Residential / Group Housing · 1 building · 45 unitsRERA P51700023918

Krishna Sankul B Wing

Deedo IDDP-THN-F42K

Its promised completion date, Dec 2025, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 60% of its units are booked.

Manjarli, Thane 421503 · by Krishna Enterprises · 67% of its projects kept the RERA date

Delivery11 mo past duePromised Dec 2025 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales60% booked27 of 45 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Its promised completion date, Dec 2025, has passed and MahaRERA does not show it completed

  • This projectRegistered 14 Jan 2020, completion promised 30 Dec 2025, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700023918
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170002391814 Jan 202030 Dec 202530 Dec 2025M/S Krishna EnterprisesProject page
Documents110

1 document held by Deedo, 109 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN number.pdf · uploaded 8 Aug 2019Source

Legal

  • Declaration Form BForm B 1MB.pdf · uploaded 8 Aug 2019Source
  • OtherDeed Of Declaration.pdf · uploaded 28 Dec 2019Source
  • OtherPartnership Deed.pdf · uploaded 28 Dec 2019Source
  • OtherCLARIFICATION LETTER.pdf · uploaded 28 Dec 2019Source
  • Legal Title reportTITLE REPORT 1 MB.pdf · uploaded 3 Jan 2020Source
  • OtherLetter.pdf · uploaded 28 Oct 2023Source
Show all 110 documentsShow fewer documents

Migrated

  • 1 PAN CardPAN number.pdf · uploaded 8 Aug 2019Source
  • 1 Details of encumbrancesNan Encumberance.pdf · uploaded 8 Aug 2019Source
  • 1 Declaration in FORM BForm B 1MB.pdf · uploaded 8 Aug 2019Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect certificate 1MB.pdf · uploaded 8 Aug 2019Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)engineer certificate 1MB.pdf · uploaded 8 Aug 2019Source
  • 1 Proforma of Allotment letterAllotment Latter.pdf · uploaded 8 Aug 2019Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Form3.pdf · uploaded 26 Aug 2019Source
  • 2 Proforma of Allotment letterProforma of Agreement for Sale.pdf · uploaded 4 Nov 2019Source
  • 1 Copy of Layout Approval (in case of layout)LAYOUT.pdf · uploaded 28 Dec 2019Source
  • 1 Building Plan Approval / NA Order for plotted developmentBUILDING PLAN.PDF · uploaded 28 Dec 2019Source
  • 1 OtherDeed Of Declaration.pdf · uploaded 28 Dec 2019Source
  • 2 OtherPartnership Deed.pdf · uploaded 28 Dec 2019Source
  • 3 OtherCLARIFICATION LETTER.pdf · uploaded 28 Dec 2019Source
  • 1 Copy of the legal title reportTITLE REPORT 1 MB.pdf · uploaded 3 Jan 2020Source
  • 1 Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT 1.pdf · uploaded 3 Jan 2020Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)31 12 19.pdf · uploaded 5 Aug 2021Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)31 3 20.pdf · uploaded 5 Aug 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)30 6 20.pdf · uploaded 5 Aug 2021Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)30 9 20.pdf · uploaded 5 Aug 2021Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)31 12 20.pdf · uploaded 5 Aug 2021Source
  • 4 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)31 3 21.pdf · uploaded 5 Aug 2021Source
  • 1 Disclosure of sold/ booked inventoryDeclaration Inventory.pdf · uploaded 5 Aug 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form 5 19 20.pdf · uploaded 5 Aug 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5 20 21.pdf · uploaded 5 Aug 2021Source
  • 1 Declaration about Commencement CertificateDeclaration.pdf · uploaded 4 Oct 2021Source
  • 2 Building Plan Approval / NA Order for plotted developmentWing B.pdf · uploaded 20 Oct 2021Source
  • 2 Disclosure of sold/ booked inventoryDeclaration of Sold Flats.pdf · uploaded 23 Apr 2022Source
  • 1 CERSAI detailsCERSAI REPORT.pdf · uploaded 2 Jun 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5.pdf · uploaded 20 Dec 2022Source
  • 3 Disclosure of sold/ booked inventoryDeclosure of Inventory.pdf · uploaded 4 Feb 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 4 Apr 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Krishna Enterprises.pdf · uploaded 28 Sep 2023Source
  • 3 Building Plan Approval / NA Order for plotted developmentBlue Print.pdf · uploaded 27 Oct 2023Source
  • 2 Commencement Certificates / NA Order for plotted developmentCommencement Certificate Revised.pdf · uploaded 27 Oct 2023Source
  • 2 Declaration about Commencement CertificateDeclaration about Commencement Certificate.pdf · uploaded 27 Oct 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 27 Oct 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 27 Oct 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 27 Oct 2023Source
  • 1 Proforma of Agreement for saleProforma of Agreement for Sale.pdf · uploaded 28 Oct 2023Source
  • 4 OtherLetter.pdf · uploaded 28 Oct 2023Source
  • 4 Disclosure of sold/ booked inventoryDeclaration of Inventory.pdf · uploaded 31 Oct 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the samebank account declaration.pdf · uploaded 5 Apr 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)architect certificate.pdf · uploaded 29 May 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)eng certificate.pdf · uploaded 29 May 2024Source
  • 5 Disclosure of sold/ booked inventoryDisclosure sold unsold inventory.pdf · uploaded 29 May 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 23-24.pdf · uploaded 28 Oct 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2A.pdf · uploaded 8 Nov 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A 23-24.pdf · uploaded 18 Nov 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A 23-24.pdf · uploaded 18 Nov 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 April 24 to June 24.pdf · uploaded 18 Feb 2025Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 July 24 to Sept 24.pdf · uploaded 18 Feb 2025Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Oct 24 to Dec 24.pdf · uploaded 18 Feb 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Jan 24 to March 24.pdf · uploaded 18 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Oct to Dec 23.pdf · uploaded 18 Feb 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Jan to Mar 24.pdf · uploaded 18 Feb 2025Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Apr to june 24.pdf · uploaded 18 Feb 2025Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 July to Sept 24.pdf · uploaded 18 Feb 2025Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Oct to Dec 24.pdf · uploaded 18 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 April 24 to June 24.pdf · uploaded 18 Feb 2025Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Oct 24 to Dec 24.pdf · uploaded 18 Feb 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 July 24 to Sept 24.pdf · uploaded 18 Feb 2025Source
  • 1 Disclosure of sold/ booked inventoryDOI 30 06 24.pdf · uploaded 18 Feb 2025Source
  • 2 Disclosure of sold/ booked inventoryDOI 30 09 24.pdf · uploaded 18 Feb 2025Source
  • 3 Disclosure of sold/ booked inventoryDOI 31 12 24.pdf · uploaded 18 Feb 2025Source
  • Form 1Form 1 March 24.pdf · uploaded 13 Aug 2026Source
  • Form 2Form 2 March 24.pdf · uploaded 13 Aug 2026Source
  • Form 3Form 3 March 24.pdf · uploaded 13 Aug 2026Source
  • Disclosure of Sold and Booked InventoryDisclosure of Inventory.pdf · uploaded 13 Aug 2026Source
  • Form 1Form 1 June 24.pdf · uploaded 13 Aug 2026Source
  • Form 2Form 2 June 24.pdf · uploaded 13 Aug 2026Source
  • Form 3Form 3 June 24.pdf · uploaded 13 Aug 2026Source
  • Disclosure of Sold and Booked InventoryDisclosure of Inventory.pdf · uploaded 13 Aug 2026Source
  • Form 1Form 1 Sept 2024.pdf · uploaded 13 Aug 2026Source
  • Form 2Form 2 Sept 2024.pdf · uploaded 13 Aug 2026Source
  • Form 3Form 3 Sept 2024.pdf · uploaded 13 Aug 2026Source
  • Disclosure of Sold and Booked InventoryDisclosure of Inventory.pdf · uploaded 13 Aug 2026Source
  • Form 1Form 1 Dec 24.pdf · uploaded 13 Aug 2026Source
  • Form 2Form 2 Dec 2024.pdf · uploaded 13 Aug 2026Source
  • Form 3Form 3 Dec 24.pdf · uploaded 13 Aug 2026Source
  • Disclosure of Sold and Booked InventoryDisclosure of Inventory.pdf · uploaded 13 Aug 2026Source
  • Withdrawal Update Form 1Form 1.pdf · uploaded 13 Aug 2026Source
  • Withdrawal Update Form 1Form 1.pdf · uploaded 13 Aug 2026Source
  • Withdrawal Update Form 1Form 1.pdf · uploaded 13 Aug 2026Source
  • Withdrawal Update Form 2Form 2.pdf · uploaded 13 Aug 2026Source
  • Withdrawal Update Form 2Form 2.pdf · uploaded 13 Aug 2026Source
  • Withdrawal Update Form 2Form 2.pdf · uploaded 13 Aug 2026Source
  • Withdrawal Update Form 3Form 3.pdf · uploaded 13 Aug 2026Source
  • Withdrawal Update Form 3Form 3.pdf · uploaded 13 Aug 2026Source
  • Withdrawal Update Form 3Form 3.pdf · uploaded 13 Aug 2026Source

Technical

  • DocumentLAYOUT.pdf · uploaded 28 Dec 2019Source
  • DocumentBUILDING PLAN.PDF · uploaded 28 Dec 2019Source
  • DocumentWing B.pdf · uploaded 20 Oct 2021Source
  • DocumentBlue Print.pdf · uploaded 27 Oct 2023Source

Technical (Architect)

  • DocumentForm 1 Jan 24 to March 24.pdf · uploaded 18 Feb 2025Source
  • DocumentForm 1 April 24 to June 24.pdf · uploaded 18 Feb 2025Source
  • DocumentForm 1 July 24 to Sept 24.pdf · uploaded 18 Feb 2025Source
  • DocumentForm 1 Oct 24 to Dec 24.pdf · uploaded 18 Feb 2025Source
  • DocumentForm 1.pdf · uploaded 13 Aug 2026Source

Technical (Engineer)

  • DocumentForm 2 April 24 to June 24.pdf · uploaded 18 Feb 2025Source
  • DocumentForm 2 July 24 to Sept 24.pdf · uploaded 18 Feb 2025Source
  • DocumentForm 2 Oct 24 to Dec 24.pdf · uploaded 18 Feb 2025Source
  • DocumentForm 2.pdf · uploaded 13 Aug 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel GUT NO 23 H NO 22/A

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
101, 102, 103, 104, 106, 107, 108, 201, 202, 203, 204, 205, 206, 207, 208, 301, 302, 303, 304, 305, 306, 307, 308, 401, 402, 403, 404, 405, 406, 407, 408, 501, 502, 503, 504, 505, 506, 507, 508, 601, 602, 603, 604, 605, Flat 10545 units in all
Address
Gut No 23 H No 22/A, Manjarli Road, ManjarliPIN 421503
Village
Badlapur (M Cl), Ambarnath taluka
Land area for this project
1,470 sq m (15,823 sq ft)
Permissible built-up area
1,673 sq m (18,012 sq ft)
Sanctioned built-up area
1,673 sq m (18,012 sq ft)
Developed in phases
No

Survey, CTS, gat or plot numbers

GUT NO 23 H NO 22/A

Land as published on MahaRERA's project page

GUT NO 23 H NO 22/A

Boundaries

North
Gut No 15 And 18 Tdr Wide D P Road
South
M G P Road
East
Access 4 Mtr Wide Road
West
Gut No 1 P

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking45 units

27 of 45 units booked (60%), as the promoter reported to MahaRERA

101 · 1 unit102 · 1 unit103 · 1 unit104 · 1 unit106 · 1 unit107 · 1 unit108 · 1 unit201 · 1 unit202 · 1 unit203 · 1 unit204 · 1 unit205 · 1 unit206 · 1 unit207 · 1 unit208 · 1 unit301 · 1 unit302 · 1 unit303 · 1 unit304 · 1 unit305 · 1 unit306 · 1 unit307 · 1 unit308 · 1 unit401 · 1 unit402 · 1 unit403 · 1 unit404 · 1 unit405 · 1 unit406 · 1 unit407 · 1 unit408 · 1 unit501 · 1 unit502 · 1 unit503 · 1 unit504 · 1 unit505 · 1 unit506 · 1 unit507 · 1 unit508 · 1 unit601 · 1 unit602 · 1 unit603 · 1 unit604 · 1 unit605 · 1 unitFlat 105 · 1 unit
TypeCarpet areaUnitsBooked
10133.7 sq m · 363 sq ft10
10245.94 sq m · 494 sq ft10
10333.7 sq m · 363 sq ft11
10432.75 sq m · 353 sq ft10
10632.58 sq m · 351 sq ft10
10733.7 sq m · 363 sq ft10
10824.28 sq m · 261 sq ft11
20133.7 sq m · 363 sq ft11
Show all 45 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
20245.94 sq m · 494 sq ft10
20333.7 sq m · 363 sq ft11
20432.75 sq m · 353 sq ft10
20533.7 sq m · 363 sq ft11
20632.58 sq m · 351 sq ft11
20733.7 sq m · 363 sq ft10
20824.28 sq m · 261 sq ft11
30133.7 sq m · 363 sq ft11
30245.94 sq m · 494 sq ft11
30333.7 sq m · 363 sq ft11
30432.75 sq m · 353 sq ft11
30533.7 sq m · 363 sq ft11
30632.58 sq m · 351 sq ft10
30733.7 sq m · 363 sq ft11
30824.28 sq m · 261 sq ft11
40133.7 sq m · 363 sq ft11
40245.94 sq m · 494 sq ft11
40333.7 sq m · 363 sq ft11
40432.75 sq m · 353 sq ft11
40533.7 sq m · 363 sq ft11
40632.58 sq m · 351 sq ft10
40733.7 sq m · 363 sq ft11
40824.28 sq m · 261 sq ft11
50133.7 sq m · 363 sq ft10
50224.28 sq m · 261 sq ft11
50333.7 sq m · 363 sq ft11
50432.75 sq m · 353 sq ft10
50533.7 sq m · 363 sq ft10
50632.58 sq m · 351 sq ft11
50733.7 sq m · 363 sq ft11
50824.28 sq m · 261 sq ft11
60133.7 sq m · 363 sq ft10
60232.75 sq m · 353 sq ft10
60333.7 sq m · 363 sq ft10
60432.58 sq m · 351 sq ft10
60533.7 sq m · 363 sq ft10
Flat 10533.7 sq m · 363 sq ft11

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals7

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectRaj Associates—
Chartered accountantAshwini K Prabhu & Associateshu—
Chartered accountantPritam Nevrekar & Associates—
Chartered accountantS D Satam & Co—
EngineerAtul Kurtarkar & Associates—
EngineerSaad Consultant—
OtherShantilal M Patel—

Source: MahaRERA project page. Contact details are not shown.