Unnathi Associates

Deedo IDDD-4FF9

Of 4 registrations whose promised date has arrived, 4 kept it (100%).

Projects1414 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

10 of 14 registrations with dates moved or missed their RERA date · months late against the original promise

14 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Raunak HeightsP51700000766Thane (M Corp.)Certificate Signed30 Dec 202530 Dec 2025On date
Raunak DelightP51700002037Thane (M Corp.)Certificate Signed31 Dec 201831 Dec 2018On date
Raunak Bliss Phase AP51700005363Thane (M Corp.)Certificate Signed30 Dec 202430 Dec 2024On date
Raunak Bliss Phase A - A3P51700007033OwaleCertificate Signed30 Jun 202630 Jun 2026On date
Raunak Bliss - B1P51700020204Thane (M Corp.)Certificate Signed30 Dec 202930 Apr 2030+4 mo
Raunak Bliss - B2P51700020244Thane (M Corp.)Certificate Signed30 Dec 202930 Apr 2030+4 mo
Raunak 108P51700028435Thane (M Corp.)Certificate Signed30 Jun 202730 Oct 2027+4 mo
Raunak Bliss B1P51700046534ThaneCertificate Signed31 Dec 202930 Apr 2030+4 mo
Raunak Bliss B3P51700046564ThaneCertificate Signed31 Dec 202930 Apr 2030+4 mo
Raunak Bliss B2P51700046565ThaneCertificate Signed31 Dec 202930 Apr 2030+4 mo
Raunak Bliss A4P51700046674ThaneCertificate Signed31 Dec 202930 Apr 2030+4 mo
Raunak Bliss B6P51700050827Thane (M Corp.)Certificate Signed31 Dec 203030 Apr 2031+4 mo
Raunak Bliss B5P51700050828Thane (M Corp.)Certificate Signed31 Dec 203030 Apr 2031+4 mo
Raunak Bliss B4P51700050829Thane (M Corp.)Certificate Signed31 Dec 203030 Apr 2031+4 mo
Show all 14 registrationsShow fewer

Unnathi Associates, in questions

Does Unnathi Associates finish projects on time?

Of 4 MahaRERA registrations whose promised completion date has arrived, 4 kept it (100%). Across Maharashtra, 73% kept their date.

How many projects has Unnathi Associates registered with MahaRERA?

14 projects under 14 MahaRERA registrations; 4 completed on MahaRERA.

Does Unnathi Associates have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology