Deedo IDDP-THN-WAF3Completion was pushed back 4 months, to Apr 2033; no MahaRERA orders on record; 35% of its units are booked.
Mogharpada, Thane 400615 · by Neelshilp Constructions Private Limited
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2033
- This projectRegistered 15 Dec 2025, completion promised 31 Dec 2032, revised to 30 Apr 2033.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationPR1330002501763
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| PR1330002501763 | 15 Dec 2025 | 31 Dec 2032 | 30 Apr 2033 | Neelshilp Constructions Private Limited | Project page |
Documents34
1 document held by Deedo, 33 filings listed on MahaRERA's project page
Finance
Legal
- OthersDETAILS OF ENCUMBRANCES- LITIGATION.pdf · uploaded 8 Dec 2025Source
- OthersANNEXURE- A - Sandesh Ambre (upload).pdf · uploaded 8 Dec 2025Source
- OthersANNEXURE- A - Milind Mohod (upload).pdf · uploaded 8 Dec 2025Source
- OthersSelf - declaration for Name change.pdf · uploaded 8 Dec 2025Source
- Declaration Form BTitle Report - New.pdf · uploaded 8 Dec 2025Source
Show all 34 documentsShow fewer documents
Legal
- Declaration Form BDeclaration - Form B.pdf · uploaded 8 Dec 2025Source
- Declaration Form BConveyance Deed - 19112024 (upload).pdf · uploaded 8 Dec 2025Source
- Declaration Form BExchange Deed - 12022025 - 3124 (upload).pdf · uploaded 8 Dec 2025Source
- Declaration Form BExchange Deed - 12022025 - 3125 (upload).pdf · uploaded 8 Dec 2025Source
- Declaration Form B7- 12 - 63-1 - 19112025.pdf · uploaded 8 Dec 2025Source
- Declaration Form B7- 12 - 63-2-B - 19112025.pdf · uploaded 8 Dec 2025Source
Migrated
- Withdrawal Update Form 1Withdrawal Update Form 1 · uploaded 3 Feb 2026Source
- Withdrawal Update Form 2Withdrawal Update Form 2 · uploaded 3 Feb 2026Source
- Withdrawal Update Form 3CA Certificates Elyra by Puraniks.pdf · uploaded 3 Feb 2026Source
- Withdrawal Update Form 1Form 1 - Elyra.pdf · uploaded 20 Apr 2026Source
- Withdrawal Update Form 1Form 1 - Elyra.pdf · uploaded 20 Apr 2026Source
- Withdrawal Update Form 2Form 2.pdf · uploaded 20 Apr 2026Source
- Withdrawal Update Form 2Form 2.pdf · uploaded 20 Apr 2026Source
- Withdrawal Update Form 3Form 3 Final.pdf · uploaded 20 Apr 2026Source
- Withdrawal Update Form 3Form 3 Final.pdf · uploaded 20 Apr 2026Source
- Withdrawal Update Form 1Form 1 - Architect Certificate.pdf · uploaded 20 Jul 2026Source
- Withdrawal Update Form 2Form 2 Engineers Certificate Elyra.pdf · uploaded 20 Jul 2026Source
- Withdrawal Update Form 3Form 3 - CA Certificates.pdf · uploaded 20 Jul 2026Source
- Form 5 (FY 2025-2026)Elyra by Puraniks - sign.pdf · uploaded 30 Sep 2026Source
Technical
- Document2025 SANCTION_CC -17-11-2025_PLAN-1 Highlight.pdf · uploaded 5 Dec 2025Source
- Document2025 SANCTION_CC -17-11-2025_PLAN-2.pdf · uploaded 5 Dec 2025Source
- Others4 Arch Dept - Annexure D- Declaration for Commencement Certificate - done.pdf · uploaded 8 Dec 2025Source
- OthersCC verification email.pdf · uploaded 8 Dec 2025Source
- DocumentDeclaration one plot one registration.pdf · uploaded 10 Dec 2025Source
Technical (Architect)
- DocumentForm 1 - Architect Certificate.pdf · uploaded 20 Jul 2026Source
Technical (Engineer)
- DocumentForm 2 Engineers Certificate Elyra.pdf · uploaded 20 Jul 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 2B, Survey No. Old 52 New 63 Hissa Nos. 1
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- —119 units in all
- Address
- Ghodbunder Road, Mouje MogharpadaPIN 400615
- Village
- Mogharpada, Thane taluka
- Location
- 19.27566, 72.96481
- Land area for this project
- 1,205 sq m (12,971 sq ft)
- Permissible built-up area
- 5,469 sq m (58,873 sq ft)
- Sanctioned built-up area
- 5,469 sq m (58,873 sq ft)
- Recreational open space
- 0 sq m (0 sq ft)
- Designated bank account
- 76
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
Survey No. Old 52 New 63 Hissa Nos. 1 and 2B
Boundaries
- North
- Garden Reservation/Access
- South
- S. No. 52/2
- East
- Garden Reservaton Area No. 3
- West
- S. No. 55/4A
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking119 units
119 units registered
| Type | Carpet area | Units |
|---|---|---|
| — | — | 119 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals1
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Engineer | Saurabh Raikar | — |
Source: MahaRERA project page. Contact details are not shown.