RERA projects in Purne (Ct)

3 projects under 8 MahaRERA registrations, registered 2017–2023. 13% have a completion date extended beyond the one promised.

Locality
3RERA projects
8Registrationssome projects hold several
7Completion still due1 past their completion date
4 monthsMedian extension beyond promised date13% of registrations extended
0Regulatory casesnone on MahaRERA's lists
10Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20171
20180
20190
20200
20210
20223
20234

Projects in Purne (Ct)

3 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Dosti Greater Thane Sector 3A Cluster 1BAdrika Developers Private LimitedP51700053057, P51700053096, P5170005321712 Oct 202331 Oct 203031 Oct 2030Not yet due0
DGT Sector 3AAdrika Developers Private LimitedP51700048333, P51700048334, P51700048335 +126 Dec 202231 Aug 202831 Aug 2028Not yet due0
Deepraj ResidencyDeepraj EnterprisesP517000119671 Sep 201731 Dec 201931 Dec 2019Promised date passed0

Other localities in Bhiwandi

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Adrika Developers Private Limited2 projects
  2. Deepraj Enterprises1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology