Chavan Star
Deedo IDDP-THN-4M43Completion was pushed back 4 months, to Oct 2027; no MahaRERA orders on record; 22% of its units are booked.
Kalyan, Thane 421301 · by Anjana Sahebrao Chavan, Om Shree Saikrupa Construction
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Oct 2027
- This projectRegistered 29 Oct 2024, completion promised 30 Jun 2027, revised to 30 Oct 2027.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700077757
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700077757 | 29 Oct 2024 | 30 Jun 2027 | 30 Oct 2027 | Om Shree Saikrupa Construction | Project page |
Documents94
1 document held by Deedo, 93 filings listed on MahaRERA's project page
Finance
- PAN CardPANCARD.pdf · uploaded 13 Aug 2024Source
- Other – FinanceCC_Email Snanpshot.pdf · uploaded 7 Oct 2024Source
- OthersDisclosure of Sold and Unsold Inventory.pdf · uploaded 3 Jul 2025Source
- OthersRevised Permission Star.pdf · uploaded 3 Jul 2025Source
- OthersBlank Documents.pdf · uploaded 6 Oct 2025Source
- OthersBlank Documents.pdf · uploaded 6 Oct 2025Source
- OthersBlank Documents.pdf · uploaded 6 Oct 2025Source
Show all 94 documentsShow fewer documents
Finance
- OthersBlank Documents.pdf · uploaded 6 Oct 2025Source
Legal
- Legal Title reportTITLE CERTIFICATE.pdf · uploaded 13 Aug 2024Source
- Declaration Form BFORM B.pdf · uploaded 13 Aug 2024Source
- Other – LegalANNEXURE A.pdf · uploaded 7 Oct 2024Source
- Other – LegalALLOTMENT LETTER.pdf · uploaded 22 Oct 2024Source
- Other – LegalSelf Declaration on Proprietorship.pdf · uploaded 22 Oct 2024Source
Migrated
- 1 PAN CardPANCARD.pdf · uploaded 13 Aug 2024Source
- 1 Copy of the legal title reportTITLE CERTIFICATE.pdf · uploaded 13 Aug 2024Source
- 1 a Details of encumbrances concerned to Financeilovepdf_merged (1).pdf · uploaded 13 Aug 2024Source
- 1 Copy of Layout Approval (in case of layout)SANCTIONED PLAN AND LAYOUT.pdf · uploaded 13 Aug 2024Source
- 1 Declaration in FORM BFORM B.pdf · uploaded 13 Aug 2024Source
- 1 Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT CERTIFICATE.pdf · uploaded 13 Aug 2024Source
- 1 Building Plan Approval / NA Order for plotted developmentSANCTIONED PLAN AND LAYOUT.pdf · uploaded 13 Aug 2024Source
- 1 Declaration about Commencement CertificateDeclaration Commencement Certificate.pdf · uploaded 13 Aug 2024Source
- 1 Declaration about all RERA Designated Bank Accounts (Format A)Bank letter Format A.pdf · uploaded 13 Aug 2024Source
- 1 Deviation Report with respect to Allotment letterDEVIATION ALLOTMENT.pdf · uploaded 13 Aug 2024Source
- 1 b Details of encumbrances concerned to Legalilovepdf_merged (1).pdf · uploaded 13 Aug 2024Source
- 1 Other – TechnicalDeclaration Annexure A.pdf · uploaded 13 Aug 2024Source
- 1 Deviation Report with respect to model copy of AgreementDEVIATION AGGREEMENT.pdf · uploaded 13 Aug 2024Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsDate (3).pdf · uploaded 13 Aug 2024Source
- 1 Disclosure for secured/unsecured finance availed for the projectSecured Unsecured word file.pdf · uploaded 13 Aug 2024Source
- 1 Proforma of Allotment letterAllotment Agreement Final.pdf · uploaded 7 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1_Signed.pdf · uploaded 7 Oct 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 chavan star_Signed_11zon.pdf · uploaded 7 Oct 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form2_Signed_Final.pdf · uploaded 7 Oct 2024Source
- 1 Other – LegalANNEXURE A.pdf · uploaded 7 Oct 2024Source
- 1 Status of Formation of Legal Entity (Society/Co Op etc.)Allotment Agreement Final.pdf · uploaded 7 Oct 2024Source
- 1 Other – FinanceCC_Email Snanpshot.pdf · uploaded 7 Oct 2024Source
- 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)Format_B_Bank Letterhead_Chavan Star_Revised.pdf · uploaded 8 Oct 2024Source
- 2 Other – LegalSelf Declaration on Proprietorship.pdf · uploaded 22 Oct 2024Source
- 3 Other – LegalALLOTMENT LETTER.pdf · uploaded 22 Oct 2024Source
- 2 Status of Formation of Legal Entity (Society/Co Op etc.)ALLOTMENT LETTER.pdf · uploaded 22 Oct 2024Source
- 1 CERSAI detailsUndertaking_CERSAI_Star.pdf · uploaded 22 Oct 2024Source
- 1 Proforma of Agreement for saleAGREEMENT For Sale _Final.pdf · uploaded 22 Oct 2024Source
- 2 Proforma of Agreement for saleALLOTMENT LETTER.pdf · uploaded 22 Oct 2024Source
- Form 1Form_1_ChavanStar.pdf · uploaded 19 May 2025Source
- Form 2Form 2_Chavan_Star.pdf · uploaded 19 May 2025Source
- Form 3Form 3.pdf · uploaded 19 May 2025Source
- Disclosure of Sold and Booked InventoryDisclosure of sold and Book Inventory.pdf · uploaded 19 May 2025Source
- Self-declaration of Quarterly ProgressSelf Declaration_Chavan Star.pdf · uploaded 19 May 2025Source
- Form 1Disclosure of sold and Book Inventory.pdf · uploaded 19 May 2025Source
- Form 2Self Declaration_Chavan Star.pdf · uploaded 19 May 2025Source
- Form 3Form_1_ChavanStar.pdf · uploaded 19 May 2025Source
- Disclosure of Sold and Booked InventoryForm 3.pdf · uploaded 19 May 2025Source
- Self-declaration of Quarterly ProgressForm 2_Chavan_Star.pdf · uploaded 19 May 2025Source
- Withdrawal Update Form 1FORM 1_Signed.pdf · uploaded 3 Jul 2025Source
- Withdrawal Update Form 1FORM 1_Signed.pdf · uploaded 3 Jul 2025Source
- Withdrawal Update Form 2Form2_Signed_Final.pdf · uploaded 3 Jul 2025Source
- Withdrawal Update Form 2Form2_Signed_Final.pdf · uploaded 3 Jul 2025Source
- Withdrawal Update Form 3FORM 3_March_2025.pdf · uploaded 3 Jul 2025Source
- Withdrawal Update Form 3FORM 3_March_2025.pdf · uploaded 3 Jul 2025Source
- Withdrawal Update Form 1FORM_1_STAR_Signed.pdf · uploaded 3 Sep 2025Source
- Withdrawal Update Form 2Form_2_Signed.pdf · uploaded 3 Sep 2025Source
- Withdrawal Update Form 3Withdrawal Application Form3_signed.pdf · uploaded 3 Sep 2025Source
- Withdrawal Update Form 1FORM_1_STAR_Signed.pdf · uploaded 10 Sep 2025Source
- Withdrawal Update Form 1FORM_1_STAR_Signed.pdf · uploaded 10 Sep 2025Source
- Withdrawal Update Form 1FORM_1_STAR_Signed.pdf · uploaded 10 Sep 2025Source
- Withdrawal Update Form 1FORM_1_STAR_Signed.pdf · uploaded 10 Sep 2025Source
- Withdrawal Update Form 2Form_2_Signed.pdf · uploaded 10 Sep 2025Source
- Withdrawal Update Form 2Form_2_Signed.pdf · uploaded 10 Sep 2025Source
- Withdrawal Update Form 2Form_2_Signed.pdf · uploaded 10 Sep 2025Source
