RERA projects in Rahanal (Ct)

2 projects under 2 MahaRERA registrations, registered 2020–2023. 50% have a completion date extended beyond the one promised.

Locality
2RERA projects
2Registrations
1Completion still due1 past their completion date
4 monthsMedian extension beyond promised date50% of registrations extended
0Regulatory casesnone on MahaRERA's lists
9Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20201
20210
20220
20231

Projects in Rahanal (Ct)

2 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Munisuvrat Textile ParkMunisuvrat Commercial Parks LLPP5170005239321 Aug 202331 Mar 202731 Jul 2027Extended 4 mo0
Siddhivinayak GardensA1 BuildconP5170002508818 Mar 202030 Dec 202430 Dec 2024Promised date passed0

Other localities in Bhiwandi

Most active promoters

By projects registered here, as named on MahaRERA.

  1. A1 Buildcon1 project
  2. Munisuvrat Commercial Parks LLP1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology