Residential / Group Housing · 5 buildings · 490 unitsRERA P51700020267

Palava Verde A - E

Deedo IDDP-THN-199Z

Its promised completion date, May 2025, has passed and MahaRERA does not show it completed; MahaRERA lists it: deregistered; 1% of its units are booked.

Khoni, Thane 421204 · by Palava Dwellers Pvt Ltd · 44% of its projects kept the RERA date

Delivery1 yr 6 mo past duePromised May 2025 · no extension on record · not shown completedRegulatoryDeregistered1 MahaRERA listing or order on recordSales1% booked6 of 490 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Its promised completion date, May 2025, has passed and MahaRERA does not show it completed

  • This projectRegistered 30 Mar 2019, completion promised 30 May 2025, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

5 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory record1

What MahaRERA has published about this project. A listing records what the authority published; it is not a judgment of the project.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700020267
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170002026730 Mar 201930 May 202530 May 2025Palava Dwellers Pvt LtdProject page
Documents107

2 documents held by Deedo, 105 filings listed on MahaRERA's project page

Registration certificate

Other

  • OtherDate not statedView

Legal

  • Legal Title reportPalava Lakefront Casa Florenica - Casa Florea - Casa Olivia - Casa Verde.pdf · uploaded 22 Mar 2019Source
  • Legal Title reportSupplemental Report on Title Lakefront.pdf · uploaded 22 Mar 2019Source
  • Declaration Form BVERDE A - E.pdf · uploaded 22 Mar 2019Source
  • Other – LegalAnnexure A.pdf · uploaded 14 Nov 2024Source
  • Other – LegalMDL Authority for RERA Registration.pdf · uploaded 14 Nov 2024Source
  • Other – LegalMDL-PDPL merger INC-28.pdf · uploaded 14 Nov 2024Source
Show all 107 documentsShow fewer documents

Legal

  • Other – LegalPalava Verde A E - Notary.pdf · uploaded 14 Nov 2024Source
  • Other – LegalNCLT Order Palava to MDL.pdf · uploaded 18 Nov 2024Source
  • Other – LegalNCLT Order Palava to MDL.pdf · uploaded 18 Nov 2024Source

