Residential / Group Housing · 1 building · 15 unitsRERA P51700030883

Mandar Arcade

Deedo IDDP-THN-33DZ

Its promised completion date, Jan 2024, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 0% of its units are booked.

Kulgaon, Thane 421503 · by Gaondevi Developers

Delivery2 yrs 10 mo past duePromised Jan 2024 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 15 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Its promised completion date, Jan 2024, has passed and MahaRERA does not show it completed

  • This projectRegistered 20 Sep 2021, completion promised 31 Jan 2024, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700030883
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170003088320 Sep 202131 Jan 202431 Jan 2024Gaondevi DevelopersProject page
Documents27

1 document held by Deedo, 26 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN_Gaondevi Dev.pdf · uploaded 22 Jul 2021Source

Legal

  • Legal Title reportLegal Title Report.pdf · uploaded 22 Jul 2021Source
  • Declaration Form BForm B - Gaondevi Developers.pdf · uploaded 26 Aug 2021Source

Migrated

  • 1 PAN CardPAN_Gaondevi Dev.pdf · uploaded 22 Jul 2021Source
  • 1 Copy of the legal title reportLegal Title Report.pdf · uploaded 22 Jul 2021Source
  • 1 Details of encumbrancesNo Encumbrance.pdf · uploaded 22 Jul 2021Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement.pdf · uploaded 22 Jul 2021Source
Show all 27 documentsShow fewer documents

Migrated

  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2- Gaondevi.pdf · uploaded 22 Jul 2021Source
  • 1 Proforma of Allotment letterAllotment letter.pdf · uploaded 5 Aug 2021Source
  • 2 Proforma of Allotment letterAgreement for sale.pdf · uploaded 5 Aug 2021Source
  • 1 Declaration in FORM BForm B - Gaondevi Developers.pdf · uploaded 26 Aug 2021Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect's Certificate.pdf · uploaded 26 Aug 2021Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_Gaondevi.pdf · uploaded 26 Aug 2021Source
  • 1 Copy of Layout Approval (in case of layout)Approval Plan Gaondevi Developers 7_Sept _21.pdf · uploaded 7 Sep 2021Source
  • 1 Building Plan Approval / NA Order for plotted developmentApproval Plan Gaondevi Developers 7_Sept _21.pdf · uploaded 7 Sep 2021Source
  • 1 Declaration about Commencement CertificateDeclaration about commencemet certificte.pdf · uploaded 7 Sep 2021Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT'S CERTIFICATE001.pdf · uploaded 23 Aug 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 3CA.pdf · uploaded 23 Aug 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3CA.pdf · uploaded 23 Aug 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5_Gaondevi Developers_FY22-23.pdf · uploaded 23 Oct 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-5_Gaondevi_22-23.pdf · uploaded 27 Oct 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form-5_Gaindevi_21-22.pdf · uploaded 27 Oct 2023Source

Technical

  • DocumentApproval Plan Gaondevi Developers 7_Sept _21.pdf · uploaded 7 Sep 2021Source
  • DocumentApproval Plan Gaondevi Developers 7_Sept _21.pdf · uploaded 7 Sep 2021Source

Technical (Architect)

  • DocumentARCHITECT'S CERTIFICATE001.pdf · uploaded 23 Aug 2023Source

Technical (Engineer)

  • DocumentForm-5_Gaondevi_22-23.pdf · uploaded 27 Oct 2023Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel Survey No.49H.No.21Plot No.7B

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 1RK, Office space, Shop15 units in all
Address
Survey No.49/H.No.21/Plot No.7B, KulgaonPIN 421503
Village
Badlapur (M Cl), Ambarnath taluka
Land area for this project
283 sq m (3,051 sq ft)
Permissible built-up area
339 sq m (3,652 sq ft)
Sanctioned built-up area
339 sq m (3,652 sq ft)
Designated bank account
66
Developed in phases
No

Survey, CTS, gat or plot numbers

Survey No.49H.No.21Plot No.7B

Land as published on MahaRERA's project page

Survey No.49/H.No.21/Plot No.7B

Boundaries

North
Plot No 8
South
Plot No 5
East
Pathway
West
20 Feet Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking15 units

0 of 15 units booked (0%), as the promoter reported to MahaRERA

1BHK · 6 units1RK · 3 unitsOffice space · 2 unitsShop · 4 units
TypeCarpet areaUnitsBooked
1BHK26.85 sq m · 289 sq ft30
1BHK27.7 sq m · 298 sq ft30
1RK17.12 sq m · 184 sq ft30
Office space12.15 sq m · 131 sq ft10
Office space14.41 sq m · 155 sq ft10
Shop8.3 sq m · 89 sq ft20
Shop9.15 sq m · 98 sq ft20

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectPramod V Patil & Associates—
Chartered accountantAishwarya Kale—
EngineerAtul Kudtarkar & Associates—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology