MahaRERA shows it completed, after its date was pushed back 3 years; no MahaRERA orders on record; 20% of its units are booked.

Kamatghar, Thane 421302 · by Suresh Mithalal Jain

DeliveryCompletedCompletion / occupancy certificate on MahaRERA · after a 3 yrs extensionRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales20% booked3 of 15 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed, after its date was pushed back 3 years

  • This projectRegistered 25 Oct 2017, completion promised 30 Sep 2019, revised to 30 Sep 2022.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700013727
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170001372725 Oct 201730 Sep 201930 Sep 2022Suresh Mithalal JainProject page
Documents59

3 documents held by Deedo, 56 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Other

  • OtherDate not statedView

Finance

  • PAN CardPANCARD.pdf · uploaded 30 Sep 2017Source

Legal

  • Declaration Form BForm B.pdf · uploaded 30 Sep 2017Source
  • Legal Title reportSearch Report.pdf · uploaded 30 Sep 2017Source

Migrated

  • 1 PAN CardPANCARD.pdf · uploaded 30 Sep 2017Source
  • 1 Copy of the legal title reportSearch Report.pdf · uploaded 30 Sep 2017Source
Show all 59 documentsShow fewer documents

Migrated

  • 1 Details of encumbrancesFree fom encrumbrances Declaration.pdf · uploaded 30 Sep 2017Source
  • 1 Copy of Layout Approval (in case of layout)Plan Layout.pdf · uploaded 30 Sep 2017Source
  • 1 Building Plan Approval (IOD)Development permission.pdf · uploaded 30 Sep 2017Source
  • 1 Declaration in FORM BForm B.pdf · uploaded 30 Sep 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)architect certificate.pdf · uploaded 30 Sep 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)engineer certificate.pdf · uploaded 30 Sep 2017Source
  • 1 Certificates of CA (Form 3)CA Certificate.pdf · uploaded 30 Sep 2017Source
  • 1 Proforma of Allotment letterallotment letter.pdf · uploaded 30 Sep 2017Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 11 Oct 2018Source
  • 1 Declaration about Commencement CertificateDECLARATION ABOUT COMMENCEMNT CERTIFICATE ON LETTER HEAD.pdf · uploaded 20 Oct 2021Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)March 2020_compressed.pdf · uploaded 20 Oct 2021Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Dec 2020_compressed.pdf · uploaded 20 Oct 2021Source
  • 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)June 2020_compressed.pdf · uploaded 20 Oct 2021Source
  • 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)March 2021_compressed.pdf · uploaded 20 Oct 2021Source
  • 6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Sept 2020_compressed.pdf · uploaded 20 Oct 2021Source
  • 7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)June 2021_compressed.pdf · uploaded 20 Oct 2021Source
  • 8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Sept 2021_compressed.pdf · uploaded 20 Oct 2021Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)1 March 2020_compressed.pdf · uploaded 20 Oct 2021Source
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)2 June 2020_compressed.pdf · uploaded 20 Oct 2021Source
  • 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)3 Sept 2020_compressed.pdf · uploaded 20 Oct 2021Source
  • 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)4 Dec 2020_compressed.pdf · uploaded 20 Oct 2021Source
  • 6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)5 March 2021_compressed.pdf · uploaded 20 Oct 2021Source
  • 7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)6 June 2021_compressed.pdf · uploaded 20 Oct 2021Source
  • 8 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)7 Sept 2021_compressed.pdf · uploaded 20 Oct 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)1 March 2020.pdf · uploaded 20 Oct 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)2 June 2020.pdf · uploaded 20 Oct 2021Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)3 Sept 2020.pdf · uploaded 20 Oct 2021Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)4 Dec 2020.pdf · uploaded 20 Oct 2021Source
  • 4 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)5 March 2021.pdf · uploaded 20 Oct 2021Source
  • 2 Certificates of CA (Form 3)1 Dec 2019.pdf · uploaded 20 Oct 2021Source
  • 3 Certificates of CA (Form 3)2 March 2020.pdf · uploaded 20 Oct 2021Source
  • 4 Certificates of CA (Form 3)3 June 2020.pdf · uploaded 20 Oct 2021Source
  • 5 Certificates of CA (Form 3)4 Sept 2020.pdf · uploaded 20 Oct 2021Source
  • 6 Certificates of CA (Form 3)5 Dec 2020.pdf · uploaded 20 Oct 2021Source
  • 7 Certificates of CA (Form 3)6 March 2021.pdf · uploaded 20 Oct 2021Source
  • 8 Certificates of CA (Form 3)7 June 2021.pdf · uploaded 20 Oct 2021Source
  • 9 Certificates of CA (Form 3)8 Sept 2021_compressed.pdf · uploaded 20 Oct 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)March 2019.pdf · uploaded 20 Oct 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)March 2020.pdf · uploaded 20 Oct 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)March 2021.pdf · uploaded 20 Oct 2021Source
  • 1 Disclosure of sold/ booked inventoryDECLARATION OF SOLD OR BOOKED FLATS .pdf · uploaded 21 Oct 2021Source
  • 2 Proforma of Allotment letterSimco Jyoti Developer Agreement for Sale Draft.pdf · uploaded 11 Dec 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Engineer Certificate 2021-2022.pdf · uploaded 16 Feb 2023Source
  • 2 Disclosure of sold/ booked inventorySimco Jyoti - Inventory disclosure.pdf · uploaded 16 Feb 2023View
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Simco Jyoti - Form 5 - CA certificate.pdf · uploaded 16 Feb 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameSimco Jyoti - Declaration of bank account.pdf · uploaded 16 Feb 2023Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentSimco Realty OC.pdf · uploaded 5 Oct 2023Source

Technical

  • DocumentPlan Layout.pdf · uploaded 30 Sep 2017Source
  • DocumentDevelopment permission.pdf · uploaded 30 Sep 2017Source

Technical (Architect)

  • DocumentSept 2021_compressed.pdf · uploaded 20 Oct 2021Source

Technical (Engineer)

  • Document7 Sept 2021_compressed.pdf · uploaded 20 Oct 2021Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 137/1, 137/4

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK15 units in all
Address
164/6, 137/1, 137/4, PLOT NO. 11, Citizen Compound, Oswal sagar hall, Juna Agra Road, KamatgharPIN 421302
Village
Bhiwandi (M Corp.), Bhiwandi taluka
Land area for this project
793 sq m (8,535 sq ft)
Permissible built-up area
1,689 sq m (18,178 sq ft)
Sanctioned built-up area
1,597 sq m (17,185 sq ft)
Designated bank account
212
Developed in phases
No

Survey, CTS, gat or plot numbers

137/1137/4164/6PLOT NO. 11

Land as published on MahaRERA's project page

164/6, 137/1, 137/4, PLOT NO. 11

Boundaries

North
Road
South
Open Land
East
Plot No 10
West
Plot No 12

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking15 units

3 of 15 units booked (20%), as the promoter reported to MahaRERA

1BHK · 8 units2BHK · 7 units
TypeCarpet areaUnitsBooked
1BHK41.2 sq m · 443 sq ft82
2BHK54.7 sq m · 589 sq ft71

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals1

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectJalaluddin Moinuddin Ansari—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Kamatghar

All 22 projects in Kamatghar · Compare M/s SIMCO JYOTI with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology