PR1330002501763

Elyra by Puraniks · Mogharpada, Thane · Neelshilp Constructions Private Limited

Promised for 31 Dec 2032, extended to 30 Apr 2033, which is still ahead.

The revised date is 4 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Dec 2032 to 30 Apr 2033.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate15 Dec 2025View

Orders 0

No MahaRERA order or list names this number.

Questions about PR1330002501763

Is Elyra by Puraniks delayed?

Its completion moved from 31 Dec 2032 to 30 Apr 2033; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for PR1330002501763. The completion date moved from 31 Dec 2032 to 30 Apr 2033.

Who is the promoter?

MahaRERA records Neelshilp Constructions Private Limited as the promoter of PR1330002501763.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names PR1330002501763.

Answers are generated from the record.

Data through23 Nov 2026, 01:56SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology