Of 6 registrations whose promised date has arrived, 5 kept it (83%). The rest ran a median 4 mo late.

Projects1928 RERA registrations
Kept RERA date83%Maharashtra: 73%
Median delay4 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases3no insolvency

14 registrations of 28 ran past the RERA date

Months late against the original RERA promise, per registration

28 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

CaseProjectDate
complaintGodrej ReserveComplaint CC006000000591382Not on record
complaintGodrej ReserveComplaint CC006000000591385Not on record
complaintGodrej ReserveComplaint CC12501911Not on record

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
The Trees, OriginsP51800000158KurlaCertificate Signed30 Jun 202330 Jun 2023On date
The Trees Residential Phase 2P51800000161KurlaCertificate Signed30 Jun 202230 Jun 2022On date
The Trees, Residential Phase 1P51800000165KurlaCertificate Signed30 Jun 202230 Jun 2022On date
Godrej AnandamP50500004427Nagpur (M Corp.)Certificate Signed29 Aug 202429 Aug 2024+26 mo*
Godrej Urban ParkP51800028364KurlaCertificate Signed30 Sep 202630 Sep 2026On date
Godrej Riviera Phase 1P51700032552KalyanCertificate Signed16 Dec 202716 Dec 2027On date
Godrej AscendP51700034608Thane (M Corp.)Certificate Signed30 Apr 202830 Aug 2028+4 mo
Godrej AscendP51700046541Thane (M Corp.)Certificate Signed31 Dec 202830 Apr 2029+4 mo
Godrej Orchard EstateP50500048466BesaCertificate Signed31 Dec 202431 Dec 2024On date
Godrej AscendP51700049514Thane (M Corp.)Certificate Signed31 Oct 202928 Feb 2030+4 mo
Godrej Emerald WatersP52100051200Pimpri Chinchawad (M Corp.)Certificate Signed28 Feb 202928 Feb 2029On date
Godrej AscendP51700053668Thane (M Corp.)Certificate Signed31 Dec 202930 Apr 2030+4 mo
Godrej Sky TerracesP51800053882DeonarActive25 Mar 2029—On date
Godrej CarmichaelP51900054088Malabar HillCertificate Signed31 Dec 203031 Dec 2030On date
Godrej ReserveP51800054690AkurliActive30 Jun 2030—On date
Godrej ReserveP51800054691AkurliActive30 Jun 2030—On date
Godrej ReserveP51800054703AkurliActive30 Jun 2030—On date
Godrej ReserveP51800055694AkurliCertificate Signed30 Jun 203030 Jun 2030On date
Godrej NurtureP51800077080BhandupCertificate Signed31 Mar 203231 Mar 2032On date
Godrej NurtureP51800077085BhandupCertificate Signed31 Mar 203231 Jul 2032+4 mo
Godrej SkylinePM1260002400007Keshavnagar MundwaCertificate Signed31 Jul 202930 Nov 2029+4 mo
Godrej SquareP51800077810BhandupCertificate Signed31 Oct 202828 Feb 2029+4 mo
Godrej ReserveP51800079457AkurliCertificate Signed30 Jun 203130 Oct 2031+4 mo
Godrej SkyshorePM1180002500076VarsovaCertificate Signed31 Dec 203130 Apr 2032+4 mo
Godrej Eternal PalmsPM1330002500429Navi Mumbai (M Corp.)Certificate Signed31 Dec 203230 Apr 2033+4 mo
Godrej ElarisPM1260002501385Mundhwa SouthCertificate Signed16 May 203216 Sep 2032+4 mo
Godrej VaranyaPM1271012502176KhargharCertificate Signed30 Jun 203430 Oct 2034+4 mo
Godrej VaranyaPM1271012502343KhargharCertificate Signed31 Dec 203230 Apr 2033+4 mo