- Withdrawal Update Form 2Form_2_Signed.pdf · uploaded 10 Sep 2025Source
- Withdrawal Update Form 3Withdrawal Application Form3_signed.pdf · uploaded 10 Sep 2025Source
- Withdrawal Update Form 3Withdrawal Application Form3_signed.pdf · uploaded 10 Sep 2025Source
- Withdrawal Update Form 3Withdrawal Application Form3_signed.pdf · uploaded 10 Sep 2025Source
- Withdrawal Update Form 3Withdrawal Application Form3_signed.pdf · uploaded 10 Sep 2025Source
- Withdrawal Update Form 1Form_1_Chavan Star_30_09_2025_Final.pdf · uploaded 12 May 2026Source
- Withdrawal Update Form 1Form_1_Chavan Star_31_12_2025_Sign.pdf · uploaded 12 May 2026Source
- Withdrawal Update Form 2Form_2_Star_Sep_2025.pdf · uploaded 12 May 2026Source
- Withdrawal Update Form 2Chavan Star Form -2 Dec-25.pdf · uploaded 12 May 2026Source
- Withdrawal Update Form 3Form 3_Chavan Star_30_09_2025_Final.pdf · uploaded 12 May 2026Source
- Withdrawal Update Form 3Form_1_Chavan Star_31_12_2025_Sign.pdf · uploaded 12 May 2026Source
- Withdrawal Update Form 1Form_1_Star_31_03_2026.pdf · uploaded 9 Jun 2026Source
- Withdrawal Update Form 2Form-2 Star_31_03_2026.pdf · uploaded 9 Jun 2026Source
- Withdrawal Update Form 3Form3_Star_31_03_2026_New.pdf · uploaded 9 Jun 2026Source
- Form 5 (FY 2024-2025)Form 5 CHAVAN STAR Signed.pdf · uploaded 18 Jun 2026Source
- Form 2A (FY 2024-2025)Form 2A_Chavan_Star_31_03_2025.pdf · uploaded 6 Jul 2026Source
- Form 2A (FY 2025-2026)Form 2A_31_03_2026.pdf · uploaded 6 Jul 2026Source
- Form 5 (FY 2025-2026)Form_5_CHAVAN_STAR_31_03_2026.pdf · uploaded 6 Jul 2026Source
Technical
- DocumentSANCTIONED PLAN AND LAYOUT.pdf · uploaded 13 Aug 2024Source
- Other – TechnicalDeclaration Annexure A.pdf · uploaded 13 Aug 2024Source
- DocumentPLANS.pdf · uploaded 3 Jul 2025Source
- OthersPLANS.pdf · uploaded 3 Jul 2025Source
- OthersPLANS.pdf · uploaded 3 Jul 2025Source
- DocumentPLANS.pdf · uploaded 3 Sep 2025Source
Technical (Architect)
- DocumentForm_1_Star_31_03_2026.pdf · uploaded 5 Jun 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel H.No. 2/A, S. No.80
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- —76 units in all
- Address
- S. No.80, H.No. 2/A, Beturkar Pada, Next to MSEB officePIN 421301
- Village
- Kalyan, Kalyan taluka
- Location
- 19.26176, 73.13359
- Designated bank account
- 76
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- Survey No 79
- South
- Survey No 84
- East
- Survey No 86 2
- West
- 60ft Wide Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking76 units
76 units registered
| Type | Carpet area | Units |
|---|---|---|
| — | — | 76 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals1
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Up Creation | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Kalyan
- Heena HeightsRERA PR1331012602459
- Vighnaharta ApartmentRERA PR1330002602354
- Vakratund Residency-1RERA PM1330002602265
- Seasons MannatRERA PM1331012601752
- Sarvoday AfrozRERA PR1330002601328
- Santosshi AvenueRERA PM1330002600839
- Gayatri SamarthRERA P51700081125
- New Chaitanya PrabhaRERA PR1330002600047
All 176 projects in Kalyan · Compare Chavan Star with another project