Deedo IDDP-THN-9SJ3Completion was pushed back 4 months, to Apr 2030; no MahaRERA orders on record; 67% of its units are booked.
Owale, Thane 400615 · by Unnathi Associates · 100% of its projects kept the RERA date
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2030
- This projectRegistered 29 Mar 2019, completion promised 30 Dec 2029, revised to 30 Apr 2030.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
2 buildings
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700020244
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700020244 | 29 Mar 2019 | 30 Dec 2029 | 30 Apr 2030 | Unnathi Associates | Project page |
Documents48
2 documents held by Deedo, 46 filings listed on MahaRERA's project page
Show all 48 documentsShow fewer documents
Legal
Migrated
- 1 PAN CardUA PAN.pdf · uploaded 26 Mar 2019Source
- 1 Copy of the legal title reportTITLE 1.pdf · uploaded 26 Mar 2019Source
- 2 Copy of the legal title reportTITLE 2.pdf · uploaded 26 Mar 2019Source
- 3 Copy of the legal title reportTITLE 3.pdf · uploaded 26 Mar 2019Source
- 4 Copy of the legal title reportTITLE 4.pdf · uploaded 26 Mar 2019Source
- 5 Copy of the legal title reportTITLE 5.pdf · uploaded 26 Mar 2019Source
- 6 Copy of the legal title reportTITLE 6.pdf · uploaded 26 Mar 2019Source
- 7 Copy of the legal title reportTITLE 7.pdf · uploaded 26 Mar 2019Source
- 1 Details of encumbrancesEncumbrace.pdf · uploaded 26 Mar 2019Source
- 1 Copy of Layout Approval (in case of layout)RAUNAK BILLS - LAYOUT.pdf · uploaded 26 Mar 2019Source
- 1 Building Plan Approval (IOD)B2 - BUILDING PLAN.pdf · uploaded 26 Mar 2019Source
- 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 26 Mar 2019Source
- 1 Declaration in FORM BForm B - Raunak Bliss - B2.pdf · uploaded 26 Mar 2019Source
- 1 Proforma of Allotment letterFSA -Raunak Bliss RERA Agreement -B2.pdf · uploaded 26 Mar 2019Source
- 1 Certificates of CA (Form 3)CA Certificate Bliss B2_compressed.pdf · uploaded 27 Mar 2019Source
- 1 Form 2AForm 2A- UA- Raunak Bliss-B2.pdf · uploaded 8 Jul 2019Source
- 2 Form 2AForm - 2A Raunak Bliss-B2.pdf · uploaded 4 Nov 2019Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Raunak Bliss B2.pdf · uploaded 18 Dec 2019Source
- 3 Form 2ARaunak Bliss - B2.pdf · uploaded 3 Jan 2020Source
- 1 Details of Restarting of Construction work post lockdownRB - B2 RERA Updation - Restarting Work.pdf · uploaded 26 Jun 2020Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Raunak Bliss - B2.pdf · uploaded 17 Mar 2021Source
- 4 Form 2ARaunak Bliss B2.pdf · uploaded 1 Jul 2021Source
- 5 Form 2ARaunak Bliss B2.pdf · uploaded 18 Oct 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Raunak Bliss B2.pdf · uploaded 8 Apr 2022Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)BlissB2_22.pdf · uploaded 2 May 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)UA_FORM5_RAUNAK BLISS B2_21-22.pdf · uploaded 22 Oct 2022Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Rauank Bliss B2 Form 2A 2023.pdf · uploaded 4 Oct 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form5_Bliss_B2_O.pdf · uploaded 23 Nov 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)14_Form-2A-Raunak Bliss B2 - Old.pdf · uploaded 3 Jul 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)B2_Old.pdf · uploaded 29 Oct 2024Source
- 1 Certificates of CA (Form 3)CA Certificate Raunak Bliss B2 30092024.pdf · uploaded 13 Dec 2024Source
- Form 1Form 1 Bliss B2 31032025.pdf · uploaded 3 Jul 2025Source
- Form 2Form 2 Eng Certificate B2.pdf · uploaded 3 Jul 2025Source
- Form 3Signed CA Certificate Raunak Bliss B2 31032025.pdf · uploaded 3 Jul 2025Source
- Disclosure of Sold and Booked InventoryB2 Sold Inventory 31032025.pdf · uploaded 3 Jul 2025View
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 21/1 21/3 21/4 21/5
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Address
- 21/1 21/3 21/4 21/5, Owale, OwalePIN 400615
- Village
- Thane (M Corp.), Thane taluka
- Land area for this project
- 964 sq m (10,372 sq ft)
- Permissible built-up area
- 8,700 sq m (93,646 sq ft)
- Sanctioned built-up area
- 7,850 sq m (84,497 sq ft)
- Designated bank account
- 76
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
21/1 21/3 21/4 21/5
Boundaries
- North
- 30 Mtr Dp Road
- South
- 40 Mtr Dp Road
- East
- 30 Mtr Dp Road
- West
- 40 Mtr Dp Road
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals1
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Scapes | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Owale
- Shree SienaRERA PR1330002601104
- Delta Greenville - AsterRERA P51700078827
- Delta Greenville - CedarRERA P51700078829
- Raunak Bliss B4RERA P51700050829
- Raunak Bliss B5RERA P51700050828
- Raunak Bliss B6RERA P51700050827
- Horizon PearlRERA P51700050797
- Elita D3RERA P51700034754
All 28 projects in Owale · Compare Raunak Bliss - B2 with another project