Migrated

  • 1 Copy of the legal title reportPalava Lakefront Casa Florenica - Casa Florea - Casa Olivia - Casa Verde.pdf · uploaded 22 Mar 2019Source
  • 2 Copy of the legal title reportSupplemental Report on Title Lakefront.pdf · uploaded 22 Mar 2019Source
  • 1 Details of encumbrancesPalava Verde A to E.pdf · uploaded 22 Mar 2019Source
  • 1 Copy of Layout Approval (in case of layout)D01 - Sector-D - Layout Plan.pdf · uploaded 22 Mar 2019Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC.PDF · uploaded 22 Mar 2019Source
  • 1 Declaration in FORM BVERDE A - E.pdf · uploaded 22 Mar 2019Source
  • 1 Certificates of CA (Form 3)VERDE A E.pdf · uploaded 22 Mar 2019Source
  • 1 Proforma of Allotment letterATS Casa Verde.pdf · uploaded 22 Mar 2019Source
  • 1 Building Plan Approval (IOD)1_compressed (1).pdf · uploaded 29 Mar 2019Source
  • 2 Building Plan Approval (IOD)2.pdf · uploaded 29 Mar 2019Source
  • 3 Building Plan Approval (IOD)3.pdf · uploaded 29 Mar 2019Source
  • 4 Building Plan Approval (IOD)4.pdf · uploaded 29 Mar 2019Source
  • 1 Form 2AVERDE A TO E.pdf · uploaded 17 Jun 2019Source
  • 2 Form 2APalava Verde A to E.pdf · uploaded 28 Aug 2020Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)23 Palava Verde A to E.pdf · uploaded 27 Oct 2020Source
  • 3 Form 2AP51700020267.pdf · uploaded 13 Aug 2021Source
  • 2 Certificates of CA (Form 3)58 PALAVA VERDE A TO E.pdf · uploaded 9 Oct 2021Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)38 PALAVA VERDE A-E.pdf · uploaded 14 Oct 2021Source
  • 1 Disclosure of sold/ booked inventoryP51700020267.pdf · uploaded 14 Oct 2021Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)37_Verde A-E.pdf · uploaded 15 Oct 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)22 Palava Verde A To E.pdf · uploaded 15 Oct 2021Source
  • 4 Form 2A69 PALAVA VERDE A-E.pdf · uploaded 18 Nov 2021Source
  • 3 Certificates of CA (Form 3)58 PALAVA VERDE A - E.pdf · uploaded 15 Dec 2021Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)38 PALAVA VERDE A-E.pdf · uploaded 17 Dec 2021Source
  • 2 Disclosure of sold/ booked inventoryPalava Verde A-E.pdf · uploaded 27 Dec 2021View
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)58 PALAVA VERDE A TO E.pdf · uploaded 30 Jun 2022Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)58 PALAVA VERDE A TO E.pdf · uploaded 1 Sep 2022Source
  • 4 Certificates of CA (Form 3)58 PALAVA VERDE A TO E.pdf · uploaded 1 Sep 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)58 PALAVA VERDE A - E.pdf · uploaded 12 Nov 2022Source
  • 3 Disclosure of sold/ booked inventoryPalava Verde A-E.pdf · uploaded 28 Mar 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the same61 verde a to e.pdf · uploaded 27 Apr 2023Source
  • 4 Disclosure of sold/ booked inventorySold Unsold_Verde.pdf · uploaded 26 May 2023Source
  • 5 Disclosure of sold/ booked inventoryVerde A-E - March23.pdf · uploaded 24 Jul 2023Source
  • 6 Disclosure of sold/ booked inventoryPalava Verde A-E - June23.pdf · uploaded 24 Jul 2023Source
  • 5 Certificates of CA (Form 3)46 PALAVA VERDE A - E - Form3.pdf · uploaded 24 Jul 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Palava Verde A - E.pdf · uploaded 16 Oct 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Palava Verde A To E - Form1 - Sep23.pdf · uploaded 23 Nov 2023Source
  • 7 Disclosure of sold/ booked inventoryPalava Verde A-E - P51700020267.pdf · uploaded 8 Dec 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form1 - Palava Verde A-E - P51700020267 - Dec23.pdf · uploaded 26 Feb 2024Source
  • 8 Disclosure of sold/ booked inventorySold Unsold - Palava Verde A-E - P51700020267 - Dec23.pdf · uploaded 26 Feb 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)FY 18-19.pdf · uploaded 6 May 2024Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)FY 19-20.pdf · uploaded 6 May 2024Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)FY 20-21.pdf · uploaded 6 May 2024Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)FY 21-22.pdf · uploaded 6 May 2024Source
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)FY 22-23.pdf · uploaded 6 May 2024Source
  • 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)FY 23-24.pdf · uploaded 6 May 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)FY 18-19.pdf · uploaded 6 May 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)FY 19-20.pdf · uploaded 6 May 2024Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)FY 20-21.pdf · uploaded 6 May 2024Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)FY 21-22.pdf · uploaded 6 May 2024Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)FY 22-23.pdf · uploaded 6 May 2024Source
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)FY 23-24.pdf · uploaded 6 May 2024Source
  • 6 Certificates of CA (Form 3)FY 18-19.pdf · uploaded 6 May 2024Source
  • 7 Certificates of CA (Form 3)FY 19-20.pdf · uploaded 6 May 2024Source
  • 8 Certificates of CA (Form 3)FY 20-21.pdf · uploaded 6 May 2024Source
  • 9 Certificates of CA (Form 3)FY 21-22.pdf · uploaded 6 May 2024Source
  • 10 Certificates of CA (Form 3)FY 22-23.pdf · uploaded 6 May 2024Source
  • 11 Certificates of CA (Form 3)FY 23-24.pdf · uploaded 6 May 2024Source
  • 9 Disclosure of sold/ booked inventorySold Unsold - Palava Verde A-E - P51700020267 - March 24.pdf · uploaded 28 May 2024Source
  • 10 Disclosure of sold/ booked inventoryPalava Verde A-E - P51700020267 - June24.pdf · uploaded 7 Aug 2024Source
  • 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)Palava Verde A-E - P51700020267 - June24.pdf · uploaded 10 Aug 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)P51700020267 - Palava Verde A - E.pdf · uploaded 18 Oct 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 2 3 - March 24.pdf · uploaded 14 Nov 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 2 3 - Sep 24.pdf · uploaded 14 Nov 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 2 3 - June 24.pdf · uploaded 14 Nov 2024Source
  • 1 Certificates of CA (Form 3)Form 1 2 3 - March 24.pdf · uploaded 14 Nov 2024Source
  • 2 Certificates of CA (Form 3)Form 1 2 3 - June 24.pdf · uploaded 14 Nov 2024Source
  • 3 Certificates of CA (Form 3)Form 1 2 3 - Sep 24.pdf · uploaded 14 Nov 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 1 2 3 - March 24.pdf · uploaded 14 Nov 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 1 2 3 - June 24.pdf · uploaded 14 Nov 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 1 2 3 - Sep 24.pdf · uploaded 14 Nov 2024Source
  • 2 Other – LegalMDL Authority for RERA Registration.pdf · uploaded 14 Nov 2024Source
  • 4 Other – LegalPalava Verde A E - Notary.pdf · uploaded 14 Nov 2024Source
  • 3 Other – LegalMDL-PDPL merger INC-28.pdf · uploaded 14 Nov 2024Source
  • 1 Other – LegalAnnexure A.pdf · uploaded 14 Nov 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2A.pdf · uploaded 14 Nov 2024Source
  • 1 Disclosure of sold/ booked inventorySold Unsold - June 24.pdf · uploaded 14 Nov 2024Source
  • 2 Disclosure of sold/ booked inventorySold Unsold - Sep 24.pdf · uploaded 14 Nov 2024View
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2A.pdf · uploaded 14 Nov 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A.pdf · uploaded 14 Nov 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A.pdf · uploaded 14 Nov 2024Source
  • 1 Other – LegalNCLT Order Palava to MDL.pdf · uploaded 18 Nov 2024Source
  • 5 Other – LegalNCLT Order Palava to MDL.pdf · uploaded 18 Nov 2024Source

Technical

  • DocumentD01 - Sector-D - Layout Plan.pdf · uploaded 22 Mar 2019Source
  • Document1_compressed (1).pdf · uploaded 29 Mar 2019Source
  • Document2.pdf · uploaded 29 Mar 2019Source
  • Document3.pdf · uploaded 29 Mar 2019Source
  • Document4.pdf · uploaded 29 Mar 2019Source

Technical (Architect)

  • DocumentPalava Verde A-E - P51700020267 - June24.pdf · uploaded 10 Aug 2024Source
  • DocumentForm 1 2 3 - June 24.pdf · uploaded 14 Nov 2024Source
  • DocumentForm 1 2 3 - March 24.pdf · uploaded 14 Nov 2024Source
  • DocumentForm 1 2 3 - Sep 24.pdf · uploaded 14 Nov 2024Source

Technical (Engineer)

  • DocumentFY 23-24.pdf · uploaded 6 May 2024Source
  • DocumentForm 1 2 3 - March 24.pdf · uploaded 14 Nov 2024Source
  • DocumentForm 1 2 3 - June 24.pdf · uploaded 14 Nov 2024Source
  • DocumentForm 1 2 3 - Sep 24.pdf · uploaded 14 Nov 2024Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 61 PT, 62 PT

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK490 units in all
Address
61 PT, 62 PT, 63/2 PT, Kalyan Shifphata Road Palava, PalavaPIN 421204
Village
Khoni, Kalyan taluka
Land area for this project
7,076 sq m (76,164 sq ft)
Permissible built-up area
2,58,344 sq m (27,80,794 sq ft)
Sanctioned built-up area
2,55,766 sq m (27,53,045 sq ft)
Recreational open space
4,470 sq m (48,116 sq ft)
Designated bank account
76
Developed in phases
Yes

Survey, CTS, gat or plot numbers

61 PT62 PT63/2 PT

Land as published on MahaRERA's project page

61 PT,62 PT, 63/2 PT

Boundaries

North
63 by 2 and 64 by 2
South
61 and 62
East
53 by 1 and 148 by 13
West
63 by 2

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking490 units

6 of 490 units booked (1%), as the promoter reported to MahaRERA

1BHK · 232 units2BHK · 258 units
BuildingTypeCarpet areaUnitsBooked
Palava Verde A1BHK39.32 sq m · 423 sq ft440
Palava Verde A1BHK40.78 sq m · 439 sq ft22
Palava Verde A2BHK49.54 sq m · 533 sq ft240
Palava Verde A2BHK51.85 sq m · 558 sq ft20
Palava Verde A2BHK52.24 sq m · 562 sq ft220
Palava Verde B1BHK31.51 sq m · 339 sq ft10
Palava Verde B1BHK39.32 sq m · 423 sq ft750
Palava Verde B1BHK40.78 sq m · 439 sq ft11
Show all 35 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
Palava Verde B2BHK49.54 sq m · 533 sq ft240
Palava Verde B2BHK51.85 sq m · 558 sq ft20
Palava Verde B2BHK56.77 sq m · 611 sq ft10
Palava Verde B2BHK57.54 sq m · 619 sq ft110
Palava Verde C1BHK31.51 sq m · 339 sq ft10
Palava Verde C1BHK39.32 sq m · 423 sq ft500
Palava Verde C1BHK40.78 sq m · 439 sq ft11
Palava Verde C1BHK41.35 sq m · 445 sq ft10
Palava Verde C2BHK49.54 sq m · 533 sq ft350
Palava Verde C2BHK51.85 sq m · 558 sq ft30
Palava Verde C2BHK52.24 sq m · 562 sq ft120
Palava Verde C2BHK56.77 sq m · 611 sq ft10
Palava Verde C2BHK57.54 sq m · 619 sq ft110
Palava Verde D1BHK38.07 sq m · 410 sq ft20
Palava Verde D2BHK47.71 sq m · 514 sq ft230
Palava Verde D2BHK52.33 sq m · 563 sq ft10
Palava Verde D2BHK57.15 sq m · 615 sq ft120
Palava Verde D2BHK57.34 sq m · 617 sq ft120
Palava Verde D2BHK59.55 sq m · 641 sq ft11
Palava Verde E1BHK31.51 sq m · 339 sq ft10
Palava Verde E1BHK39.32 sq m · 423 sq ft500
Palava Verde E1BHK40.78 sq m · 439 sq ft11
Palava Verde E1BHK41.35 sq m · 445 sq ft20
Palava Verde E2BHK49.54 sq m · 533 sq ft470
Palava Verde E2BHK51.85 sq m · 558 sq ft20
Palava Verde E2BHK56.77 sq m · 611 sq ft10
Palava Verde E2BHK57.54 sq m · 619 sq ft110

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals7

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectVilas Desai & Associates—
Chartered accountantB B Jain & Associates—
Chartered accountantChirag Sarvaiya & Co—
Chartered accountantMska & Associates—
EngineerK C Shah Consultants—
Registered real estate agentHousenotch Private Limited—
Registered real estate agentShashi Kumar Sharma—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project page · MahaRERA regulatory lists and ordersData through is when MahaRERA's project page was last read.Report a problemMethodology