RERA projects in Kon (Ct)
34 projects under 34 MahaRERA registrations, registered 2017–2025. 47% have a completion date extended beyond the one promised.
Locality
34RERA projects
34Registrations
22Completion still due12 past their completion date
4 monthsMedian extension beyond promised date47% of registrations extended
1Regulatory caseson 1 project
63Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 2 |
| 2018 | 2 |
| 2019 | 3 |
| 2020 | 3 |
| 2021 | 1 |
| 2022 | 7 |
| 2023 | 8 |
| 2024 | 3 |
| 2025 | 5 |
Projects in Kon (Ct)
34 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Shree Saishraddha Apartment Building AShree Saishraddha Enterprises | P51700024939 | 12 Mar 2020 | 30 Mar 2023 | 30 Mar 2023 | Promised date passed | 0 |
| Flower ValleyJagani Developers | P51700024317 | 5 Feb 2020 | 9 Nov 2023 | 8 Nov 2025 | Extended 24 mo | 0 |
| Lalbaug DarshanVishal R Group & Enterprises | P51700021729 | 22 Jul 2019 | 30 Dec 2022 | 30 Dec 2022 | Promised date passed | 0 |
| Asmeeta Texpa - IIMagus Infratech Private Limited | P51700020215 | 29 Mar 2019 | 30 Dec 2030 | 30 Dec 2030 | Not yet due | 1 |
| Guruprabha SankulVinay Koli | P51700019996 | 15 Mar 2019 | 30 Dec 2021 | 30 Sep 2025 | Extended 45 mo | 0 |
| Kalyan NagariHonest Developers | P51700016054 | 13 Apr 2018 | 30 Mar 2024 | 30 Mar 2024 | Promised date passed | 0 |
| Continental FuturaContinental Sidhant Reality | P51700015939 | 9 Apr 2018 | 30 Mar 2024 | 31 Mar 2028 | Extended 48 mo | 0 |
| Yuvaansh ApartmentManvi Construction | P51700014634 | 20 Dec 2017 | 30 Dec 2021 | 30 Dec 2021 | Promised date passed | 0 |
| Asmeeta Infratech Limited - Asmeeta TexpaAsmeeta Infratech Limited | P51700009154 | 19 Aug 2017 | 31 Dec 2019 | 31 Dec 2019 | Promised date passed | 0 |
Other localities in Bhiwandi
Most active promoters
By projects registered here, as named on MahaRERA.
- Hendar Laxman Mhatre2 projects
- Honest Developers2 projects
- Kalyan Buildcon2 projects
- Magus Infratech Private Limited2 projects
- Shree Saishraddha Enterprises2 projects
- Trimurti Enterprises2 projects
- Al Bruj Developers1 project
- Asmeeta Infratech Limited1 project
- Cheroba Homes1 project
- Continental Sidhant Reality1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology