pdf · uploaded 2 Nov 2023Source
- 1 Proforma of Allotment letterP51700053668 · 02112023 Allotment - with Highlights V1 450PM.pdf · uploaded 2 Nov 2023Source
- 2 Proforma of Allotment letterP51700053668 · 02112023 Application Form V1 327PM.pdf · uploaded 2 Nov 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameP51700053668 · 02112023 Non Encumbrance Certificate GPL Bank Account V1 500PM.pdf · uploaded 2 Nov 2023Source
- 1 Deviation Report with respect to Allotment letterP51700053668 · 02112023 Deviation Report Allotment Letter V1504PM.pdf · uploaded 2 Nov 2023Source
- 1 Deviation Report with respect to model copy of AgreementP51700053668 · 02112023 Deviation Report AFS_scan-1-16.pdf · uploaded 2 Nov 2023Source
- 2 Deviation Report with respect to model copy of AgreementP51700053668 · 02112023 Deviation Report AFS_scan-17-32.pdf · uploaded 2 Nov 2023Source
- 1 Other – LegalP51700053668 · 1 Other – Legal.pdf · uploaded 2 Nov 2023Source
- 2 Other – LegalP51700053668 · 2 Other – Legal.pdf · uploaded 2 Nov 2023Source
- 3 Other – LegalP51700053668 · 3 Other – Legal.pdf · uploaded 2 Nov 2023Source
- 4 Other – LegalP51700053668 · Common Area.pdf · uploaded 2 Nov 2023Source
- 1 Other – TechnicalP51700053668 · 32 - EXT_RERA Compliance - Godrej Ascend.pdf · uploaded 2 Nov 2023Source
- 3 Copy of Layout Approval (in case of layout)P51700053668 · 1 GFA LAYOUT 08112023 Ph4 T1 Highlighted.pdf · uploaded 8 Nov 2023Source
- 2 Copy of Layout Approval (in case of layout)P51700034608 · Layout Approval_Tower 5.pdf · uploaded 5 Jan 2024Source
- 3 Copy of Layout Approval (in case of layout)P51700034608 · Layout Approval_Tower 5.pdf · uploaded 5 Jan 2024Source
- 2 Building Plan Approval / NA Order for plotted developmentP51700034608 · Ascend amended Permission and Full CC.pdf · uploaded 5 Jan 2024Source
- 2 Commencement Certificates / NA Order for plotted developmentP51700034608 · Ascend amended Permission and Full CC.pdf · uploaded 5 Jan 2024Source
- 2 Declaration about Commencement CertificateP51700034608 · CC declaration_Phase 1.pdf · uploaded 5 Jan 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700034608 · Ascend_Ph1_Arch Cert_Sep23_upload.pdf · uploaded 5 Jan 2024Source
- 4 Copy of Layout Approval (in case of layout)P51700034608 · Layout Approval_Phase 1.pdf · uploaded 8 Jan 2024Source
- 3 Building Plan Approval / NA Order for plotted developmentP51700034608 · T2 Sheet 5.pdf · uploaded 8 Jan 2024Source
- 4 Building Plan Approval / NA Order for plotted developmentP51700034608 · T2 Sheet 6.pdf · uploaded 8 Jan 2024Source
- 5 Building Plan Approval / NA Order for plotted developmentP51700034608 · T2 Sheet 7.pdf · uploaded 8 Jan 2024Source
- 6 Building Plan Approval / NA Order for plotted developmentP51700034608 · T2 Sheet 8.pdf · uploaded 8 Jan 2024Source
- 7 Building Plan Approval / NA Order for plotted developmentP51700034608 · T2 Sheet 9.pdf · uploaded 8 Jan 2024Source
- 8 Building Plan Approval / NA Order for plotted developmentP51700034608 · T2 Sheet 10.pdf · uploaded 8 Jan 2024Source
- 9 Building Plan Approval / NA Order for plotted developmentP51700034608 · T2 Sheet 11.pdf · uploaded 8 Jan 2024Source
- 10 Building Plan Approval / NA Order for plotted developmentP51700034608 · T4 Sheet 15.pdf · uploaded 8 Jan 2024Source
- 11 Building Plan Approval / NA Order for plotted developmentP51700034608 · T4 Sheet 16.pdf · uploaded 8 Jan 2024Source
- 12 Building Plan Approval / NA Order for plotted developmentP51700034608 · T4 Sheet 17.pdf · uploaded 8 Jan 2024Source
- 13 Building Plan Approval / NA Order for plotted developmentP51700034608 · T4 Sheet 18.pdf · uploaded 8 Jan 2024Source
- 14 Building Plan Approval / NA Order for plotted developmentP51700034608 · T4 Sheet 19.pdf · uploaded 8 Jan 2024Source
- 15 Building Plan Approval / NA Order for plotted developmentP51700034608 · T4 Sheet 20.pdf · uploaded 8 Jan 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700034608 · Ph 1 Dec 22_upload.pdf · uploaded 8 Jan 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700034608 · Ph 1 Sep 22_upload.pdf · uploaded 8 Jan 2024Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700034608 · Ph 1 Mar 23_upload.pdf · uploaded 8 Jan 2024Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700034608 · Ph 1 Jun 23_upload.pdf · uploaded 8 Jan 2024Source
- 4 Commencement Certificates / NA Order for plotted developmentP51700046541 · CC 011123_compressed_upload.pdf · uploaded 9 Jan 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700046541 · Ph 2 Sep 22_upload.pdf · uploaded 9 Jan 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700046541 · Ph 2 Dec 22_upload.pdf · uploaded 9 Jan 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700046541 · Ph 2 Mar 23_upload.pdf · uploaded 9 Jan 2024Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700046541 · Ph 2 Jun 23_upload.pdf · uploaded 9 Jan 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700046541 · Ph 2 Sep 22_upload.pdf · uploaded 9 Jan 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700046541 · Ph 2 Dec 22_upload.pdf · uploaded 9 Jan 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700046541 · Ph 2 Mar 23_upload.pdf · uploaded 9 Jan 2024Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700046541 · Ph 2 Jun 23_upload.pdf · uploaded 9 Jan 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700046541 · Ph 2 Sep 22_compressed_upload.pdf · uploaded 9 Jan 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700046541 · Ph 2 Dec 22_compressed_upload.pdf · uploaded 9 Jan 2024Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700046541 · Ph 2 Mar 23_compressed_upload.pdf · uploaded 9 Jan 2024Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700046541 · Ph 2 Jun 23_compressed_upload.pdf · uploaded 9 Jan 2024Source
- 3 Commencement Certificates / NA Order for plotted developmentP51700034608 · CC 011123_compressed_upload.pdf · uploaded 9 Jan 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700034608 · Ph 1 Sept 22_upload.pdf · uploaded 9 Jan 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700034608 · Ph 1 Dec 22_upload.pdf · uploaded 9 Jan 2024Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700034608 · Ph 1 Mar 23_upload.pdf · uploaded 9 Jan 2024Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700034608 · Ph 1 Jun 23_upload.pdf · uploaded 9 Jan 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700034608 · Ph 1 Sep 22_compressed_upload.pdf · uploaded 9 Jan 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700034608 · Ph 1 Dec 22_compressed_upload.pdf · uploaded 9 Jan 2024Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700034608 · Ph 1 Mar 23_compressed.pdf · uploaded 9 Jan 2024Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700034608 · Ph 1 Jun 23_compressed_upload.pdf · uploaded 9 Jan 2024Source
- 3 Commencement Certificates / NA Order for plotted developmentP51700049514 · CC 011123_compressed_upload.pdf · uploaded 9 Jan 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700049514 · Ph 3 Mar 23_upload.pdf · uploaded 9 Jan 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700049514 · Ph 3 Mar 23_compressed_upload.pdf · uploaded 9 Jan 2024Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700034608 · Ph 1 Jun 22_upload.pdf · uploaded 15 Jan 2024Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700034608 · 2022 06 Ph 1 Jun 22_compressed_upload.pdf · uploaded 15 Jan 2024Source
- 1 Proforma of Agreement for saleP51700034608 · Proforma of AFS_upload.pdf · uploaded 15 Jan 2024Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700046541 · Ph 2 Dec 23_signed.pdf · uploaded 16 Jan 2024Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700046541 · Ph 2 Dec 23_signed.pdf · uploaded 16 Jan 2024Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700034608 · Ph 1 Jun 22_upload.pdf · uploaded 16 Jan 2024Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700034608 · Ph 1 Dec 23_signed.pdf · uploaded 16 Jan 2024Source
- 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700034608 · Ph 1 Dec 23_signed.pdf · uploaded 16 Jan 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)P51700034608 · Godrej Ascend_Form 2A_FY23_upload.pdf · uploaded 16 Jan 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700049514 · Ph 3 Dec 23_signed.pdf · uploaded 16 Jan 2024Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700049514 · Ph 3 Dec 23_signed.pdf · uploaded 16 Jan 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700053668 · Ph 4 Dec 23_signed.pdf · uploaded 16 Jan 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700053668 · Ph 4 Dec_signed.pdf · uploaded 16 Jan 2024Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700034608 · Ph 1 CA_compressed_upload.pdf · uploaded 19 Jan 2024Source
- 2 Disclosure of sold/ booked inventoryP51700046541 · Ph 2_signed.pdf · uploaded 22 Jan 2024Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700046541 · Ph 2 CA_signed.pdf · uploaded 22 Jan 2024Source
- 2 Disclosure of sold/ booked inventoryP51700034608 · Ph 1_signed.pdf · uploaded 22 Jan 2024Source
- 3 Disclosure of sold/ booked inventoryP51700049514 · Ph 3_signed.pdf · uploaded 22 Jan 2024Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700049514 · Ph 3 CA_signed.pdf · uploaded 22 Jan 2024Source
- 1 Disclosure of sold/ booked inventoryP51700053668 · Ph 4_signed.pdf · uploaded 22 Jan 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700053668 · Ph 4 CA_signed.pdf · uploaded 22 Jan 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)P51700046541 · Ph 2_Form 2A_signed.pdf · uploaded 23 Jan 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)P51700049514 · Ph 3_Form 2A_signed.pdf · uploaded 23 Jan 2024Source
- 1 Status of Formation of Legal Entity (Society/Co Op etc.)P51700034608 · Society Name Reservation Certificate - Ascend Tower 2.pdf · uploaded 25 Jan 2024Source
- 1 Home Buyer /Allottee Grievance Redressal CellP51700046541 · Home Buyer Allottee Grievance Redressal Cell Godrej Ascend Phase 2.pdf · uploaded 29 Jan 2024Source
- 1 Home Buyer /Allottee Grievance Redressal CellP51700034608 · Home Buyer Allottee Grievance Redressal Cell Godrej Ascend Phase 1.pdf · uploaded 29 Jan 2024Source
- 1 Home Buyer /Allottee Grievance Redressal CellP51700049514 · Home Buyer Allottee Grievance Redressal Cell Godrej Ascend Phase 3.pdf · uploaded 29 Jan 2024Source
- 1 Home Buyer /Allottee Grievance Redressal CellP51700053668 · Home Buyer Allottee Grievance Redressal Cell Godrej Ascend Phase 4.pdf · uploaded 29 Jan 2024Source
- 5 Copy of Layout Approval (in case of layout)P51700034608 · Phase 1 Retail Correction _Layout.pdf · uploaded 5 Feb 2024Source
- 6 Copy of Layout Approval (in case of layout)P51700034608 · Phase 1 Retail Correction _Layout-2.pdf · uploaded 5 Feb 2024Source
- 1 Status of Formation of Legal Entity (Society/Co Op etc.)P51700046541 · Society Name Reservation Certificate Ascend Tower 3.pdf · uploaded 15 Feb 2024Source
- 2 Status of Formation of Legal Entity (Society/Co Op etc.)P51700034608 · Society Name Reservation Certificate - Ascend Tower 4.pdf · uploaded 15 Feb 2024Source
- 1 Status of Formation of Legal Entity (Society/Co Op etc.)P51700049514 · Society Name Reservation Certificate - Ascend Tower 5.pdf · uploaded 15 Feb 2024Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700046541 · Arch Ph 2_signed.pdf · uploaded 19 Apr 2024Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700046541 · Engg_Ph2_signed.pdf · uploaded 19 Apr 2024Source
- 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700034608 · Arch Ph 1_signed.pdf · uploaded 19 Apr 2024Source
- 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700034608 · Engg_Ph1_signed.pdf · uploaded 19 Apr 2024Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700049514 · Arch Ph 3_signed.pdf · uploaded 19 Apr 2024Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700049514 · Engg_Ph3_signed.pdf · uploaded 19 Apr 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700053668 · Arch Ph 4_signed.pdf · uploaded 19 Apr 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700053668 · Engg_Ph4_signed.pdf · uploaded 19 Apr 2024Source
- 2 Copy of Layout Approval (in case of layout)P51700046541 · Sheet -1 Layout_upload.pdf · uploaded 22 Apr 2024Source
- 3 Building Plan Approval / NA Order for plotted developmentP51700046541 · Sheet -15_T3.pdf · uploaded 22 Apr 2024Source
- 4 Building Plan Approval / NA Order for plotted developmentP51700046541 · Sheet -16_T3.pdf · uploaded 22 Apr 2024Source
- 5 Building Plan Approval / NA Order for plotted developmentP51700046541 · Sheet -17_T3.pdf · uploaded 22 Apr 2024Source
- 5 Commencement Certificates / NA Order for plotted developmentP51700046541 · Amended DP CC 26032024_upload.pdf · uploaded 22 Apr 2024Source
- 4 Declaration about Commencement CertificateP51700046541 · CC declaration_Ph2_signed.pdf · uploaded 22 Apr 2024Source
- 3 Disclosure of sold/ booked inventoryP51700046541 · Ph 2_signed.pdf · uploaded 22 Apr 2024Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700046541 · CA Ph 2_signed.pdf · uploaded 22 Apr 2024Source
- 7 Copy of Layout Approval (in case of layout)P51700034608 · Sheet -1 Layout_upload.pdf · uploaded 22 Apr 2024Source
- 16 Building Plan Approval / NA Order for plotted developmentP51700034608 · Sheet -8_T2.pdf · uploaded 22 Apr 2024Source
- 17 Building Plan Approval / NA Order for plotted developmentP51700034608 · Sheet -9_T2.pdf · uploaded 22 Apr 2024Source
- 18 Building Plan Approval / NA Order for plotted developmentP51700034608 · Sheet -10_T2.pdf · uploaded 22 Apr 2024Source
- 19 Building Plan Approval / NA Order for plotted developmentP51700034608 · Sheet -11_T2.pdf · uploaded 22 Apr 2024Source
- 20 Building Plan Approval / NA Order for plotted developmentP51700034608 · Sheet -12_T2.pdf · uploaded 22 Apr 2024Source
- 21 Building Plan Approval / NA Order for plotted developmentP51700034608 · Sheet -13_T2.pdf · uploaded 22 Apr 2024Source
- 22 Building Plan Approval / NA Order for plotted developmentP51700034608 · Sheet -14_T2.pdf · uploaded 22 Apr 2024Source
- 4 Commencement Certificates / NA Order for plotted developmentP51700034608 · Amended DP CC 26032024_upload.pdf · uploaded 22 Apr 2024Source
- 3 Disclosure of sold/ booked inventoryP51700034608 · Ph 1_signed.pdf · uploaded 22 Apr 2024Source
- 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700034608 · CA Ph 1_signed.pdf · uploaded 22 Apr 2024Source
- 3 Copy of Layout Approval (in case of layout)P51700049514 · Sheet -1 Layout_upload.pdf · uploaded 22 Apr 2024Source
- 5 Building Plan Approval / NA Order for plotted developmentP51700049514 · Sheet -18_T5.pdf · uploaded 22 Apr 2024Source
- 6 Building Plan Approval / NA Order for plotted developmentP51700049514 · Sheet -19_T5.pdf · uploaded 22 Apr 2024Source
- 7 Building Plan Approval / NA Order for plotted developmentP51700049514 · Sheet -20_T5.pdf · uploaded 22 Apr 2024Source
- 8 Building Plan Approval / NA Order for plotted developmentP51700049514 · Sheet -21_T5.pdf · uploaded 22 Apr 2024Source
- 4 Commencement Certificates / NA Order for plotted developmentP51700049514 · Amended DP CC 26032024_upload.pdf · uploaded 22 Apr 2024Source
- 3 Declaration about Commencement CertificateP51700049514 · CC declaration_Ph3_signed.pdf · uploaded 22 Apr 2024Source
- 4 Disclosure of sold/ booked inventoryP51700049514 · Ph 3_signed_upload.pdf · uploaded 22 Apr 2024Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700049514 · CA Ph 3_signed.pdf · uploaded 22 Apr 2024Source
- 4 Copy of Layout Approval (in case of layout)P51700053668 · Sheet -1 Layout.pdf · uploaded 22 Apr 2024Source
- 8 Building Plan Approval / NA Order for plotted developmentP51700053668 · Sheet -2_T1.pdf · uploaded 22 Apr 2024Source
- 9 Building Plan Approval / NA Order for plotted developmentP51700053668 · Sheet -3_T1.pdf · uploaded 22 Apr 2024Source
- 10 Building Plan Approval / NA Order for plotted developmentP51700053668 · Sheet -4_T1.pdf · uploaded 22 Apr 2024Source
- 11 Building Plan Approval / NA Order for plotted developmentP51700053668 · Sheet -5_T1.pdf · uploaded 22 Apr 2024Source
- 12 Building Plan Approval / NA Order for plotted developmentP51700053668 · Sheet -6_T1.pdf · uploaded 22 Apr 2024Source
- 13 Building Plan Approval / NA Order for plotted developmentP51700053668 · Sheet -7_T1.pdf · uploaded 22 Apr 2024Source
- 2 Commencement Certificates / NA Order for plotted developmentP51700053668 · Ascend Amended Permission and CC 26032024.pdf · uploaded 22 Apr 2024Source
- 2 Declaration about Commencement CertificateP51700053668 · CC declaration_Ph4_signed.pdf · uploaded 22 Apr 2024Source
- 2 Disclosure of sold/ booked inventoryP51700053668 · Ph 4_signed.pdf · uploaded 22 Apr 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700053668 · CA Ph 4_signed.pdf · uploaded 22 Apr 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)P51700046541 · Form 2A_Ph2_FY24_signed.pdf · uploaded 17 Jun 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)P51700034608 · Form 2A_Ph1_FY24_signed.pdf · uploaded 17 Jun 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)P51700049514 · Form 2A_Ph3_FY24_signed.pdf · uploaded 17 Jun 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)P51700053668 · Form 2A_Ph4_FY24_signed.pdf · uploaded 1 Jul 2024Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700046541 · Ascend_Ph2_Jun24_signed.pdf · uploaded 17 Jul 2024Source
- 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700034608 · Ascend_Ph1_Jun24_signed.pdf · uploaded 17 Jul 2024Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700049514 · Ascend_Ph3_Jun24_signed.pdf · uploaded 17 Jul 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700053668 · Ascend_Ph4_Jun24_signed.pdf · uploaded 17 Jul 2024Source
- 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700046541 · Ascend_Ph2_Jun24_signed.pdf · uploaded 18 Jul 2024Source
- 4 Disclosure of sold/ booked inventoryP51700046541 · Inventory Disclosure_Ph2_signed.pdf · uploaded 18 Jul 2024Source
- 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700046541 · CA cert_Ph2_Jun24_signed.pdf · uploaded 18 Jul 2024Source
- 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700034608 · Ascend_Ph1_Jun24_signed.pdf · uploaded 18 Jul 2024Source
- 4 Disclosure of sold/ booked inventoryP51700034608 · Inventory Disclosure_Ph1_signed.pdf · uploaded 18 Jul 2024Source
- 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700034608 · CA cert_Ph1_Jun24_signed_compressed.pdf · uploaded 18 Jul 2024Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700049514 · Ascend_Ph3_Jun24_signed.pdf · uploaded 18 Jul 2024Source
- 5 Disclosure of sold/ booked inventoryP51700049514 · Inventory Disclosure_Ph3_signed.pdf · uploaded 18 Jul 2024Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700049514 · CA cert_Ph3_Jun24_signed_compressed.pdf · uploaded 18 Jul 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700053668 · Ascend_Ph4_Jun24_signed.pdf · uploaded 18 Jul 2024Source
- 3 Disclosure of sold/ booked inventoryP51700053668 · Inventory Disclosure_Ph4_signed.pdf · uploaded 18 Jul 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700053668 · CA cert_Ph4_Jun24_signed.pdf · uploaded 18 Jul 2024Source
- Form 5 (FY 2023-2024)P51700034608 · Form 5 (FY 2023-2024) · uploaded 23 Sep 2024Source
- Form 5 (FY 2023-2024)P51700046541 · Ascend Phase 2 Signed Deliverables.pdf · uploaded 30 Sep 2024Source
- Form 5 (FY 2023-2024)P51700049514 · Ascend Phase 3 Signed Deliverables.pdf · uploaded 30 Sep 2024Source
- Form 5 (FY 2023-2024)P51700053668 · Ascend Phase 4 Signed Deliverables.pdf · uploaded 30 Sep 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)P51700046541 · Godrej Ascend Phase 2 Form 5 FY 2023 24.pdf · uploaded 6 Oct 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)P51700046541 · Godrej Ascend Phase 2 Form 5 FY 2023 24.pdf · uploaded 6 Oct 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)P51700046541 · Godrej Ascend Phase 2 Form 5 FY 2023 24.pdf · uploaded 6 Oct 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)P51700034608 · Godrej Ascend Ph 1 - Signed Form 5.pdf · uploaded 6 Oct 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)P51700034608 · Godrej Ascend Ph 1 - Signed Form 5.pdf · uploaded 6 Oct 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)P51700034608 · Godrej Ascend Ph 1 - Signed Form 5.pdf · uploaded 6 Oct 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)P51700049514 · Godrej Ascend Phase 3 Form 5 FY 2023 24.pdf · uploaded 6 Oct 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)P51700049514 · Godrej Ascend Phase 3 Form 5 FY 2023 24.pdf · uploaded 6 Oct 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)P51700049514 · Godrej Ascend Phase 3 Form 5 FY 2023 24.pdf · uploaded 6 Oct 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)P51700053668 · Godrej Ascend Phase 4 Form 5 Fy 2023 24.pdf · uploaded 6 Oct 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)P51700053668 · Godrej Ascend Phase 4 Form 5 Fy 2023 24.pdf · uploaded 6 Oct 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)P51700053668 · Godrej Ascend Phase 4 Form 5 Fy 2023 24.pdf · uploaded 6 Oct 2024Source
- 1 Other – LegalP51700046541 · Board Resolution Ascend RERA compliance 26 Sep 24.pdf · uploaded 19 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700046541 · Phase 2 Arch cert Sep 24.pdf · uploaded 19 Oct 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700046541 · Phase 2 Engr cert Sep 24.pdf · uploaded 19 Oct 2024Source
- 1 Disclosure of sold/ booked inventoryP51700046541 · Phase 2 Sold inventory disclosure Sep 24.pdf · uploaded 19 Oct 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700046541 · Phase 2 CA cert Sep 24.pdf · uploaded 19 Oct 2024Source
- 1 Other – LegalP51700046541 · Board Resolution Ascend RERA compliance 26 Sep 24.pdf · uploaded 19 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700046541 · Phase 2 Arch cert Sep 24.pdf · uploaded 19 Oct 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700046541 · Phase 2 Engr cert Sep 24.pdf · uploaded 19 Oct 2024Source
- 1 Disclosure of sold/ booked inventoryP51700046541 · Phase 2 Sold inventory disclosure Sep 24.pdf · uploaded 19 Oct 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700046541 · Phase 2 CA cert Sep 24.pdf · uploaded 19 Oct 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700046541 · Phase 2 Arch cert Sep 24.pdf · uploaded 19 Oct 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700046541 · Phase 2 CA cert Sep 24.pdf · uploaded 19 Oct 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700046541 · Phase 2 Engr cert Sep 24.pdf · uploaded 19 Oct 2024Source
- 1 Other – LegalP51700046541 · Board Resolution Ascend RERA compliance 26 Sep 24.pdf · uploaded 19 Oct 2024Source
- 2 Disclosure of sold/ booked inventoryP51700046541 · Phase 2 Sold inventory disclosure Sep 24.pdf · uploaded 19 Oct 2024Source
- 1 OtherP51700034608 · Board Resolution Ascend RERA compliance 26 Sep 24.pdf · uploaded 19 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700034608 · Phase 1 Arch cert Sep 24.pdf · uploaded 19 Oct 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700034608 · Phase 1 CA cert Sep 24.pdf · uploaded 19 Oct 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700034608 · Phase 1 Engr cert Sep 24.pdf · uploaded 19 Oct 2024Source
- 1 Disclosure of sold/ booked inventoryP51700034608 · Phase 1 Sold inventory disclosure Sep 24.pdf · uploaded 19 Oct 2024Source
- 1 OtherP51700034608 · Board Resolution Ascend RERA compliance 26 Sep 24.pdf · uploaded 19 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700034608 · Phase 1 Arch cert Sep 24.pdf · uploaded 19 Oct 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700034608 · Phase 1 CA cert Sep 24.pdf · uploaded 19 Oct 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700034608 · Phase 1 Engr cert Sep 24.pdf · uploaded 19 Oct 2024Source
- 1 Disclosure of sold/ booked inventoryP51700034608 · Phase 1 Sold inventory disclosure Sep 24.pdf · uploaded 19 Oct 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700034608 · Phase 1 Arch cert Sep 24.pdf · uploaded 19 Oct 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700034608 · Phase 1 CA cert Sep 24.pdf · uploaded 19 Oct 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700034608 · Phase 1 Engr cert Sep 24.pdf · uploaded 19 Oct 2024Source
- 1 OtherP51700034608 · Board Resolution Ascend RERA compliance 26 Sep 24.pdf · uploaded 19 Oct 2024Source
- 2 Disclosure of sold/ booked inventoryP51700034608 · Phase 1 Sold inventory disclosure Sep 24.pdf · uploaded 19 Oct 2024Source
- 1 Other – LegalP51700049514 · Board Resolution Ascend RERA compliance 26 Sep 24.pdf · uploaded 19 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700049514 · Phase 3 Arch cert Sep 24.pdf · uploaded 19 Oct 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700049514 · Phase 3 Engr Cert Sep 24.pdf · uploaded 19 Oct 2024Source
- 1 Disclosure of sold/ booked inventoryP51700049514 · Phase 3 Sold inventory disclosure Sep 24.pdf · uploaded 19 Oct 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700049514 · Phase 3 CA cert Sep 24.pdf · uploaded 19 Oct 2024Source
- 1 Other – LegalP51700049514 · Board Resolution Ascend RERA compliance 26 Sep 24.pdf · uploaded 19 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700049514 · Phase 3 Arch cert Sep 24.pdf · uploaded 19 Oct 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700049514 · Phase 3 Engr Cert Sep 24.pdf · uploaded 19 Oct 2024Source
- 1 Disclosure of sold/ booked inventoryP51700049514 · Phase 3 Sold inventory disclosure Sep 24.pdf · uploaded 19 Oct 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700049514 · Phase 3 CA cert Sep 24.pdf · uploaded 19 Oct 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700049514 · Phase 3 Arch cert Sep 24.pdf · uploaded 19 Oct 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700049514 · Phase 3 CA cert Sep 24.pdf · uploaded 19 Oct 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700049514 · Phase 3 Engr Cert Sep 24.pdf · uploaded 19 Oct 2024Source
- 1 Other – LegalP51700049514 · Board Resolution Ascend RERA compliance 26 Sep 24.pdf · uploaded 19 Oct 2024Source
- 3 Disclosure of sold/ booked inventoryP51700049514 · Phase 3 Sold inventory disclosure Sep 24.pdf · uploaded 19 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700053668 · Phase 4 Arch cert Sep 24.pdf · uploaded 19 Oct 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700053668 · Phase 4 Engr cert Sep 24.pdf · uploaded 19 Oct 2024Source
- 1 Disclosure of sold/ booked inventoryP51700053668 · Phase 4 Sold inventory disclosure Sep 24.pdf · uploaded 19 Oct 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700053668 · Phase 4 CA cert Sep 24.pdf · uploaded 19 Oct 2024Source
- 1 Other – LegalP51700053668 · Board Resolution Ascend RERA compliance 26 Sep 24.pdf · uploaded 19 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700053668 · Phase 4 Arch cert Sep 24.pdf · uploaded 19 Oct 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700053668 · Phase 4 Engr cert Sep 24.pdf · uploaded 19 Oct 2024Source
- 1 Disclosure of sold/ booked inventoryP51700053668 · Phase 4 Sold inventory disclosure Sep 24.pdf · uploaded 19 Oct 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700053668 · Phase 4 CA cert Sep 24.pdf · uploaded 19 Oct 2024Source
- 1 Other – LegalP51700053668 · Board Resolution Ascend RERA compliance 26 Sep 24.pdf · uploaded 19 Oct 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700053668 · Phase 4 Arch cert Sep 24.pdf · uploaded 19 Oct 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700053668 · Phase 4 CA cert Sep 24.pdf · uploaded 19 Oct 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700053668 · Phase 4 Engr cert Sep 24.pdf · uploaded 19 Oct 2024Source
- 1 Other – LegalP51700053668 · Board Resolution Ascend RERA compliance 26 Sep 24.pdf · uploaded 19 Oct 2024Source
- 2 Disclosure of sold/ booked inventoryP51700053668 · Phase 4 Sold inventory disclosure Sep 24.pdf · uploaded 19 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700046541 · Ascend RERA Ph 2 Arch cert Dec 24.pdf · uploaded 20 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700046541 · Ascend RERA Ph 2 Engr cert Dec 24.pdf · uploaded 20 Jan 2025Source
- 1 Disclosure of sold/ booked inventoryP51700046541 · Phase 2 Sold inventory disclosure Dec 24.pdf · uploaded 20 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700046541 · Ascend RERA Ph 2 CA cert Dec 24.pdf · uploaded 20 Jan 2025Source
- 1 Proforma of Agreement for saleP51700046541 · Godrej Ascend Tower 3 AFS Phase 2.pdf · uploaded 20 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700046541 · Ascend RERA Ph 2 Arch cert Dec 24.pdf · uploaded 20 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700046541 · Ascend RERA Ph 2 Engr cert Dec 24.pdf · uploaded 20 Jan 2025Source
- 1 Disclosure of sold/ booked inventoryP51700046541 · Phase 2 Sold inventory disclosure Dec 24.pdf · uploaded 20 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700046541 · Ascend RERA Ph 2 CA cert Dec 24.pdf · uploaded 20 Jan 2025Source
- 1 Proforma of Agreement for saleP51700046541 · Godrej Ascend Tower 3 AFS Phase 2.pdf · uploaded 20 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700046541 · Ascend RERA Ph 2 Arch cert Dec 24.pdf · uploaded 20 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700046541 · Ascend RERA Ph 2 CA cert Dec 24.pdf · uploaded 20 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700046541 · Ascend RERA Ph 2 Engr cert Dec 24.pdf · uploaded 20 Jan 2025Source
- 1 Disclosure of sold/ booked inventoryP51700046541 · Phase 2 Sold inventory disclosure Dec 24.pdf · uploaded 20 Jan 2025Source
- 1 Proforma of Agreement for saleP51700046541 · Godrej Ascend Tower 3 AFS Phase 2.pdf · uploaded 20 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700034608 · Ascend RERA Ph 1 Arch cert Dec 24.pdf · uploaded 20 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700034608 · Ascend RERA Ph 1 Engr cert Dec 24.pdf · uploaded 20 Jan 2025Source
- 1 Disclosure of sold/ booked inventoryP51700034608 · Phase 1 Sold inventory disclosure Dec 24.pdf · uploaded 20 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700034608 · Ascend RERA Ph 1 CA cert Dec 24.pdf · uploaded 20 Jan 2025Source
- 1 Proforma of Agreement for saleP51700034608 · Godrej Ascend AFS Phase 1.pdf · uploaded 20 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700034608 · Ascend RERA Ph 1 Arch cert Dec 24.pdf · uploaded 20 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700034608 · Ascend RERA Ph 1 Engr cert Dec 24.pdf · uploaded 20 Jan 2025Source
- 1 Disclosure of sold/ booked inventoryP51700034608 · Phase 1 Sold inventory disclosure Dec 24.pdf · uploaded 20 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700034608 · Ascend RERA Ph 1 CA cert Dec 24.pdf · uploaded 20 Jan 2025Source
- 1 Proforma of Agreement for saleP51700034608 · Godrej Ascend AFS Phase 1.pdf · uploaded 20 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700034608 · Ascend RERA Ph 1 Arch cert Dec 24.pdf · uploaded 20 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700034608 · Ascend RERA Ph 1 CA cert Dec 24.pdf · uploaded 20 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700034608 · Ascend RERA Ph 1 Engr cert Dec 24.pdf · uploaded 20 Jan 2025Source
- 1 Disclosure of sold/ booked inventoryP51700034608 · Phase 1 Sold inventory disclosure Dec 24.pdf · uploaded 20 Jan 2025Source
- 1 Proforma of Agreement for saleP51700034608 · Godrej Ascend AFS Phase 1.pdf · uploaded 20 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700049514 · Ascend RERA Ph 3 Arch cert Dec 24.pdf · uploaded 20 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700049514 · Ascend RERA Ph 3 Engr cert Dec 24.pdf · uploaded 20 Jan 2025Source
- 1 Disclosure of sold/ booked inventoryP51700049514 · Phase 3 Sold inventory disclosure Dec 24.pdf · uploaded 20 Jan 2025Source
- 1 Disclosure of sold/ booked inventoryP51700049514 · Phase 3 Sold inventory disclosure Dec 24.pdf · uploaded 20 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700049514 · Ascend RERA Ph 3 CA cert Dec 24.pdf · uploaded 20 Jan 2025Source
- 1 Proforma of Agreement for saleP51700049514 · Godrej Ascend Tower 5 AFS Phase 3.pdf · uploaded 20 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700049514 · Ascend RERA Ph 3 Arch cert Dec 24.pdf · uploaded 20 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700049514 · Ascend RERA Ph 3 Engr cert Dec 24.pdf · uploaded 20 Jan 2025Source
- 1 Disclosure of sold/ booked inventoryP51700049514 · Phase 3 Sold inventory disclosure Dec 24.pdf · uploaded 20 Jan 2025Source
- 1 Disclosure of sold/ booked inventoryP51700049514 · Phase 3 Sold inventory disclosure Dec 24.pdf · uploaded 20 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700049514 · Ascend RERA Ph 3 CA cert Dec 24.pdf · uploaded 20 Jan 2025Source
- 1 Proforma of Agreement for saleP51700049514 · Godrej Ascend Tower 5 AFS Phase 3.pdf · uploaded 20 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700049514 · Ascend RERA Ph 3 Arch cert Dec 24.pdf · uploaded 20 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700049514 · Ascend RERA Ph 3 CA cert Dec 24.pdf · uploaded 20 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700049514 · Ascend RERA Ph 3 Engr cert Dec 24.pdf · uploaded 20 Jan 2025Source
- 1 Disclosure of sold/ booked inventoryP51700049514 · Phase 3 Sold inventory disclosure Dec 24.pdf · uploaded 20 Jan 2025Source
- 2 Disclosure of sold/ booked inventoryP51700049514 · Phase 3 Sold inventory disclosure Dec 24.pdf · uploaded 20 Jan 2025Source
- 1 Proforma of Agreement for saleP51700049514 · Godrej Ascend Tower 5 AFS Phase 3.pdf · uploaded 20 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700053668 · Ascend RERA Ph 4 Arch cert Dec 24.pdf · uploaded 20 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700053668 · Ascend RERA Ph 4 Engr cert Dec 24.pdf · uploaded 20 Jan 2025Source
- 1 Disclosure of sold/ booked inventoryP51700053668 · Phase 4 Sold inventory disclosure Dec 24.pdf · uploaded 20 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700053668 · Ascend RERA Ph 4 CA cert Dec 24.pdf · uploaded 20 Jan 2025Source
- 1 Proforma of Agreement for saleP51700053668 · Godrej Ascend Tower 1 AFS Phase 4.pdf · uploaded 20 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700053668 · Ascend RERA Ph 4 Arch cert Dec 24.pdf · uploaded 20 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700053668 · Ascend RERA Ph 4 Engr cert Dec 24.pdf · uploaded 20 Jan 2025Source
- 1 Disclosure of sold/ booked inventoryP51700053668 · Phase 4 Sold inventory disclosure Dec 24.pdf · uploaded 20 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700053668 · Ascend RERA Ph 4 CA cert Dec 24.pdf · uploaded 20 Jan 2025Source
- 1 Proforma of Agreement for saleP51700053668 · Godrej Ascend Tower 1 AFS Phase 4.pdf · uploaded 20 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700053668 · Ascend RERA Ph 4 Arch cert Dec 24.pdf · uploaded 20 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700053668 · Ascend RERA Ph 4 CA cert Dec 24.pdf · uploaded 20 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700053668 · Ascend RERA Ph 4 Engr cert Dec 24.pdf · uploaded 20 Jan 2025Source
- 1 Disclosure of sold/ booked inventoryP51700053668 · Phase 4 Sold inventory disclosure Dec 24.pdf · uploaded 20 Jan 2025Source
- 1 Proforma of Agreement for saleP51700053668 · Godrej Ascend Tower 1 AFS Phase 4.pdf · uploaded 20 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700046541 · Ascend Phase 2 Arch certificate Mar 25.pdf · uploaded 17 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700046541 · Ascend Phase 2 CA Certificate.pdf · uploaded 17 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700046541 · Ascend Phase 2 engineers certificate Mar 25.pdf · uploaded 17 Apr 2025Source
- 1 Disclosure of sold/ booked inventoryP51700046541 · Ascend Phase 2 Sold inventory Mar 25.pdf · uploaded 17 Apr 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)P51700046541 · Ascend Phase 2 Sold inventory Mar 25.pdf · uploaded 17 Apr 2025Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)P51700046541 · Ascend Phase 2 Quality certificate mar 25.pdf · uploaded 17 Apr 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700034608 · Ascend Phase 1 Arch certificate.pdf · uploaded 17 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700034608 · Ascend Phase 1 CA Certificate Mar 25-compressed.pdf · uploaded 17 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700034608 · Ascend Phase 1 Engineers certificate Mar 25.pdf · uploaded 17 Apr 2025Source
- 1 Disclosure of sold/ booked inventoryP51700034608 · Ascend Phase 1 Sold inventory Mar 25.pdf · uploaded 17 Apr 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)P51700034608 · Ascend Phase 1 Quality certificate Mar 25.pdf · uploaded 17 Apr 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700049514 · Ascend Phase 3 Arch certificate Mar 25.pdf · uploaded 17 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700049514 · Ascend Phase 3 CA certificate Mar 25-compressed.pdf · uploaded 17 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700049514 · Ascend Phase 3 Engineers certificate Mar 25.pdf · uploaded 17 Apr 2025Source
- 1 Disclosure of sold/ booked inventoryP51700049514 · Ascend Phase 3 Sold inventory Mar 25.pdf · uploaded 17 Apr 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)P51700049514 · Ascend Phase 3 Quality certificate.pdf · uploaded 17 Apr 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700053668 · Ascend Phase 4 Arch certificate mar 25.pdf · uploaded 17 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700053668 · Ascend Phase 4 CA certificate Mar 25.pdf · uploaded 17 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700053668 · Ascend Phase 4 Engineer certificate Mar 25.pdf · uploaded 17 Apr 2025Source
- 1 Disclosure of sold/ booked inventoryP51700053668 · Ascend Phase 4 Sold inventory Mar 25.pdf · uploaded 17 Apr 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)P51700053668 · Ascend Phase 4 Quality certificate.pdf · uploaded 17 Apr 2025Source
- Form 2A (FY 2024-2025)P51700046541 · Ascend -Ph 2_ Quality Assurance Certificate FY 25 (2).pdf · uploaded 17 Jun 2025Source
- Form 2A (FY 2024-2025)P51700034608 · Ascend -Ph 1_ Quality Assurance Certificate FY 25 (2).pdf · uploaded 17 Jun 2025Source
- Form 2A (FY 2024-2025)P51700049514 · Ascend -Ph 3_ Quality Assurance Certificate FY 25 (2).pdf · uploaded 17 Jun 2025Source
- Form 2A (FY 2024-2025)P51700053668 · Ascend -Ph 4_ Quality Assurance Certificate FY 25 (2).pdf · uploaded 17 Jun 2025Source
- Form 1P51700046541 · Ascend Arch certificate Phase 2 Jun 25.pdf · uploaded 18 Jul 2025Source
- Form 2P51700046541 · Ascend Engineers certificate Phase 2 Jun 25.pdf · uploaded 18 Jul 2025Source
- Form 3P51700046541 · Ascend Phase 2 CA Certificate Jun 25.pdf · uploaded 18 Jul 2025Source
- Disclosure of Sold and Booked InventoryP51700046541 · Ascend Phase 2 Sold inventory.pdf · uploaded 18 Jul 2025Source
- Form 1P51700034608 · Ascend Arch certificate Phase 1 Jun 25.pdf · uploaded 18 Jul 2025Source
- Form 2P51700034608 · Ascend Engineers certificate Phase 1 Jun 25.pdf · uploaded 18 Jul 2025Source
- Form 3P51700034608 · Ascend Phase 1 CA Certificate Jun 25.pdf · uploaded 18 Jul 2025Source
- Disclosure of Sold and Booked InventoryP51700034608 · Ascend Phase 1 Sold inventory.pdf · uploaded 18 Jul 2025Source
- Form 1P51700049514 · Ascend Arch certificate Phase 3 Jun 25.pdf · uploaded 18 Jul 2025Source
- Form 2P51700049514 · Ascend Engineers certificate Phase 3 Jun 25.pdf · uploaded 18 Jul 2025Source
- Form 3P51700049514 · Ascend Phase 3 CA Certificate Jun 25.pdf · uploaded 18 Jul 2025Source
- Disclosure of Sold and Booked InventoryP51700049514 · Ascend Phase 3 Sold inventory.pdf · uploaded 18 Jul 2025Source
- Form 1P51700053668 · Ascend Arch certificate Phase 4 Jun 25.pdf · uploaded 18 Jul 2025Source
- Form 2P51700053668 · Ascend Engineers certificate Phase 4 Jun 25.pdf · uploaded 18 Jul 2025Source
- Form 3P51700053668 · Ascend Phase 4 CA Certificate Jun 25.pdf · uploaded 18 Jul 2025Source
- Disclosure of Sold and Booked InventoryP51700053668 · Ascend Phase 4 Sold inventory.pdf · uploaded 18 Jul 2025Source
- Form 5 (FY 2024-2025)P51700046541 · Ascend Phase 2.pdf · uploaded 28 Aug 2025Source
- Form 5 (FY 2024-2025)P51700034608 · Ascend Phase I.pdf · uploaded 28 Aug 2025Source
- Form 5 (FY 2024-2025)P51700049514 · Ascend Phase 3.pdf · uploaded 28 Aug 2025Source
- Form 5 (FY 2024-2025)P51700053668 · Ascend Phase 4.pdf · uploaded 28 Aug 2025Source
- Form 1P51700046541 · Ascend Ph 2 Arch Cer.pdf · uploaded 16 Oct 2025Source
- Form 2P51700046541 · Ascend Ph 2 EC.pdf · uploaded 16 Oct 2025Source
- Form 3P51700046541 · Ascend Ph 2 CA Cer.pdf · uploaded 16 Oct 2025Source
- Disclosure of Sold and Booked InventoryP51700046541 · Ascend Ph 2 Inventory Disclosure.pdf · uploaded 16 Oct 2025Source
- Form 1P51700034608 · Ascend Ph 1 Arch Cer.pdf · uploaded 16 Oct 2025Source
- Form 2P51700034608 · Ascend Ph 1 EC.pdf · uploaded 16 Oct 2025Source
- Form 3P51700034608 · Ascend Ph 1 CA Cer.pdf · uploaded 16 Oct 2025Source
- Disclosure of Sold and Booked InventoryP51700034608 · Ascend Ph 1 Inventory Disclosure.pdf · uploaded 16 Oct 2025Source
- Form 1P51700049514 · Ascend Ph 3 Arch Cer.pdf · uploaded 16 Oct 2025Source
- Form 2P51700049514 · Ascend Ph 3 EC.pdf · uploaded 16 Oct 2025Source
- Form 3P51700049514 · Ascend Ph 3 CA Cer.pdf · uploaded 16 Oct 2025Source
- Disclosure of Sold and Booked InventoryP51700049514 · Ascend Ph 3 Inventory Disclosure.pdf · uploaded 16 Oct 2025Source
- Form 1P51700053668 · Ascend Ph 4 Arch Cer.pdf · uploaded 16 Oct 2025Source
- Form 2P51700053668 · Ascend Ph 4 EC.pdf · uploaded 16 Oct 2025Source
- Form 3P51700053668 · Ascend Ph 4 CA Cer.pdf · uploaded 16 Oct 2025Source
- Disclosure of Sold and Booked InventoryP51700053668 · Ascend Ph 4 Inventory Disclosure.pdf · uploaded 16 Oct 2025Source
- Form 1P51700046541 · Arch ph 2.pdf · uploaded 20 Jan 2026Source
- Form 2P51700046541 · EC ph 2.pdf · uploaded 20 Jan 2026Source
- Disclosure of Sold and Booked InventoryP51700046541 · Inventory ph 2.pdf · uploaded 20 Jan 2026Source
- Form 3P51700046541 · CA ph 2.pdf · uploaded 20 Jan 2026Source
- Form 1P51700034608 · Arch ph 1.pdf · uploaded 20 Jan 2026Source
- Form 2P51700034608 · EC ph 1.pdf · uploaded 20 Jan 2026Source
- Form 3P51700034608 · CA ph 1_compressed.pdf · uploaded 20 Jan 2026Source
- Disclosure of Sold and Booked InventoryP51700034608 · Inventory ph 1.pdf · uploaded 20 Jan 2026Source
- Form 1P51700049514 · Arch ph 3.pdf · uploaded 20 Jan 2026Source
- Form 2P51700049514 · EC ph 3.pdf · uploaded 20 Jan 2026Source
- Form 3P51700049514 · CA ph 3.pdf · uploaded 20 Jan 2026Source
- Disclosure of Sold and Booked InventoryP51700049514 · Inventory ph 3.pdf · uploaded 20 Jan 2026Source
- Form 1P51700053668 · Arch ph 4.pdf · uploaded 20 Jan 2026Source
- Form 2P51700053668 · EC ph 4.pdf · uploaded 20 Jan 2026Source
- Form 3P51700053668 · CA ph 4.pdf · uploaded 20 Jan 2026Source
- Disclosure of Sold and Booked InventoryP51700053668 · Inventory ph 4.pdf · uploaded 20 Jan 2026Source
- Form 1P51700046541 · Arch Ph2.pdf · uploaded 20 Apr 2026Source
- Form 2P51700046541 · EC Ph 2.pdf · uploaded 20 Apr 2026Source
- Form 3P51700046541 · CA Cer Ph2.pdf · uploaded 20 Apr 2026Source
- Disclosure of Sold and Booked InventoryP51700046541 · Ascend Inventory Declaration Ph2.pdf · uploaded 20 Apr 2026Source
- Form 1P51700034608 · Arch Ph1.pdf · uploaded 20 Apr 2026Source
- Form 2P51700034608 · EC Ph 1.pdf · uploaded 20 Apr 2026Source
- Form 3P51700034608 · CA Cer Ph1.pdf · uploaded 20 Apr 2026Source
- Disclosure of Sold and Booked InventoryP51700034608 · Ascend Inventory Declaration Ph1.pdf · uploaded 20 Apr 2026Source
- Form 1P51700049514 · Arch Ph3.pdf · uploaded 20 Apr 2026Source
- Form 2P51700049514 · EC Ph 3.pdf · uploaded 20 Apr 2026Source
- Form 3P51700049514 · CA Cer Ph3.pdf · uploaded 20 Apr 2026Source
- Disclosure of Sold and Booked InventoryP51700049514 · Ascend Inventory Declaration Ph3.pdf · uploaded 20 Apr 2026Source
- Form 1P51700053668 · Arch Ph4.pdf · uploaded 20 Apr 2026Source
- Form 2P51700053668 · EC Ph 4.pdf · uploaded 20 Apr 2026Source
- Form 3P51700053668 · CA Cer Ph4.pdf · uploaded 20 Apr 2026Source
- Disclosure of Sold and Booked InventoryP51700053668 · Ascend Inventory Declaration Ph4.pdf · uploaded 20 Apr 2026Source
- Form 2A (FY 2025-2026)P51700046541 · Form 2A Ascend ph 2.pdf · uploaded 16 Jun 2026Source
- Form 2A (FY 2025-2026)P51700034608 · Form 2A Ascend ph 1.pdf · uploaded 16 Jun 2026Source
- Form 2A (FY 2025-2026)P51700049514 · Form 2A Ascend ph 3.pdf · uploaded 16 Jun 2026Source
- Form 2A (FY 2025-2026)P51700053668 · Form 2A Ascend ph 4.pdf · uploaded 16 Jun 2026Source
- Form 1P51700046541 · Form 1 Architect certificate.pdf · uploaded 15 Jul 2026Source
- Form 2P51700046541 · Form 2 Engineer certificate.pdf · uploaded 15 Jul 2026Source
- Form 3P51700046541 · Form 3- CA certificate.pdf · uploaded 15 Jul 2026Source
- Disclosure of Sold and Booked InventoryP51700046541 · Disclosure of Inventory.pdf · uploaded 15 Jul 2026Source
- Form 1P51700034608 · Form 1 Architect certificate.pdf · uploaded 15 Jul 2026Source
- Form 2P51700034608 · Form 2 Engineer certificate.pdf · uploaded 15 Jul 2026Source
- Form 3P51700034608 · Form 3- CA certificate.pdf · uploaded 15 Jul 2026Source
- Disclosure of Sold and Booked InventoryP51700034608 · Disclosure of Inventory.pdf · uploaded 15 Jul 2026Source
- Form 1P51700049514 · Form 1 Architect certificate.pdf · uploaded 15 Jul 2026Source
- Form 2P51700049514 · Form 2 Engineer certificate.pdf · uploaded 15 Jul 2026Source
- Form 3P51700049514 · Form 3- CA certificate.pdf · uploaded 15 Jul 2026Source
- Disclosure of Sold and Booked InventoryP51700049514 · Disclosure of Inventory.pdf · uploaded 15 Jul 2026Source
- Form 1P51700053668 · Form 1 Architect certificate.pdf · uploaded 15 Jul 2026Source
- Form 2P51700053668 · Form 2 Engineer certificate.pdf · uploaded 15 Jul 2026Source
- Form 3P51700053668 · Form 3- CA certificate.pdf · uploaded 15 Jul 2026Source
- Disclosure of Sold and Booked InventoryP51700053668 · Disclosure of Inventory.pdf · uploaded 15 Jul 2026Source
- Form 5 (FY 2025-2026)P51700046541 · Ph II Form 5.pdf · uploaded 4 Sep 2026Source
- Form 5 (FY 2025-2026)P51700034608 · Ph I Form 5.pdf · uploaded 4 Sep 2026Source
- Form 5 (FY 2025-2026)P51700049514 · PH III Form 5.pdf · uploaded 4 Sep 2026Source
- Form 5 (FY 2025-2026)P51700053668 · Ph IV Form 5.pdf · uploaded 4 Sep 2026Source
Technical
- DocumentP51700034608 · Godrej Ascend - DP CC.pdf · uploaded 17 Apr 2022Source
- DocumentP51700034608 · Layout - compressed for upload.pdf · uploaded 18 Apr 2022Source
- DocumentP51700046541 · Layout Phase-II_upload.pdf · uploaded 11 Jul 2022Source
- DocumentP51700046541 · 13_compressed.pdf · uploaded 27 Jul 2022Source
- Other – TechnicalP51700046541 · Godrej Ascend - RERA promoter change_compressed2.pdf · uploaded 27 Jul 2022Source
- DocumentP51700046541 · 13_compressed.pdf · uploaded 23 Aug 2022Source
- DocumentP51700049514 · Building Plan_Pg21_Upload.pdf · uploaded 16 Jan 2023Source
- Other – TechnicalP51700049514 · Other Technical_upload.pdf · uploaded 23 Jan 2023Source
- DocumentP51700049514 · Layout ph3_uploadfile1.pdf · uploaded 6 Feb 2023Source
- DocumentP51700049514 · Layout ph3_uploadfile2.pdf · uploaded 6 Feb 2023Source
- DocumentP51700049514 · Building Plan_Pg22_Upload.pdf · uploaded 9 Feb 2023Source
- DocumentP51700049514 · Building Plan_Pg23_Upload.pdf · uploaded 9 Feb 2023Source
- DocumentP51700049514 · Building Plan_Pg24_Upload.pdf · uploaded 9 Feb 2023Source
- DocumentP51700053668 · 1 GFA LAYOUT 01112023 Model NEW.pdf · uploaded 2 Nov 2023Source
- DocumentP51700053668 · 1 GFA LAYOUT 01112023 1 R.pdf · uploaded 2 Nov 2023Source
- DocumentP51700053668 · Sheet 01_compressed_11zon.pdf · uploaded 2 Nov 2023Source
- DocumentP51700053668 · Sheet 02_compressed.pdf · uploaded 2 Nov 2023Source
- DocumentP51700053668 · Sheet 03_compressed.pdf · uploaded 2 Nov 2023Source
- DocumentP51700053668 · Sheet 04_compressed.pdf · uploaded 2 Nov 2023Source
- DocumentP51700053668 · Sheet 05_compressed.pdf · uploaded 2 Nov 2023Source
- DocumentP51700053668 · Sheet 06_compressed.pdf · uploaded 2 Nov 2023Source
- DocumentP51700053668 · Sheet 07_compressed.pdf · uploaded 2 Nov 2023Source
- Other – TechnicalP51700053668 · 32 - EXT_RERA Compliance - Godrej Ascend.pdf · uploaded 2 Nov 2023Source
- DocumentP51700053668 · 1 GFA LAYOUT 08112023 Ph4 T1 Highlighted.pdf · uploaded 8 Nov 2023Source
- DocumentP51700034608 · Layout Approval_Tower 5.pdf · uploaded 5 Jan 2024Source
- DocumentP51700034608 · Layout Approval_Tower 5.pdf · uploaded 5 Jan 2024Source
- DocumentP51700034608 · Ascend amended Permission and Full CC.pdf · uploaded 5 Jan 2024Source
- DocumentP51700034608 · Layout Approval_Phase 1.pdf · uploaded 8 Jan 2024Source
- DocumentP51700034608 · T2 Sheet 5.pdf · uploaded 8 Jan 2024Source
- DocumentP51700034608 · T2 Sheet 6.pdf · uploaded 8 Jan 2024Source
- DocumentP51700034608 · T2 Sheet 7.pdf · uploaded 8 Jan 2024Source
- DocumentP51700034608 · T2 Sheet 8.pdf · uploaded 8 Jan 2024Source
- DocumentP51700034608 · T2 Sheet 9.pdf · uploaded 8 Jan 2024Source
- DocumentP51700034608 · T2 Sheet 10.pdf · uploaded 8 Jan 2024Source
- DocumentP51700034608 · T2 Sheet 11.pdf · uploaded 8 Jan 2024Source
- DocumentP51700034608 · T4 Sheet 15.pdf · uploaded 8 Jan 2024Source
- DocumentP51700034608 · T4 Sheet 16.pdf · uploaded 8 Jan 2024Source
- DocumentP51700034608 · T4 Sheet 17.pdf · uploaded 8 Jan 2024Source
- DocumentP51700034608 · T4 Sheet 18.pdf · uploaded 8 Jan 2024Source
- DocumentP51700034608 · T4 Sheet 19.pdf · uploaded 8 Jan 2024Source
- DocumentP51700034608 · T4 Sheet 20.pdf · uploaded 8 Jan 2024Source
- DocumentP51700034608 · Phase 1 Retail Correction _Layout.pdf · uploaded 5 Feb 2024Source
- DocumentP51700034608 · Phase 1 Retail Correction _Layout-2.pdf · uploaded 5 Feb 2024Source
- DocumentP51700046541 · Sheet -1 Layout_upload.pdf · uploaded 22 Apr 2024Source
- DocumentP51700046541 · Sheet -15_T3.pdf · uploaded 22 Apr 2024Source
- DocumentP51700046541 · Sheet -16_T3.pdf · uploaded 22 Apr 2024Source
- DocumentP51700046541 · Sheet -17_T3.pdf · uploaded 22 Apr 2024Source
- DocumentP51700034608 · Sheet -1 Layout_upload.pdf · uploaded 22 Apr 2024Source
- DocumentP51700034608 · Sheet -8_T2.pdf · uploaded 22 Apr 2024Source
- DocumentP51700034608 · Sheet -9_T2.pdf · uploaded 22 Apr 2024Source
- DocumentP51700034608 · Sheet -10_T2.pdf · uploaded 22 Apr 2024Source
- DocumentP51700034608 · Sheet -11_T2.pdf · uploaded 22 Apr 2024Source
- DocumentP51700034608 · Sheet -12_T2.pdf · uploaded 22 Apr 2024Source
- DocumentP51700034608 · Sheet -13_T2.pdf · uploaded 22 Apr 2024Source
- DocumentP51700034608 · Sheet -14_T2.pdf · uploaded 22 Apr 2024Source
- DocumentP51700049514 · Sheet -1 Layout_upload.pdf · uploaded 22 Apr 2024Source
- DocumentP51700049514 · Sheet -18_T5.pdf · uploaded 22 Apr 2024Source
- DocumentP51700049514 · Sheet -19_T5.pdf · uploaded 22 Apr 2024Source
- DocumentP51700049514 · Sheet -20_T5.pdf · uploaded 22 Apr 2024Source
- DocumentP51700049514 · Sheet -21_T5.pdf · uploaded 22 Apr 2024Source
- DocumentP51700053668 · Sheet -1 Layout.pdf · uploaded 22 Apr 2024Source
- DocumentP51700053668 · Sheet -2_T1.pdf · uploaded 22 Apr 2024Source
- DocumentP51700053668 · Sheet -3_T1.pdf · uploaded 22 Apr 2024Source
- DocumentP51700053668 · Sheet -4_T1.pdf · uploaded 22 Apr 2024Source
- DocumentP51700053668 · Sheet -5_T1.pdf · uploaded 22 Apr 2024Source
- DocumentP51700053668 · Sheet -6_T1.pdf · uploaded 22 Apr 2024Source
- DocumentP51700053668 · Sheet -7_T1.pdf · uploaded 22 Apr 2024Source
Technical (Architect)
- DocumentP51700034608 · Form 1 Godrej Ascend Phase 1.pdf · uploaded 20 Sep 2024Source
- DocumentP51700046541 · Architect Certificate Phase 2 June 2024.pdf · uploaded 25 Sep 2024Source
- DocumentP51700049514 · Form 1 June 24.pdf · uploaded 25 Sep 2024Source
- DocumentP51700053668 · Form 1 June 24.pdf · uploaded 25 Sep 2024Source
- DocumentP51700046541 · Phase 2 Arch cert Sep 24.pdf · uploaded 19 Oct 2024Source
- DocumentP51700046541 · Phase 2 Arch cert Sep 24.pdf · uploaded 19 Oct 2024Source
- DocumentP51700046541 · Phase 2 Arch cert Sep 24.pdf · uploaded 19 Oct 2024Source
- DocumentP51700034608 · Phase 1 Arch cert Sep 24.pdf · uploaded 19 Oct 2024Source
- DocumentP51700034608 · Phase 1 Arch cert Sep 24.pdf · uploaded 19 Oct 2024Source
- DocumentP51700034608 · Phase 1 Arch cert Sep 24.pdf · uploaded 19 Oct 2024Source
- DocumentP51700049514 · Phase 3 Arch cert Sep 24.pdf · uploaded 19 Oct 2024Source
- DocumentP51700049514 · Phase 3 Arch cert Sep 24.pdf · uploaded 19 Oct 2024Source
- DocumentP51700049514 · Phase 3 Arch cert Sep 24.pdf · uploaded 19 Oct 2024Source
- DocumentP51700053668 · Phase 4 Arch cert Sep 24.pdf · uploaded 19 Oct 2024Source
- DocumentP51700053668 · Phase 4 Arch cert Sep 24.pdf · uploaded 19 Oct 2024Source
- DocumentP51700053668 · Phase 4 Arch cert Sep 24.pdf · uploaded 19 Oct 2024Source
- DocumentP51700046541 · Ascend RERA Ph 2 Arch cert Dec 24.pdf · uploaded 20 Jan 2025Source
- DocumentP51700046541 · Ascend RERA Ph 2 Arch cert Dec 24.pdf · uploaded 20 Jan 2025Source
- DocumentP51700046541 · Ascend RERA Ph 2 Arch cert Dec 24.pdf · uploaded 20 Jan 2025Source
- DocumentP51700034608 · Ascend RERA Ph 1 Arch cert Dec 24.pdf · uploaded 20 Jan 2025Source
- DocumentP51700034608 · Ascend RERA Ph 1 Arch cert Dec 24.pdf · uploaded 20 Jan 2025Source
- DocumentP51700034608 · Ascend RERA Ph 1 Arch cert Dec 24.pdf · uploaded 20 Jan 2025Source
- DocumentP51700049514 · Ascend RERA Ph 3 Arch cert Dec 24.pdf · uploaded 20 Jan 2025Source
- DocumentP51700049514 · Ascend RERA Ph 3 Arch cert Dec 24.pdf · uploaded 20 Jan 2025Source
- DocumentP51700049514 · Ascend RERA Ph 3 Arch cert Dec 24.pdf · uploaded 20 Jan 2025Source
- DocumentP51700053668 · Ascend RERA Ph 4 Arch cert Dec 24.pdf · uploaded 20 Jan 2025Source
- DocumentP51700053668 · Ascend RERA Ph 4 Arch cert Dec 24.pdf · uploaded 20 Jan 2025Source
- DocumentP51700053668 · Ascend RERA Ph 4 Arch cert Dec 24.pdf · uploaded 20 Jan 2025Source
- DocumentP51700046541 · Ascend Phase 2 Arch certificate Mar 25.pdf · uploaded 17 Apr 2025Source
- DocumentP51700034608 · Ascend Phase 1 Arch certificate.pdf · uploaded 17 Apr 2025Source
- DocumentP51700049514 · Ascend Phase 3 Arch certificate Mar 25.pdf · uploaded 17 Apr 2025Source
- DocumentP51700053668 · Ascend Phase 4 Arch certificate mar 25.pdf · uploaded 17 Apr 2025Source
Technical (Engineer)
- DocumentP51700034608 · Form 2 Ascend Ph 1 Jun 24 organized.pdf · uploaded 20 Sep 2024Source
- DocumentP51700046541 · Engineer Certificate Phase 2 JUNE 2024.pdf · uploaded 25 Sep 2024Source
- DocumentP51700049514 · Form 2 June 24.pdf · uploaded 25 Sep 2024Source
- DocumentP51700053668 · Form 2 June 24.pdf · uploaded 25 Sep 2024Source
- DocumentP51700046541 · Phase 2 Engr cert Sep 24.pdf · uploaded 19 Oct 2024Source
- DocumentP51700046541 · Phase 2 Engr cert Sep 24.pdf · uploaded 19 Oct 2024Source
- DocumentP51700046541 · Phase 2 Engr cert Sep 24.pdf · uploaded 19 Oct 2024Source
- DocumentP51700034608 · Phase 1 Engr cert Sep 24.pdf · uploaded 19 Oct 2024Source
- DocumentP51700034608 · Phase 1 Engr cert Sep 24.pdf · uploaded 19 Oct 2024Source
- DocumentP51700034608 · Phase 1 Engr cert Sep 24.pdf · uploaded 19 Oct 2024Source
- DocumentP51700049514 · Phase 3 Engr Cert Sep 24.pdf · uploaded 19 Oct 2024Source
- DocumentP51700049514 · Phase 3 Engr Cert Sep 24.pdf · uploaded 19 Oct 2024Source
- DocumentP51700049514 · Phase 3 Engr Cert Sep 24.pdf · uploaded 19 Oct 2024Source
- DocumentP51700053668 · Phase 4 Engr cert Sep 24.pdf · uploaded 19 Oct 2024Source
- DocumentP51700053668 · Phase 4 Engr cert Sep 24.pdf · uploaded 19 Oct 2024Source
- DocumentP51700053668 · Phase 4 Engr cert Sep 24.pdf · uploaded 19 Oct 2024Source
- DocumentP51700046541 · Ascend RERA Ph 2 Engr cert Dec 24.pdf · uploaded 20 Jan 2025Source
- DocumentP51700046541 · Ascend RERA Ph 2 Engr cert Dec 24.pdf · uploaded 20 Jan 2025Source
- DocumentP51700046541 · Ascend RERA Ph 2 Engr cert Dec 24.pdf · uploaded 20 Jan 2025Source
- DocumentP51700034608 · Ascend RERA Ph 1 Engr cert Dec 24.pdf · uploaded 20 Jan 2025Source
- DocumentP51700034608 · Ascend RERA Ph 1 Engr cert Dec 24.pdf · uploaded 20 Jan 2025Source
- DocumentP51700034608 · Ascend RERA Ph 1 Engr cert Dec 24.pdf · uploaded 20 Jan 2025Source
- DocumentP51700049514 · Ascend RERA Ph 3 Engr cert Dec 24.pdf · uploaded 20 Jan 2025Source
- DocumentP51700049514 · Ascend RERA Ph 3 Engr cert Dec 24.pdf · uploaded 20 Jan 2025Source
- DocumentP51700049514 · Ascend RERA Ph 3 Engr cert Dec 24.pdf · uploaded 20 Jan 2025Source
- DocumentP51700053668 · Ascend RERA Ph 4 Engr cert Dec 24.pdf · uploaded 20 Jan 2025Source
- DocumentP51700053668 · Ascend RERA Ph 4 Engr cert Dec 24.pdf · uploaded 20 Jan 2025Source
- DocumentP51700053668 · Ascend RERA Ph 4 Engr cert Dec 24.pdf · uploaded 20 Jan 2025Source
- DocumentP51700046541 · Ascend Phase 2 engineers certificate Mar 25.pdf · uploaded 17 Apr 2025Source
- DocumentP51700034608 · Ascend Phase 1 Engineers certificate Mar 25.pdf · uploaded 17 Apr 2025Source
- DocumentP51700049514 · Ascend Phase 3 Engineers certificate Mar 25.pdf · uploaded 17 Apr 2025Source
- DocumentP51700053668 · Ascend Phase 4 Engineer certificate Mar 25.pdf · uploaded 17 Apr 2025Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Thane (M Corp.), Thane taluka
Survey, CTS, gat or plot numbers
Boundaries
- North
- Survey number 38 and 104
- South
- Survey number 69 and 71
- East
- Survey number 97
- West
- Survey number 4
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. | RERA |
|---|---|---|---|
| Chartered accountant | Piyush Jain | — | P51700046541 |
| Chartered accountant | Piyush Jain | — | P51700049514 |
| Chartered accountant | Piyush Jain | — | P51700034608 |
| Chartered accountant | Rupen Dilip Kumar Shah | — | P51700046541 |
| Chartered accountant | Rupen Dilip Kumar Shah | — | P51700049514 |
| Chartered accountant | Rupen Dilip Kumar Shah | — | P51700034608 |
| Engineer | Rajendra Joshi | — | P51700034608 |
| Engineer | Rajendra Joshi | — | P51700049514 |
| Engineer | Rajendra Joshi | — | P51700046541 |
Source: MahaRERA project page. Contact details are not shown.