Deedo IDDP-THN-5H0VCompletion was pushed back 4 months, to Apr 2028; no MahaRERA orders on record; 14% of its units are booked.
Gandhare, Thane 421301 · by V V Construction Co
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2028
- This projectRegistered 14 Aug 2023, completion promised 31 Dec 2027, revised to 30 Apr 2028.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700052343
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700052343 | 14 Aug 2023 | 31 Dec 2027 | 30 Apr 2028 | V V Construction Co | Project page |
Documents77
1 document held by Deedo, 76 filings listed on MahaRERA's project page
Legal
Migrated
- 1 PAN Cardpan card of firm.pdf · uploaded 13 Jan 2023Source
- 1 Copy of Layout Approval (in case of layout)PLAN LAYOUT.pdf · uploaded 13 Jan 2023Source
- 1 Building Plan Approval / NA Order for plotted developmentPLAN LAYOUT.pdf · uploaded 13 Jan 2023Source
- 1 Commencement Certificates / NA Order for plotted developmentKDMC CC VV construction CO_compressed.pdf · uploaded 13 Jan 2023Source
Show all 77 documentsShow fewer documents
Migrated
- 1 Declaration about Commencement CertificateDECLARATION OF COMMENCE.pdf · uploaded 13 Jan 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)vv construction co architect certificate LATEST.pdf · uploaded 13 Jan 2023Source
- 1 Deviation Report with respect to Allotment letterDEVIATION ALLOTMENT.pdf · uploaded 13 Jan 2023Source
- 1 Deviation Report with respect to model copy of AgreementDEVIATION AGREEMENT.pdf · uploaded 13 Jan 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)vv construction co engineer’s certificate.pdf · uploaded 16 Jan 2023Source
- 1 Declaration in FORM Bform b.pdf · uploaded 26 Jan 2023Source
- 1 Proforma of Agreement for saleAGREEMENT FOR SALES LATEST.pdf · uploaded 26 Jan 2023Source
- 1 Copy of the legal title reportvv title NEW.pdf · uploaded 29 Mar 2023Source
- 1 Disclosure of Interest in Other Real Estate Organizationspartner rera.pdf · uploaded 23 May 2023Source
- 1 Proforma of Allotment letter01 model of allotment new format.pdf · uploaded 23 May 2023Source
- 2 PAN CardNAME CHANGE DEED.pdf · uploaded 25 May 2023Source
- 2 Copy of the legal title reportNAME CHANGE DEED.pdf · uploaded 25 May 2023Source
- 1 a Details of encumbrances concerned to FinanceLEGAL FINAL.pdf · uploaded 30 May 2023Source
- 1 b Details of encumbrances concerned to LegalLEGAL FINAL.pdf · uploaded 30 May 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 VVCons_compressed.pdf · uploaded 30 May 2023Source
- 2 a Details of encumbrances concerned to FinanceFinancial encumbranmces.pdf · uploaded 4 Aug 2023Source
- 2 b Details of encumbrances concerned to LegalFinancial encumbranmces.pdf · uploaded 4 Aug 2023Source
- 1 CERSAI detailsCERSAI.pdf · uploaded 4 Aug 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBank declaration.pdf · uploaded 4 Aug 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 Q2 2023-24.pdf · uploaded 23 Jan 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 Q3 2023-24.pdf · uploaded 23 Jan 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 Q2.pdf · uploaded 7 Feb 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 Q3.pdf · uploaded 7 Feb 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 Q2.pdf · uploaded 7 Feb 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 Q3.pdf · uploaded 7 Feb 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1.pdf · uploaded 18 Jun 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2.pdf · uploaded 18 Jun 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)v v construc co-1_FORM 3.pdf · uploaded 18 Jun 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)VV CONSTRUCTION CO FORM -1 ( 2-7-24).pdf · uploaded 22 Nov 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)VV CONSTRUCTION CO FORM-1 (2-10-24).pdf · uploaded 22 Nov 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)V V construction q1_UPLOAD.pdf · uploaded 22 Nov 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)V V construction q2_UPLOAD.pdf · uploaded 22 Nov 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)VV CONSTRUCTION CO FORM -2 (6-7-24).pdf · uploaded 22 Nov 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)VV CONSTRUCTION CO FORM-2 (6-10-24) (1).pdf · uploaded 22 Nov 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)form 5 upload.pdf · uploaded 30 Nov 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)vvc - form 1 (1-1-25).pdf · uploaded 16 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 UPLOAD.pdf · uploaded 16 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)vvc form 2 (5-1-25).pdf · uploaded 16 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)(1-4-25) Form 1.pdf · uploaded 7 May 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 7 May 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)5-4-25 (1) Form 2.pdf · uploaded 7 May 2025Source
- Withdrawal Update Form 1Form 1.pdf · uploaded 19 Jul 2025Source
- Withdrawal Update Form 2Form 2.pdf · uploaded 19 Jul 2025Source
- Withdrawal Update Form 3Form 3.pdf · uploaded 19 Jul 2025Source
- Form 5 (FY 2024-2025)V V construction FORM 5.pdf · uploaded 27 Nov 2025Source
- Withdrawal Update Form 1FORM 1.pdf · uploaded 31 Dec 2025Source
- Withdrawal Update Form 2form 2.pdf · uploaded 31 Dec 2025Source
- Withdrawal Update Form 3form 3 uploaded.pdf · uploaded 31 Dec 2025Source
- Withdrawal Update Form 1FORM-1.pdf · uploaded 27 Feb 2026Source
- Withdrawal Update Form 2FORM-2.pdf · uploaded 27 Feb 2026Source
- Withdrawal Update Form 3form 3.pdf · uploaded 27 Feb 2026Source
- Withdrawal Update Form 1FORM 1.pdf · uploaded 18 May 2026Source
- Withdrawal Update Form 2FORM 2.pdf · uploaded 18 May 2026Source
- Withdrawal Update Form 3VV CONSTRUCTION FORM 3 FINAL.pdf · uploaded 18 May 2026Source
- Withdrawal Update Form 1626 form 1.pdf · uploaded 5 Oct 2026Source
- Withdrawal Update Form 2626 form 2.pdf · uploaded 5 Oct 2026Source
- Withdrawal Update Form 3FORM 3 MERGED.pdf · uploaded 5 Oct 2026Source
Technical
Technical (Architect)
- DocumentVV CONSTRUCTION CO FORM -1 ( 2-7-24).pdf · uploaded 22 Nov 2024Source
- DocumentVV CONSTRUCTION CO FORM-1 (2-10-24).pdf · uploaded 22 Nov 2024Source
- Documentvvc - form 1 (1-1-25).pdf · uploaded 16 Jan 2025Source
- Document(1-4-25) Form 1.pdf · uploaded 7 May 2025Source
- Document626 form 1.pdf · uploaded 5 Oct 2026Source
Technical (Engineer)
- DocumentVV CONSTRUCTION CO FORM -2 (6-7-24).pdf · uploaded 22 Nov 2024Source
- DocumentVV CONSTRUCTION CO FORM-2 (6-10-24) (1).pdf · uploaded 22 Nov 2024Source
- Documentvvc form 2 (5-1-25).pdf · uploaded 16 Jan 2025Source
- Document5-4-25 (1) Form 2.pdf · uploaded 7 May 2025Source
- Document626 form 2.pdf · uploaded 5 Oct 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel SURVEY NO. 26
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- —14 units in all
- Address
- Survey No. 26, Gandhare Road, GandharePIN 421301
- Village
- Gandhare, Kalyan taluka
- Location
- 19.25535, 73.13634
- Land area for this project
- 300 sq m (3,229 sq ft)
- Permissible built-up area
- 921 sq m (9,915 sq ft)
- Sanctioned built-up area
- 921 sq m (9,915 sq ft)
- Designated bank account
- 196
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
SURVEY NO. 26
Boundaries
- North
- Survey No 26
- South
- 6 Meter Wide Layout Road
- East
- Plot No 42
- West
- Plot No 45
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking14 units
14 units registered
| Type | Carpet area | Units |
|---|---|---|
| — | — | 14 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Dhiraj Bharat Patil | — |
| Chartered accountant | Kapil Khandelwal | — |
| Chartered accountant | Nitin P Kothari | — |
| Engineer | Ganesh Pandit Patil | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Gandhare
- Laxmi PrideRERA PM1330002601856
- Mangeshi CrownRERA PM1330002600843
- Mahaveer SignatureRERA PM1330002600522
- Vedant MayfairRERA PR1330002502871
- Kanchanjunga CHSRERA PM1330002502382
- ShivalayRERA PR1330002502383
- Time SquareRERA PM1330002501475
- Mohan PrestigeRERA PM1330002501005
All 51 projects in Gandhare · Compare Tulsi Palace with another project