Palava Dwellers Pvt Ltd
Deedo IDDD-3B7WOf 9 registrations whose promised date has arrived, 4 kept it (44%). The rest ran a median 9 mo late.
Delivery record
6 of 10 registrations with dates moved or missed their RERA date · months late against the original promise
10 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Deregistered | PALAVA ALLURA C and DDeregistered: PALAVA ALLURA C and D | Not on record |
| Deregistered | Palava Verde A - EDeregistered: Palava Verde A - E | Not on record |
| Deregistered | Palava Fresca A and BDeregistered: Palava Fresca A and B | Not on record |
| Deregistered | Palava Verdana A to DDeregistered: Palava Verdana A to D | Not on record |
| Deregistered | Palava Fresca E to HDeregistered: Palava Fresca E to H | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| PALAVA ALLURA C and DP51700018963 | Khoni | Certificate Signed | 30 Mar 2024 | 30 Mar 2024 | +32 mo* |
| Palava Azzurra A To DP51700019016 | Khoni | Certificate Signed | 30 Mar 2024 | 30 Mar 2024 | On date |
| Palava FrescaP51700020139 | Khoni | Certificate Signed | 27 Nov 2026 | 27 Mar 2027 | +4 mo |
| Palava Verdana A to DP51700020150 | Khoni | Certificate Signed | 28 Nov 2025 | 28 Nov 2025 | +12 mo* |
| Palava Fresca A and BP51700020160 | Khoni | Certificate Signed | 30 May 2026 | 30 May 2026 | +6 mo* |
| Palava Fresca E to HP51700020165 | Khoni | Certificate Signed | 30 May 2026 | 30 May 2026 | +6 mo* |
| Palava FrescaP51700020166 | Khoni | Certificate Signed | 30 May 2026 | 30 May 2026 | On date |
| Palava Verde A - EP51700020267 | Khoni | Certificate Signed | 30 May 2025 | 30 May 2025 | +18 mo* |
| Violet E, F & JP51700022825 | Khoni | Certificate Signed | 31 Jul 2024 | 31 Jul 2024 | On date |
| Violet A to CP51700022900 | Khoni | Certificate Signed | 31 Jul 2024 | 31 Jul 2024 | On date |
Palava Dwellers Pvt Ltd, in questions
Does Palava Dwellers Pvt Ltd finish projects on time?
Of 9 MahaRERA registrations whose promised completion date has arrived, 4 kept it (44%). The rest ran a median 9 mo late. Across Maharashtra, 73% kept their date.
How many projects has Palava Dwellers Pvt Ltd registered with MahaRERA?
9 projects under 10 MahaRERA registrations; 4 completed on MahaRERA.
Does Palava Dwellers Pvt Ltd have MahaRERA regulatory cases?
5 regulatory cases name its registrations.